Home / Browse projects / Sangli, Maharashtra / Shivalay
Shivalay
RG-MH-40360 · RERA P53100050271 · Last updated on MahaRERA portal: 14 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 3 months past the filed date
- Completion date moved by 28 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Shivalay is a Residential / Group Housing project by SUKHKARTA DEVELOPERS in Sangli, Maharashtra, registered with MahaRERA as P53100050271 on 31 Mar 2023. Possession was promised by 31 Jul 2026 and is now 3 months past that date. The completion date has moved by 28 months from the original filing. 9 of the 20 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.
At a glance
Project
- NameShivalay
- TypeResidential / Group Housing
- Location
- C.S.No. 10549
- Nishant Colony- Sangli
- Sangli Miraj Kupwad (M Corp.)
- Miraj
- Sangli
- 416416
- Pincode416416
- MapView location on Google Maps (as filed on RERA)
- RERA no.P53100050271
- ReraGenie IDRG-MH-40360
Builder
- NameSUKHKARTA DEVELOPERS
- Entity typePartnership
- PartnersPrakash Laxmanrao Patil, Vishal Vasantrao Patil, Ravindra Shivaji Mohite, Geetali Ravindra Mohite
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on31 Mar 2023
- Promised completion31 Jul 2026
- Revised completionRevised to 31 Jul 2026 (originally 31 Mar 2024)
- Buildings1 building record
- Documents filed91 files
Current status
Figures as on 14 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Shivalay | NA | 8 | 7 | 20 | 0 | 20 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 14 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.
Shivalay: 61% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 65% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 40% |
Progress on shared amenities15
As on 14 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 70% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 25% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed79
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership6
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Vandana Chandrashekhar Kulkarni | Sangli Miraj Kupwad (M Corp.) | Sangli |
| Sagar Chandrashekhar Kulkarni | Sangli Miraj Kupwad (M Corp.) | Sangli |
| Sayali Vikrant Killedar | jaysingpur | Kolhapur |
| Sonali Naveen Lohana | Sangli Miraj Kupwad (M Corp.) | Sangli |
| Ujwala Balasaheb Kulkarni | Sangli Miraj Kupwad (M Corp.) | Sangli |
| Priyank Balasaheb Kulkarni | Sangli Miraj Kupwad (M Corp.) | Sangli |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Shivalay | NA | Rs 2.08 cr | Rs 1.76 cr |
| - | NA | Rs 23.06 lakh | Rs 12.50 lakh |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Prakash L Patil |
| Engineer | Makarand M Shinde |
| Engineer | Rudraksha Construction |
| Engineer | Vaibhv Prakash Swami |
| Chartered Accountant | Ms R K Kale and associates |
| Chartered Accountant | D V Patil and Co |
| Chartered Accountant | N B Sayed & Associates |
| Chartered Accountant | Gaurav Satish Rajpal |
| Partner | Role in project |
|---|---|
| SUKHKARTA DEVELOPERS | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.
Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.
Reason as filed by the promoter1. The project stands at 99% completion. 2. The consent of 100% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaining completion work is uploaded in the Application. 5. The Project got delayed due to following reasons:- a) Unfavourable market conditions impacted sales, cash flow, and project scheduling. b) Financial constraints caused delays in procurement and construction activities. c) Shortage of skilled labour and construction materials affected project progress. d) Increased post-pandemic labour and construction costs create
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 Mar 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Mar 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 May 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed91
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 91 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: 7d68291c-4fd4-4967-aff6-6be0c9064eae.pdf | 14 Jul 2026 |
| Form 2A (FY 2022-2023)File: form 2A shivalay 2022-23.pdf | 13 Jul 2026 |
| Form 5 (FY 2022-2023)File: FORM 5 22-23 SHIVALAY.pdf | 13 Jul 2026 |
| Form 2A (FY 2023-2024)File: FORM 2A 23-24 SHIVALAY.pdf | 11 Jul 2026 |
| Withdrawal Update Form 1File: form 1 shivalay.pdf | 8 Jul 2026 |
| Withdrawal Update Form 2File: form 2 shivalay.pdf | 8 Jul 2026 |
| Withdrawal Update Form 3File: form 3 shivalay.pdf | 8 Jul 2026 |
| Form 5 (FY 2025-2026)File: FORM 5 2025-26.pdf | 9 Jun 2026 |
| Building plan approvalFile: Shivalay New Plan1.pdf | 26 May 2026 |
| Form 2A (FY 2025-2026)File: 2A 2025-26.pdf | 25 May 2026 |
| Withdrawal Update Form 1File: Shivalay Form 1 Architect Certifcate Q4 March 2026.pdf | 4 May 2026 |
| Withdrawal Update Form 2File: Shivalay Form 2 Engineer Certificate Q4 March 2026.pdf | 4 May 2026 |
| Withdrawal Update Form 3File: Shivalay Form 3 CA Cerificate Q4 March 2026.pdf | 4 May 2026 |
| Form 5 (FY 2024-2025)File: Form-5_ Shivalay_2025.pdf | 11 Feb 2026 |
| Form 5 (FY 2023-2024)File: Form - 5 Shivalay_2023-24.pdf | 11 Feb 2026 |
| Withdrawal Update Form 1File: Form 1_Shivalay_Dec 25.pdf | 10 Feb 2026 |
| Withdrawal Update Form 2File: Form 2_Shivalay_Dec 25.pdf | 10 Feb 2026 |
| Withdrawal Update Form 3File: Form 3_Shivalay_Dec 25.pdf | 10 Feb 2026 |
| Withdrawal Update Form 1File: Form -1 Sukh_Sep 25.pdf | 31 Oct 2025 |
| Withdrawal Update Form 2File: Form 2_Sukh_Sep 25.pdf | 31 Oct 2025 |
| Withdrawal Update Form 3File: Form 3_Sukh_Sep 25.pdf | 31 Oct 2025 |
| Withdrawal Update Form 1File: Form 1 Shivalay Jun 25.pdf | 21 Aug 2025 |
| Withdrawal Update Form 2File: Form - 2 Shivalay Jun 25.pdf | 21 Aug 2025 |
| Withdrawal Update Form 3File: Form 3_Shivalay_Jun 25.pdf | 21 Aug 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Shiv_Mar 25.pdf | 26 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sukh Form 3 Mar 25-compressed.pdf | 26 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Shiv_Mar 25.pdf | 26 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory_Shiv_Mar 25.pdf | 26 Apr 2025 |
| Declaration in FORM BFile: P53100050271_FileName_4.pdf | 7 Apr 2025 |
| Other - TechnicalFile: PERT shivalay.pdf | 7 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Shivalay Form 2A.pdf | 7 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Shivalay Form 5.pdf | 7 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2023-24.pdf | 2 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Circular 29.pdf | 2 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Sukh_Dec 24.pdf | 25 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sukh Dec 24-compressed.pdf | 25 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Sukh_Dec 24.pdf | 25 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory Sukh_Dec 24.pdf | 25 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_Shivalay_Mar 2024.pdf | 30 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Shivalay_Sep 24.pdf | 29 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Shivalay_Sep 24.pdf | 28 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Shivalay_ Sep 24.pdf | 28 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory_ Shivalay_ Sep 24.pdf | 28 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SK_FORM 1_JUNE 24.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SK_FORM 2_JUNE 24.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: SK_UNSOLD INVENTORY_JUNE 24.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SK_FORM 3_JUNE 24.pdf | 20 Jul 2024 |
| Declaration in FORM BFile: Shivalay Form B.pdf | 24 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Circular 29.pdf | 24 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1_Shivalay_Mar 24.pdf | 21 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2_Shivalay_Mar 24.pdf | 21 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory_Shivalay_Mar 24.pdf | 21 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3_Shivalay_Mar 24.pdf | 21 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Shivalay_Dec23 (1).pdf | 20 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Sukh_Dec 23_11zon.pdf | 16 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Sukh_Dec23_11zon.pdf | 16 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Shivalay.pdf | 26 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shiv Form 1 Sep 23.pdf | 17 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shiv Form 2 Sep 23.pdf | 17 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shiv Sep 23_compressed.pdf | 17 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5- Shivalay as on 2022-23.pdf | 5 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shivalay Form 1 Jun 23.pdf | 21 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shivalay Form 2 Jun 23.pdf | 21 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shivalay Form 3 Jun 23_compressed.pdf | 21 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 3_Shiv_Q4_Mar 23_compressed.pdf | 24 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Shiva_Q4_Mar 23.pdf | 24 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 3_Shiv_Q4_Mar 23_compressed.pdf | 24 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sukh_Engg_Q4_Mar 23.pdf | 24 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Shiv_Q4_Mar 23_compressed.pdf | 24 May 2023 |
| Declaration in FORM BFile: Form B - Firm.pdf | 23 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shivalay Architect Letter.pdf | 23 Mar 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Merged_compressed.pdf | 23 Mar 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seperate Bank Account.pdf | 23 Mar 2023 |
| Deviation Report with respect to Allotment letterFile: Deviation Report Of Allotment Letter.pdf | 23 Mar 2023 |
| Layout approvalFile: Shivalay Sanction Plan_Compressed.pdf | 16 Mar 2023 |
| Building plan approvalFile: Shivalay Sanction Plan_Compressed.pdf | 16 Mar 2023 |
| PAN CardFile: Firm Pan (Sukhakarta).pdf | 16 Mar 2023 |
| Copy of the legal title reportFile: SHIVALAY TITLE CERT.pdf | 16 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: No Encumbrane Letter Dues.pdf | 16 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: No Encumbrance Letter Litigations.pdf | 16 Mar 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sangli
Computed across the 790+ Sangli projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 91 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Shivalay on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Nishant Colony- Sangli790+ in Sangli
Filed coordinates, straight-line distance. 144 registered projects within 2 km.
SIDDHI VASTU Puram
SIDDHIVINAYAK PLATINUM
SEVEN HILLS
SHRI HARIPRIYA BUILDERS AND DEVELOPERS LLP
EVARA ESTATE
DSDB REALTY LLP
VISION CITY
VISION GROUP
NAKSHTRA
SHIV-NAKSHTRA DEVELOPERS LLP
SAHYADRISIDDHI
SAHYADRIDEVELOPERS
See every Sangli project, with the district possession charts
Builder: SUKHKARTA DEVELOPERS
SUKHKARTA DEVELOPERS has 2 registrations on MahaRERA, including SUKHKARTA and Shivalay. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sangli district page.
Frequently asked questions
What does it mean that Shivalay shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Shivalay is delayed beyond 31 Jul 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Shivalay?
The registered promoter entity is SUKHKARTA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Shivalay?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Shivalay?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Shivalay?
The professionals named in the filing: Architect: Prakash L Patil; Engineer: Makarand M Shinde; Engineer: Rudraksha Construction; Engineer: Vaibhv Prakash Swami; Chartered Accountant: Ms R K Kale and associates; Chartered Accountant: D V Patil and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Shivalay?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback