Home / Browse projects / Raigarh, Maharashtra / SHIV SHAKTI COMPLEX
SHIV SHAKTI COMPLEX
RG-MH-65596 · RERA P52000048777 · Last updated on MahaRERA portal: 18 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHIV SHAKTI COMPLEX is a Residential / Group Housing project by Shiv Shakti Developers in Raigarh, Maharashtra, registered with MahaRERA as P52000048777 on 17 Jan 2023. Possession is promised by 31 Dec 2028. The completion date has moved by 24 months from the original filing. 43 of the 235 units on this registration are recorded sold or booked, and 14 of 55 construction stages are filed complete.
At a glance
Project
- NameSHIV SHAKTI COMPLEX
- TypeResidential / Group Housing
- Location
- Chikhale Village
- Panvel
- Raigarh
- Chikhale
- Panvel
- Raigarh
- 410221
- Pincode410221
- RERA no.P52000048777
- ReraGenie IDRG-MH-65596
Builder
- NameShiv Shakti Developers
- Entity typePartnership
- PartnersVEERA AVCHAR BHATESHRA, Narayan Dhanji Dubariya, ANILKUMAR SOHANLAL SINGHVI, RAMESH BHIMABHAI DUBARIYA, MANJI RANCHHOD DUBARIYA, GANGJI BHAGA RAVARIYA
- Other registrations5 more →
- Completed3 of 6
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on17 Jan 2023
- Promised completion31 Dec 2028
- Revised completionRevised to 31 Dec 2028 (originally 31 Dec 2026)
- Buildings5 building records
- Documents filed153 files
Current status
Figures as on 18 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING NO 1 | NA | 8 | 6 | 48 | 0 | 48 |
| BUILDING NO 2, A WING | NA | 8 | 6 | 48 | 0 | 48 |
| BUILDING NO 2, B WING | NA | 8 | 6 | 54 | 0 | 54 |
| BUILDING NO 3, A WING | NA | 7 | 5 | 50 | 0 | 50 |
| BUILDING NO 3, B WING | NA | 7 | 5 | 35 | 0 | 35 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 18 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
14 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Stilt Floor, at 80%.
BUILDING NO 15%
| Activity | Progress |
|---|---|
| Excavation | 20% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
BUILDING NO 2, A WING40%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 20% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 23% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
BUILDING NO 2, B WING40%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 20% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 23% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
BUILDING NO 3, A WING51%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 12% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
BUILDING NO 3, B WING51%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 12% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
Progress on shared amenities15
As on 18 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 30% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 30% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed114
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| BUILDING NO 1 | 22 | 22 |
| BUILDING NO 2, A WING | 21 | 21 |
| BUILDING NO 2, B WING | 25 | 25 |
| BUILDING NO 3, A WING | 26 | 26 |
| BUILDING NO 3, B WING | 20 | 20 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| BUILDING NO 2, A WING | NA | Rs 6.98 cr | Rs 99.73 lakh |
| BUILDING NO 2, B WING | NA | Rs 6.98 cr | Rs 99.73 lakh |
| BUILDING NO 3, A WING | NA | Rs 6.60 cr | Rs 1.98 cr |
| BUILDING NO 3, B WING | NA | Rs 6.60 cr | Rs 1.98 cr |
| BUILDING NO 1 | NA | Rs 6.31 cr | - |
| - | NA | Rs 2.91 cr | Rs 37.99 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AAYADI ARCHITECTS & PLANNERS |
| Engineer | PRAPTI ASSOCIATE |
| Engineer | PHOENIX CONSULTANTS |
| Chartered Accountant | YOGESH NANDA AND ASSOCIATES |
| Chartered Accountant | R.B. SINGH & ASSOCIATES |
| Partner | Role in project |
|---|---|
| Shiv Shakti Developers | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe would like to inform that there has been a modification in the layout plan of the project, which has resulted in an increase in the Built-Up Area (BUA). Due to these changes, the construction timeline has been affected, and additional time will be required for completion. Furthermore, the revised Commencement Certificate (CC) has been obtained to reflect these adjustments. In light of these changes, we have not sold any units as of now, as the layout plan was undergoing revisions, and the updated CC had to be received before proceeding with further sales. Therefore, we kindly request an ext
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 23 Sep 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Mar 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Mar 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed153
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 153 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1 ARCHITECT CERTIFICATE 31 03 26.pdf | 18 Apr 2026 |
| Withdrawal Update Form 2File: FORM 2 ENGINEER CERTIFICATE 31 03 26.pdf | 18 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE 31 03 2026...pdf | 18 Apr 2026 |
| Withdrawal Update Form 1File: FORM 1 ARCHITECT CERTIFICATE 31 12 25.pdf | 20 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 ENGINEER CERTIFICATE 31 12 25.pdf | 20 Jan 2026 |
| Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE 31 12 25.pdf | 20 Jan 2026 |
| Form 5 (FY 2024-2025)File: FORM 5 SHIV SHAKTI COMPLEX.pdf | 2 Dec 2025 |
| Withdrawal Update Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf | 18 Oct 2025 |
| Withdrawal Update Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf | 18 Oct 2025 |
| Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE.pdf | 18 Oct 2025 |
| Withdrawal Update Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf | 6 Aug 2025 |
| Withdrawal Update Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf | 6 Aug 2025 |
| Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE.pdf | 6 Aug 2025 |
| Form 2A (FY 2024-2025)File: FORM 2A F.Y. 2024-25.pdf | 6 Aug 2025 |
| Withdrawal Update Form 1File: FORM 1 ARCHITECTS CERTIFICATE.pdf | 18 Jul 2025 |
| Withdrawal Update Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf | 18 Jul 2025 |
| Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE 08 05 2025.pdf | 18 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE 31 3 2025.pdf | 18 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE 31 3 2025 FINAL.pdf | 18 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE 31 3 2025.pdf | 18 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD CERTIFICATE 31 3 2025 FINAL.pdf | 18 Apr 2025 |
| Proforma of Allotment letterFile: DRAFT ALLOTMENT LETTER.pdf | 17 Apr 2025 |
| Deviation Report with respect to Allotment letterFile: REVISED DEVIATION ALLOTMENT FINAL.pdf | 17 Apr 2025 |
| Deviation Report with respect to model copy of AgreementFile: REVISED DEVIATION AGREEMENT FINAL.pdf | 17 Apr 2025 |
| Proforma of Agreement for saleFile: DRAFT AGREEMENT FOR SALE.pdf | 17 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE 15 02 2025.pdf | 7 Mar 2025 |
| Layout approvalFile: BUILDING LAYOUT PLAN PAGE 1 AND 2.pdf | 5 Mar 2025 |
| Layout approvalFile: BUILDING LAYOUT PLAN PAGE 3.pdf | 5 Mar 2025 |
| Layout approvalFile: BUILDING LAYOUT PLAN PAGE 4 AND 5.pdf | 5 Mar 2025 |
| Layout approvalFile: BUILDING LAYOUT PLAN PAGE 6 AND 7.pdf | 5 Mar 2025 |
| Layout approvalFile: BUILDING LAYOUT PLAN PAGE 1 AND 2 FINAL.pdf | 5 Mar 2025 |
| Layout approvalFile: BUILDING LAYOUT PLAN PAGE 3 AND 4 FINAL.pdf | 5 Mar 2025 |
| Layout approvalFile: BUILDING LAYOUT PLAN PAGE 5 AND 6 FINAL.pdf | 5 Mar 2025 |
| Layout approvalFile: BUILDING LAYOUT PLAN PAGE 7 FINAL.pdf | 5 Mar 2025 |
| Building plan approvalFile: BUILDING LAYOUT PLAN PAGE 3.pdf | 5 Mar 2025 |
| Building plan approvalFile: BUILDING LAYOUT PLAN PAGE 1 AND 2.pdf | 5 Mar 2025 |
| Building plan approvalFile: BUILDING LAYOUT PLAN PAGE 4 AND 5.pdf | 5 Mar 2025 |
| Building plan approvalFile: BUILDING LAYOUT PLAN PAGE 6 AND 7.pdf | 5 Mar 2025 |
| Building plan approvalFile: BUILDING LAYOUT PLAN PAGE 1 AND 2 FINAL.pdf | 5 Mar 2025 |
| Building plan approvalFile: BUILDING LAYOUT PLAN PAGE 3 AND 4 FINAL.pdf | 5 Mar 2025 |
| Building plan approvalFile: BUILDING LAYOUT PLAN PAGE 5 AND 6 FINAL.pdf | 5 Mar 2025 |
| Building plan approvalFile: BUILDING LAYOUT PLAN PAGE 7 FINAL.pdf | 5 Mar 2025 |
| Copy of Layout Approval (in case of layout)File: BUILDING LAYOUT PLAN PAGE 3.pdf | 5 Mar 2025 |
| Copy of Layout Approval (in case of layout)File: BUILDING LAYOUT PLAN PAGE 4 AND 5.pdf | 5 Mar 2025 |
| Copy of Layout Approval (in case of layout)File: BUILDING LAYOUT PLAN PAGE 6 AND 7.pdf | 5 Mar 2025 |
| Copy of Layout Approval (in case of layout)File: BUILDING LAYOUT PLAN PAGE 1 AND 2 FINAL.pdf | 5 Mar 2025 |
| Copy of Layout Approval (in case of layout)File: BUILDING LAYOUT PLAN PAGE 3 AND 4 FINAL.pdf | 5 Mar 2025 |
| Copy of Layout Approval (in case of layout)File: BUILDING LAYOUT PLAN PAGE 5 AND 6 FINAL.pdf | 5 Mar 2025 |
| Copy of Layout Approval (in case of layout)File: BUILDING LAYOUT PLAN PAGE 7 FINAL.pdf | 5 Mar 2025 |
| Copy of Layout Approval (in case of layout)File: BUILDING LAYOUT PLAN PAGE 1 AND 2.pdf | 5 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING LAYOUT PLAN PAGE 3.pdf | 5 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING LAYOUT PLAN PAGE 7 FINAL.pdf | 5 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING LAYOUT PLAN PAGE 5 AND 6 FINAL.pdf | 5 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING LAYOUT PLAN PAGE 3 AND 4 FINAL.pdf | 5 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING LAYOUT PLAN PAGE 1 AND 2 FINAL.pdf | 5 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING LAYOUT PLAN PAGE 6 AND 7.pdf | 5 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING LAYOUT PLAN PAGE 4 AND 5.pdf | 5 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING LAYOUT PLAN PAGE 1 AND 2.pdf | 5 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A ENGINEER CERTIFICATE 2023 24.pdf | 3 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECH CERTIFICATE.pdf | 15 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE FINAL.pdf | 15 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE.pdf | 15 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD QTRY UPDATE FINAL.pdf | 15 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 SHIV SHAKTI COMPLEX.pdf | 10 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD QTRLY UPDATE.pdf | 19 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERTIFICATE.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD QTRLY UPDATE.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE FINAL.pdf | 20 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE.pdf | 19 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE.pdf | 19 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Farm-2A ENGINEER CERTIFICATE.pdf | 19 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD UPDATES FINAL.pdf | 19 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE FINAL.pdf | 19 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECH 31 12 2023.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENG 31 12 2023.pdf | 20 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: BUILDING 1 31 12 2023.pdf | 20 Jan 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SUNSHINE VIEW | Kopari Vashi Navi Mumbai Plot 6 - 1 Sec-26 | 28 | Completed | Mar 2014 | Mar 2014 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 5 other registrations, which the RERA portal never shows together
- All 153 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SHIV SHAKTI COMPLEX on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Panvel, Raigarh5,900+ in Raigarh
ARIHANT ASPIRE PHASE I
ARIHANT ABODE LIMITED
Green Terraces, Godrej City, Panvel
CAROA PROPERTIES LLP
Nexspace, Godrej City, Panvel
CAROA PROPERTIES LLP
The Highlands, Godrej City, Panvel
CAROA PROPERTIES LLP
LA MER ONE
La Mer Homes LLP
Emperia Hill Crest
Emperia Builtcon
See every Raigarh project, with the district possession charts
Builder: Shiv Shakti Developers
Shiv Shakti Developers has 6 registrations on MahaRERA, including Shakti Residency and HARI SHRUSHTI. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if SHIV SHAKTI COMPLEX is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHIV SHAKTI COMPLEX?
The registered promoter entity is Shiv Shakti Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHIV SHAKTI COMPLEX?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHIV SHAKTI COMPLEX?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHIV SHAKTI COMPLEX?
The professionals named in the filing: Architect: AAYADI ARCHITECTS & PLANNERS; Engineer: PRAPTI ASSOCIATE; Engineer: PHOENIX CONSULTANTS; Chartered Accountant: YOGESH NANDA AND ASSOCIATES; Chartered Accountant: R.B. SINGH & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHIV SHAKTI COMPLEX?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback