SHIVDARSHAN

By MANAS GROUP

RG-MH-31829 · RERA P52000080153 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 9 months from the original
1 of 11Construction stages donefurthest along: Podiums (if any), 90%
101 of 108Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

SHIVDARSHAN is a Others project by MANAS GROUP in Raigarh, Maharashtra, registered with MahaRERA as P52000080153 on 2 May 2025. Possession is promised by 31 Dec 2028. The completion date has moved by 9 months from the original filing. 7 of the 108 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHIVDARSHAN
  • TypeOthers
  • Location
    • SECTOR 20
    • NEW PANVEL EAST
    • New Panvel
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000080153
  • ReraGenie IDRG-MH-31829

Builder

  • NameMANAS GROUP
  • Entity typePartnership
  • PartnersSUJEET SUBHASH THORAT, SUBASH MARUTI THORAT, SHANKAR SHIMGYA PATIL, ANAND SHANKAR CHOUGLE, RAJENDRA BARIKRAO THORAT, MANISHA GANGARAM SAWANT, SOMNATH MANGLYA DEVKAR, PRASHANT SUBHASH THORAT, VISHAL VILAS JAIN
  • Other registrations2 more →

Key dates

this monthRegisteredMay 2025First promiseMar 2028Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 May 2025
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 31 Mar 2028)
  • Buildings1 building record
  • Documents filed70 files

Current status

6%7 of 108 units booked
17.2%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHIV DARSHANNA13118919108

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 90%.

SHIV DARSHAN: 34% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)90%
Plinth90%
Stilt Floor90%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed188

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots188
Closed/Covered188

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,549 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPanvel Municipal Corporation
Permissible FSI8631.76
Proposed, not sanctioned8,615 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWARDEN HOUSE,PLOT NO 65 SECTOR 11,CBD BELAPUR NAVI MUMBAI,DISTTHANE
Estimated costRs 40.18 cr
Cost incurredRs 6.90 cr
Work done17.17%
BuildingWingEstimatedIncurred
SHIV DARSHANNARs 36.32 crRs 6.90 cr
-NARs 3.86 cr-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDIMENSIONS ARCHITECTS PVT LTD
EngineerSHRAVANI CONSLUTANTS
EngineerVISHAL Anand Thakur
Chartered AccountantD P SHEJWAL AND ASSOCIATES
PartnerRole in project
MANAS GROUP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA29052621148Mar 2028 → Dec 2028

Reason as filed by the promoter1) Poor booking response from customer. 2) Because of poor response our work was very slow.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Apr 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Feb 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Feb 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Shivdarshan 30-06-2026.pdf20 Jul 2026
Withdrawal Update Form 2File: Form 2 Shivdarshan 30-06-2026.pdf20 Jul 2026
Withdrawal Update Form 3File: Form 3 Shivdarshan 30-06-2026 sign.pdf20 Jul 2026
Withdrawal Update Form 1File: Form 1 31-03-2026.pdf22 Apr 2026
Withdrawal Update Form 2File: Form 2 31-03-2026.pdf22 Apr 2026
Withdrawal Update Form 3File: Form 3 31-03-2026 Shivdarshan Sign_.pdf22 Apr 2026
Form 2A (FY 2025-2026)File: Form 2A Shivdarshan 25-26 Sign.pdf18 Feb 2026
Layout approvalFile: updated plan cum blue print.pdf10 Feb 2026
Building plan approvalFile: updated plan cum blue print.pdf10 Feb 2026
Withdrawal Update Form 1File: 002 Form -1 plot -18 ( shivdarshan) Q-3 FY25-26.pdf9 Feb 2026
Withdrawal Update Form 2File: FORM -2 25-26 Q - 3 New.pdf9 Feb 2026
Withdrawal Update Form 3File: Form 3 Shivdarshan 31-12-2025 Sign_1.pdf9 Feb 2026
Withdrawal Update Form 1File: form (1) shivDarshan.pdf6 Jan 2026
Withdrawal Update Form 2File: Form (2) Shiv Darshan.pdf6 Jan 2026
Withdrawal Update Form 3File: Form 3 30-09-2025 Shivdarshan_.pdf6 Jan 2026
Withdrawal Update Form 1File: Form -1 30-06-25.pdf30 Sep 2025
Withdrawal Update Form 2File: Form -2 30-06-25.pdf30 Sep 2025
Withdrawal Update Form 3File: Form 3 - 30-06-25.pdf30 Sep 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MANAS FORM 3 SIGNED - converted.pdf25 Apr 2025
Other - LegalFile: CANCELLATION DEED 02.pdf18 Apr 2025
Other - LegalFile: CANCELLATION DEED 01.pdf18 Apr 2025
Other - LegalFile: 9 Other - Legal_01 (30 files merged).pdf18 Apr 2025
Other - TechnicalFile: ANNEXURE A.pdf18 Apr 2025
Layout approvalFile: PLAN 1.pdf17 Apr 2025
Layout approvalFile: PLAN 2.pdf17 Apr 2025
Layout approvalFile: PLAN 3.pdf17 Apr 2025
Layout approvalFile: PLAN 4.pdf17 Apr 2025
Layout approvalFile: PLAN 5.pdf17 Apr 2025
Building plan approvalFile: PLAN 1.pdf17 Apr 2025
Building plan approvalFile: PLAN 2.pdf17 Apr 2025
Building plan approvalFile: PLAN 3.pdf17 Apr 2025
Building plan approvalFile: PLAN 4.pdf17 Apr 2025
Building plan approvalFile: PLAN 5.pdf17 Apr 2025
Copy of Layout Approval (in case of layout)File: PLAN 1.pdf17 Apr 2025
Copy of Layout Approval (in case of layout)File: PLAN 2.pdf17 Apr 2025
Copy of Layout Approval (in case of layout)File: PLAN 3.pdf17 Apr 2025
Copy of Layout Approval (in case of layout)File: PLAN 4.pdf17 Apr 2025
Copy of Layout Approval (in case of layout)File: PLAN 5.pdf17 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN 1.pdf17 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN 2.pdf17 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN 3.pdf17 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN 4.pdf17 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN 5.pdf17 Apr 2025
Other - LegalFile: AGREEMENT TO LEASE_03.pdf17 Apr 2025
Other - LegalFile: TP 04.pdf17 Apr 2025
Other - LegalFile: TP 03.pdf17 Apr 2025
Other - LegalFile: TP 01.pdf17 Apr 2025
Other - LegalFile: AGREEMENT TO LEASE_04.pdf17 Apr 2025
Other - LegalFile: AGREEMENT TO LEASE_02.pdf17 Apr 2025
Other - LegalFile: AGREEMENT TO LEASE_01.pdf17 Apr 2025
Other - LegalFile: TP 02.pdf17 Apr 2025
Other - TechnicalFile: CC MAIL.pdf17 Apr 2025
Deviation Report with respect to model copy of AgreementFile: 1 Deviation Report with respect to model copy of Agreement (14)_1 (5 files merged).pdf17 Apr 2025
Copy of the legal title reportFile: LEGAL TITLE REPORT PLOT-18 - converted.pdf10 Apr 2025
Details of encumbrances concerned to FinanceFile: No encumbrances finances and legal.pdf10 Apr 2025
Proforma of Allotment letterFile: ALLOTMENT DRAFT.pdf10 Apr 2025
Declaration in FORM BFile: Form B.pdf10 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf10 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf10 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: COMM CERT.pdf10 Apr 2025
Declaration about Commencement CertificateFile: declaration about commencement certificate.pdf10 Apr 2025
CERSAI detailsFile: Cersai declaration.pdf10 Apr 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf10 Apr 2025
Deviation Report with respect to Allotment letterFile: DEVIATION- ALLOTMENT.pdf10 Apr 2025
Details of encumbrances concerned to LegalFile: No encumbrances finances and legal.pdf10 Apr 2025
Proforma of Agreement for saleFile: sale agreement draft.pdf10 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf10 Apr 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B NEW.pdf10 Apr 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured_unsecured finance.pdf10 Apr 2025
PAN CardFile: PAN Card.pdf9 Apr 2025

How this compares with Raigarh

6%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 9 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHIVDARSHAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEW PANVEL EAST5,900+ in Raigarh

2 kmSHIVDARSHANCompleted 131Lapsed / revoked 41Other 92Dot size: filed unitsN

Filed coordinates, straight-line distance. 264 registered projects within 2 km.

Builder: MANAS GROUP

MANAS GROUP has 3 registrations on MahaRERA, including MAULI and VITHUMAULI. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if SHIVDARSHAN is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHIVDARSHAN?

The registered promoter entity is MANAS GROUP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHIVDARSHAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHIVDARSHAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHIVDARSHAN?

The professionals named in the filing: Architect: DIMENSIONS ARCHITECTS PVT LTD; Engineer: SHRAVANI CONSLUTANTS; Engineer: VISHAL Anand Thakur; Chartered Accountant: D P SHEJWAL AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIVDARSHAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIVDARSHAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIVDARSHAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.