SHIVAM HERITAGE
RG-MH-20153 · RERA P52100014187 · Last updated on MahaRERA portal: 11 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 101 months
- 5 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHIVAM HERITAGE is a Residential / Group Housing project by VASTUSHREE DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100014187 on 14 Nov 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 101 months from the original filing. 19 of the 27 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.
At a glance
Project
- NameSHIVAM HERITAGE
- TypeResidential / Group Housing
- Location
- -
- Bhugaon
- Mulshi
- Pune
- 421115
- Pincode421115
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100014187
- ReraGenie IDRG-MH-20153
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on14 Nov 2017
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 1 Jul 2019)
- Buildings1 building record
- Documents filed187 files
Current status
Figures as on 11 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHIVAM HERITAGE | NA | 7 | 4 | 27 | 0 | 27 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 11 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.
SHIVAM HERITAGE: 80% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 11 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 95% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 70% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 80% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 90% |
| Water conservation /Rain water harvesting | Yes | 85% |
| Energy managemcnt | Yes | 80% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 90% |
Parking filed2
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Sandip Balasaheb Ingavale | Bhugaon | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SHIVAM HERITAGE | NA | Rs 4.36 cr | Rs 3.85 cr |
| - | NA | Rs 4.36 cr | Rs 3.85 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Walhekar Associates |
| Architect | S.D Walhekar |
| Engineer | Rohinee Badgujar |
| Chartered Accountant | Eknath Agale |
| Chartered Accountant | Shivraj Jagtap |
| Partner | Role in project |
|---|---|
| VASTUSHREE DEVELOPERS | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe application for additional amenity space is already applied and under process. Because of that the overall execution will get extended to 30th Sept, 2020.
Reason as filed by the promoterThe Project tenure got extended because of administrative process and other procedures documentation with PMRDA due to present pandemic situation arises due to Covid 19.
Reason as filed by the promoterFirm has submitted all the documents with respect to MOD and amenity space handover which is awaited from PMRDA authority hence extension needed.
Reason as filed by the promoterLOCAL AUTHORITY DEALY CERTIFICATE
Reason as filed by the promoterWe had completed 90% Development Work , However external development work that is approach road , water supply by Local Authorities are delayed due to policy and plan change. Essential Infrastructure is expected to complete after current monsoon season. We need time to complete the pending work and complete OC and Conveyance Procedures. We had given fair idea to our customer and got full consent from them
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Oct 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 14 Oct 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 14 Oct 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed187
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 187 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1.pdf | 11 Aug 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 11 Aug 2026 |
| Withdrawal Update Form 3File: CA Certificate.pdf | 11 Aug 2026 |
| Declaration in FORM BFile: Adobe Scan 03-May-2025 (5).pdf | 13 May 2025 |
| Declaration about Commencement CertificateFile: Declaration Commencement (1) (1).pdf | 13 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: shivam heritagr form 1.pdf | 22 Apr 2025 |
| Certificates of CA (Form 3)File: VASTUSHREE form 3.pdf | 22 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: shivam heritage form 2.pdf | 22 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: 29 Disclosure of sold_ booked inventory (1).pdf | 22 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: 29 Disclosure of sold_ booked inventory (2).pdf | 22 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Er Shivam Heritage.pdf | 2 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: NARAYAN SHINDE.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: fORM 3.pdf | 1 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SHIVAM HERITAGE.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: G S Devlopers Rera form scan copy octobar 24 _page-0001_11zon.pdf | 22 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Adobe Scan Dec 11, 2024 (4).pdf | 12 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf | 21 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 21 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Shivam Heritage Form 2 Sep.pdf | 21 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Sold unsold.pdf | 21 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 21 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Shivam Heritage Form 2 Sep.pdf | 21 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Sold unsold.pdf | 21 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf | 21 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: F2A (2).pdf | 8 Aug 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured unsecured finance availed for the project.pdf | 29 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Rohidas Shinde.pdf | 29 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A narayan Shinde.pdf | 29 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure a - Suresh Jape.pdf | 29 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Prakash kadam.pdf | 29 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: signed form 1.pdf | 13 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: signed Form 2.pdf | 13 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: signed sold unsold.pdf | 13 Jul 2024 |
| Certificates of CA (Form 3)File: signed Form 3.pdf | 13 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: signed f5 1.pdf | 13 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: signed f5 1.pdf | 13 Jul 2024 |
| Certificates of CA (Form 3)File: Form3 (1)_compressed.pdf | 9 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 28 Certificates of Architect (Form 1)(Mandatory for only ongoing project) (1).pdf | 2 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30 Certificates of Engineer (Form 2)(Mandatory for only ongoing project) (1).pdf | 2 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: 26 Disclosure of sold_ booked inventory (1).pdf | 2 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: shivam heritage (1).pdf | 10 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 27 Certificates of Architect (Form 1)(Mandatory for only ongoing project) (1).pdf | 3 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 28 Certificates of Engineer (Form 2)(Mandatory for only ongoing project) (1).pdf | 3 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: 25 Disclosure of sold_ booked inventory (1).pdf | 3 Jan 2024 |
| Certificates of CA (Form 3)File: 33 Certificates of CA (Form 3) (1).pdf | 3 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3 Vastushree Devlopers sept 2023.pdf | 31 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ilovepdf_merged (38).pdf | 20 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 July 2019.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 April 2018.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 Dec 2017.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 Oct 2017.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 July 2017.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 July 2018.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 Dec 2018.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 March 2019.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 July 2019.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 Sep 2019.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 Dec 2019.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 March 2020.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 June 2020.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 Sep 2020.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 Dec 2020.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 MArch 2021.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 July 2021.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 Sep 2021.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 Dec 2021.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 March 2022.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 June 2022.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 Sep 2023.pdf | 12 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2017.pdf | 12 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2018.pdf | 12 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2019.pdf | 12 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2020.pdf | 12 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2022.pdf | 12 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: S U june 2021.pdf | 12 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: S U Dec 2017.pdf | 12 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: S U March 2018.pdf | 12 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: S U June 2018.pdf | 12 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: S U Oct 2018.pdf | 12 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: S U Dec 2018.pdf | 12 Oct 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 187 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SHIVAM HERITAGE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bhugaon13,700+ in Pune
Filed coordinates, straight-line distance. 43 registered projects within 2 km.
Godrej Ivara
Manjari Housing Projects LLP
CANARY FARMS
CANARY FARMS
Godrej Evergreen Square
Godrej Projects Development Limited
The Aqua Retreat at Godrej Park World
Maan-Hinje Township Developers Private Lim
TANISH PARK
TANISH DEVELOPERS
Godrej Aqua Vista
Oxford Realty LLP
Builder: VASTUSHREE DEVELOPERS
VASTUSHREE DEVELOPERS has 3 registrations on MahaRERA, including SHIVAM HERITAGE and VASTUSHREE DIONA PHASE I RESIDENTIAL WING A and COMMERCIAL. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if SHIVAM HERITAGE is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHIVAM HERITAGE?
The registered promoter entity is VASTUSHREE DEVELOPERS, a partnership as per the filing. Its GSTIN 27AALFV2307E1ZA can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHIVAM HERITAGE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHIVAM HERITAGE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHIVAM HERITAGE?
The professionals named in the filing: Architect: Walhekar Associates; Architect: S.D Walhekar; Engineer: Rohinee Badgujar; Chartered Accountant: Eknath Agale; Chartered Accountant: Shivraj Jagtap. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHIVAM HERITAGE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback