Home / Browse projects / Mumbai Suburban, Maharashtra / SHIV PARVATI CHS LTD PHASE -1
SHIV PARVATI CHS LTD PHASE -1
By JAYESHJAGRUTI DEVELOPERS PVT LTD
RG-MH-86793 · RERA P51800013524 · Last updated on MahaRERA portal: 30 Oct 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 81 months
- 4 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHIV PARVATI CHS LTD PHASE -1 is a Residential / Group Housing project by JAYESHJAGRUTI DEVELOPERS PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800013524 on 9 Oct 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 81 months from the original filing.
At a glance
Project
- NameSHIV PARVATI CHS LTD PHASE -1
- TypeResidential / Group Housing
- Location
- RSC 54
- CHARKOP
- Borivali
- Mumbai Suburban
- 400067
- Pincode400067
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800013524
- ReraGenie IDRG-MH-86793
Builder
- NameJAYESHJAGRUTI DEVELOPERS PVT LTD
- Entity typeCompany
- Managing DirectorJAGANNATH LAXMAN MORE
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on9 Oct 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Mar 2020)
- Buildings4 building records
- Documents filed160 files
Current status
Figures as on 30 Oct 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHIV PARVATI CHS LTD - TOWER - A | NA | 23 | 0 | 0 | 0 | 0 |
| SHIV PARVATI CHS LTD - TOWER- B | NA | 23 | 0 | 0 | 0 | 0 |
| SHIV PARVATI CHS LTD - TOWER-C | NA | 23 | 0 | 0 | 0 | 0 |
| SHIV PARVATI CHS LTD - TOWER - D | NA | 23 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 30 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
28 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 95%.
SHIV PARVATI CHS LTD - TOWER - A91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
SHIV PARVATI CHS LTD - TOWER- B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
SHIV PARVATI CHS LTD - TOWER-C83%
| Activity | Progress |
|---|---|
| Excavation | 90% |
| Basement (if any) | 0% |
| Podiums (if any) | 75% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 61% |
SHIV PARVATI CHS LTD - TOWER - D48%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 50% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 81% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 25% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 15% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 30 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 50% |
| Water Supply | Yes | 60% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 60% |
| Storm Water Drains | Yes | 60% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 50% |
| Solid Waste Management And Disposal | Yes | 50% |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | Yes | 5% |
| Fire protection and fire safety requirements | Yes | 50% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 50% |
| Open Parking | No | Not applicable |
Parking filed383
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| SHIV PARVATI CHS LTD - TOWER - A | 87 | 87 |
| SHIV PARVATI CHS LTD - TOWER- B | 97 | 97 |
| SHIV PARVATI CHS LTD - TOWER-C | 98 | 98 |
| SHIV PARVATI CHS LTD - TOWER - D | 101 | 101 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SHIV PARVATI CHS LTD - TOWER - A | NA | Rs 145.02 cr | Rs 103.81 cr |
| SHIV PARVATI CHS LTD - TOWER-C | NA | Rs 20.00 cr | - |
| SHIV PARVATI CHS LTD - TOWER- B | NA | Rs 15.00 cr | Rs 10.74 cr |
| - | NA | Rs 15.00 cr | Rs 9.81 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | CHANDAN KELEKAR |
| Engineer | R R LAVEKAR |
| Chartered Accountant | ANIL CHINTAMAN MAHAJAN |
| Chartered Accountant | Mulraj D Gala & co |
| Partner | Role in project |
|---|---|
| JAYESHJAGRUTI DEVELOPERS PVT LTD | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe extension to the project is sought in view of delay in procurement of additional FSI from MHADA due to administrative and procedural constraints. Subsequently, the MHADA has granted additional FSI vide MHADA’s NOC No.CO/MB/REE/NOC/F-874/99/2018 dated 15/01/2018. As you are aware of, in the meantime, the GOM, Town Planning Department vide G.R. No.TBP/4315/167/CR-51/2015/VD-11 dated 23/05/2018 have entrusted and appointed the MHADA as Planning Authority to its layouts and therefore accorded rights of sanctioning and approving Building proposals of MHADA Layouts situated in the Mumbai Metropo
Reason as filed by the promoterCOVID
Reason as filed by the promoterThe catastrophic pandemic of CORONA-19 was befallen on the entire world. The Government has to impose lockdowns to curtail the virus resulting into the migration of labours on mass scale and non-availability of materials and other infrastructures. Therefore the activities of the entire housing industry have come to standstill. We are no exception to this natural calamity and disaster. The construction activities of the project under reference could not be continued further vigorously during the extension period granted by you due to lockdowns and mass migration of labour force. Presently, even
Reason as filed by the promoterThe Shiv Parvati CHS Ltd is a registered Co-operative Housing Society which is under construction on plot of land allotted by MHADA. The project was registered vide registration No. P51800013524 with MAHARERA. This is a mega project of 4 towers, namely A, B, C & D tower consisting 78 units each in every tower containing 312 units together. The construction of the project must be undertaken phase-wise as the additional FSI/Fungible FSI was not available in one attained/go. Tower-A, Tower-B & Tower-C was wholly completed and the possession of flats were already handed over to the allottees of fl
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Jul 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 22 Sep 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Jan 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed160
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 160 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Architect Certificate-FORM-1.pdf | 30 Oct 2025 |
| Withdrawal Update Form 2File: Engineer Certificate -FORM-2.pdf | 30 Oct 2025 |
| Withdrawal Update Form 3File: CHARTERED ACCOUNTENT CERTIFICATE- FORM-3.pdf | 30 Oct 2025 |
| Form 2A (FY 2024-2025)File: Enginer Certificate for Quality Assurance- FORM-2A.pdf | 30 Oct 2025 |
| Commencement certificateFile: CC.pdf | 21 Jul 2025 |
| Withdrawal Update Form 1File: ARCHITECT CERTIFICATE-FORM-1.pdf | 21 Jul 2025 |
| Withdrawal Update Form 1File: ARCHITECT CERTIFICATE-FORM-1.pdf | 21 Jul 2025 |
| Withdrawal Update Form 2File: ENGINEER CERTIFICATE-FORM-2.pdf | 21 Jul 2025 |
| Withdrawal Update Form 2File: ENGINEER CERTIFICATE-FORM-2.pdf | 21 Jul 2025 |
| Withdrawal Update Form 3File: CHARTERED ACCOUNTANT CERTIFICATE-FORM-3.pdf | 21 Jul 2025 |
| Withdrawal Update Form 3File: CHARTERED ACCOUNTANT CERTIFICATE-FORM-3.pdf | 21 Jul 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE- FORM--1.pdf | 24 Apr 2025 |
| Certificates of CA (Form 3)File: CHARTERED ACCOUNTENT CERTIFICATE-FORM-3.pdf | 24 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE-- FORM-2.pdf | 24 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SLOD BOOKED INVERTORY.pdf | 24 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ENGINEER CERTIFICATE FOR QUALITY ASSURANCE-FORM-2A.pdf | 24 Apr 2025 |
| Declaration in FORM BFile: AFFIDAVIT-CUM-DELCARATION-FORM-B.pdf | 7 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA ANNUAL REPORT-FORM-5.pdf | 27 Mar 2025 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: LETTER FROM THE BANK REGARDING THE OPEN OF RERA ACCOUNT.pdf | 24 Jan 2025 |
| Disclosure for secured/unsecured finance availed for the projectFile: DISCLOSURE FOR SECURED UNSECURED FINANCE AVAILED FOR PROJECT.pdf | 24 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE-FORM-1.pdf | 22 Jan 2025 |
| Certificates of CA (Form 3)File: CHARTERED ACCOUNTANT CERTIFICATE-FORM-3.pdf | 22 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE -FORM-2.pdf | 22 Jan 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf | 22 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD UNSOLD INVENTORY.pdf | 22 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ENGINEER`S CERTIFICATE FOR QUALITY -FORM -2A.pdf | 22 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE- FORM-1.pdf | 19 Oct 2024 |
| Certificates of CA (Form 3)File: CHRTERED ACCOUNTENT CERTIFICATE- FORM-3.pdf | 19 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE- FORM-2.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD UNDOLD INVERTSTY.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD UNSOLD INVENTORY.pdf | 19 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ENGINEER CERTIFICATE QUALITY ASSURANCE -FORM-2A.pdf | 19 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CHARTERED ACCOUNTENT ANNUAL REPORT- FORM-5.pdf | 19 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE-FORM-1.pdf | 20 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE- FORM-2.pdf | 20 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ENGINEER CERTIFICATE FOR QQUALITY ASSSURANCE FORM- 2A.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD UNSOLD INVERTARY.pdf | 20 Jul 2024 |
| Certificates of CA (Form 3)File: C HARTERED ACCOUNTANT CERTIFICATE- FORM-3.pdf | 20 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ENGINEER CERTIFICATE FOR QUALITY ASSURANCE-FORM-2A.pdf | 13 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE-Form--1.pdf | 16 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE-Form--2.pdf | 16 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD UNSOLD INVENTORY-.pdf | 16 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD UNSOLD INVENTORY--.pdf | 16 Apr 2024 |
| Certificates of CA (Form 3)File: CHARTERED ACCOUNTANT CERTIFICATE - FROM--3.pdf | 16 Apr 2024 |
| Building plan approvalFile: AMENDED PALN- IOD.pdf | 19 Jan 2024 |
| Building Plan Approval (IOD)File: AMENDED PALN- IOD.pdf | 19 Jan 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMANR CERTIFICATE- CC.pdf | 19 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFCATE-FORM-1.pdf | 19 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE-FORM-2.pdf | 19 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ENGINEER CERTIFICATE QUALITY ASSURANCE-FORM-2A.pdf | 19 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD UNSOLD INVENTORY.pdf | 19 Jan 2024 |
| Certificates of CA (Form 3)File: CHARTERED ACCOUNTANT CERTIFICATE - FROM-3.pdf | 19 Jan 2024 |
| Home Buyer /Allottee Grievance Redressal CellFile: ALLOTTEE GRIEVANCE REDRESSAL CELL LETTER.pdf | 19 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE-FORM-1.pdf | 7 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE-FORM-2.pdf | 7 Nov 2023 |
| Form 2AFile: ENGINEER CERTIFICATE QUALITY ASSURANCE-FORM-2A.pdf | 7 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE SOLD UNSOLD INVENTORY.pdf | 7 Nov 2023 |
| Certificates of CA (Form 3)File: CHARTERED ACCOUNTENT CERTIFICATE-FORM-3.pdf | 7 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CA ANNUAL REPORT ON STATMENT OF ACCOUNTS-FORM-5.pdf | 7 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE-FORM-1.pdf | 22 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE- FORM-2.pdf | 22 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ENGINEER CERTIFICATE FOR QUALITY ASSURANCE-FORM-2A.pdf | 22 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD BOOKED INVENTORY.pdf | 22 Jul 2023 |
| Certificates of CA (Form 3)File: CHARTERED ACCOUNTANT CERTIFICATE- FORM-3.pdf | 22 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE -FORM-1.pdf | 14 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE-FORM-2.pdf | 14 Apr 2023 |
| Form 2AFile: ENGINEER CERTIFICATE FOR QUALITY ASSURANCE-FORM-2A.pdf | 14 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: ENGINEER CERTIFICATE FOR QUALITY ASSURANCE-FORM-2A.pdf | 14 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD UNSOLD INVENTORY.pdf | 14 Apr 2023 |
| Certificates of CA (Form 3)File: CA CERTIFICATE -FORM-3.pdf | 14 Apr 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: OTHE REAL ESTATE ORGANIZATION-ANNEX-A.pdf | 25 Jan 2023 |
| Proforma of Agreement for saleFile: MODEL FORM OF AGREEMENT.pdf | 25 Jan 2023 |
| Other - FinanceFile: OTHER FINANCE.pdf | 25 Jan 2023 |
| Other - TechnicalFile: OTHER TECNICAL.pdf | 25 Jan 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE-CC.pdf | 18 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE-FORM-1.pdf | 18 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE -FORM- 2.pdf | 18 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: ENGINEER CERTIFICATE FOR QUALITY ASSURANCE-FORM- 2A.pdf | 18 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD UNSOLD INVENTORY.pdf | 18 Jan 2023 |
| Certificates of CA (Form 3)File: CHSRTERED ACCOUNTENT CERTIFICATE FORM-3.pdf | 18 Jan 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SHREE RAM TOWER CHS LTD | PLOT NO 21 RDP 1 MHADA LAYOUT GORAI BORIVALI WEST MUMBAI 400092 | 24 | Completed | Nov 2017 | Nov 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 160 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SHIV PARVATI CHS LTD PHASE -1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near CHARKOP6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 397 registered projects within 2 km.
Ruparel Optima Ph I
Ruparel Infra & Realty Pvt Ltd
"SALE BLDG NO. 6 (A & B) WING KNOWN AS NORTHER
N.ROSE DEVELOPERS PVT LTD
JP Commerz
Metallica Industries Limited
Ruparel Skygreens I
Shree Siddhivinayak Infrastructure & Realt
ShreejiAikyam
Rushabh Developers
Shiv Vardaan
NAVKARMIK HOMES LLP, URVI CONSTRUCTION
See every Mumbai Suburban project, with the district possession charts
Builder: JAYESHJAGRUTI DEVELOPERS PVT LTD
JAYESHJAGRUTI DEVELOPERS PVT LTD has 1 registration on MahaRERA, including SHIV PARVATI CHS LTD PHASE -1. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if SHIV PARVATI CHS LTD PHASE -1 is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHIV PARVATI CHS LTD PHASE -1?
The registered promoter entity is JAYESHJAGRUTI DEVELOPERS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHIV PARVATI CHS LTD PHASE -1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHIV PARVATI CHS LTD PHASE -1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHIV PARVATI CHS LTD PHASE -1?
The professionals named in the filing: Architect: CHANDAN KELEKAR; Engineer: R R LAVEKAR; Chartered Accountant: ANIL CHINTAMAN MAHAJAN; Chartered Accountant: Mulraj D Gala & co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHIV PARVATI CHS LTD PHASE -1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback