Completed No litigation declared Others project

Shiv Empire

By Shiv Infra

RG-MH-03062 · RERA P52000020470 · Last updated on MahaRERA portal: 5 Jun 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 14 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
May 2024Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 44 documents Report an error

Shiv Empire is a Others project by Shiv Infra in Raigarh, Maharashtra, registered with MahaRERA as P52000020470 on 15 Apr 2019. The registration is recorded completed; possession was promised by 7 May 2024. The completion date has moved by 14 months from the original filing.

At a glance

Project

  • NameShiv Empire
  • TypeOthers
  • Location
    • Sector -02
    • Ulwe
    • Ulawe
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • RERA no.P52000020470
  • ReraGenie IDRG-MH-03062

Builder

  • NameShiv Infra
  • Entity typePartnership
  • PartnersKisan Ramchandra Patil, Arvindkumar Chhaganbhai Patel, Deepak Bhagwan Patil, Appasaaheb Ananda Patil, Pravinbhai Mavji Chopra, Pratesh Baban Deshmukh, Hanumanram Rajuram Patel, Atish Satish Thorat
  • Other registrations2 more →
  • Completed2 of 3

Key dates

this monthRegisteredApr 2019First promiseMar 2023Revised toMay 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on15 Apr 2019
  • Promised completion7 May 2024
  • Revised completionRevised to 7 May 2024 (originally 30 Mar 2023)
  • Buildings1 building record
  • Documents filed44 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shiv EmpireNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

Shiv Empire: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 5 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed19

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots19
Closed/Covered19

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,250 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1874.39
Proposed, not sanctioned1,874 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKamothe

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDestination Architecture and interior Designs
PartnerRole in project
Shiv Infra-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000015303Mar 2023 → Mar 2024

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19

EXT52000026060Mar 2023 → May 2024

Reason as filed by the promoterWe, M/s. Shiv Infra, hereby declare the following with respect to the project Shiv Empire bearing registration number. P52000020470 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, we received the Occupation Certificate (OC) on 07th May 2024 and we have initiated the process for the possession as well, hence we won't be required to upload consents. To provide assurance and facilitate a smooth completion process, we are closely monitoring the remaining activities, ensuring timely executio

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Apr 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Apr 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Apr 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Apr 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Jun 2025

Documents filed44

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2 Occupancy Certificate_ Completion Certificate_ Architect's certificate of completion for5 Jun 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: P52000020470_FileName_1.pdf27 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A -22-23_11zon.pdf6 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A - 23-24_11zon.pdf6 Jan 2025
Declaration in FORM BFile: Form B.pdf4 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1.pdf4 Jan 2025
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf4 Jan 2025
Certificates of CA (Form 3)File: Form 3.pdf4 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf4 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf4 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 19-20.pdf4 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf4 Jan 2025
Disclosure of sold/ booked inventoryFile: C - 29.pdf4 Jan 2025
CERSAI detailsFile: cersai.pdf4 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf4 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf4 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Ann A.pdf4 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: f5.pdf4 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - Shiv Empire as on March 2021.pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - Shiv Empire as on March 2022.pdf31 Mar 2023
Declaration about Commencement CertificateFile: Format D.pdf29 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 19-20.pdf29 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf29 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf29 Mar 2023
Disclosure of sold/ booked inventoryFile: Circular 29.pdf29 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Shiv Empire FY 19-20 (1).pdf8 Dec 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 shiv Empire.pdf23 Aug 2019
Certificates of CA (Form 3)File: Form 3 Shiv Empire.pdf23 Aug 2019
Building plan approvalFile: Plan _page-0001 (1).pdf8 Apr 2019
Building plan approvalFile: Plan _page-0002 (1).pdf8 Apr 2019
Building plan approvalFile: Plan _page-0003.pdf8 Apr 2019
Building plan approvalFile: Plan _page-0004.pdf8 Apr 2019
Layout approvalFile: Plan _page-0001 (1).pdf8 Apr 2019
Copy of the legal title reportFile: Shiv Infra Title Report-min.pdf8 Apr 2019
Copy of Layout Approval (in case of layout)File: Plan _page-0001 (1).pdf8 Apr 2019
Building Plan Approval (IOD)File: Plan _page-0001 (1).pdf8 Apr 2019
Building Plan Approval (IOD)File: Plan _page-0002 (1).pdf8 Apr 2019
Building Plan Approval (IOD)File: Plan _page-0003.pdf8 Apr 2019
Building Plan Approval (IOD)File: Plan _page-0004.pdf8 Apr 2019
Proforma of Allotment letterFile: Shiv Infra - Incomplete (1).pdf8 Apr 2019
Certificates of CA (Form 3)File: Form 3 - Shiv Empire_compressed.pdf4 Apr 2019
Details of encumbrancesFile: shiv Infra encumbrance.pdf3 Apr 2019
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf3 Apr 2019
Declaration in FORM BFile: shiv Infra form B.pdf3 Apr 2019

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 14 months
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shiv Empire on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ulwe5,900+ in Raigarh

Builder: Shiv Infra

Shiv Infra has 3 registrations on MahaRERA, including Shiv Empire and BHAVESHWAR CAASA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Shiv Empire is delayed beyond 7 May 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shiv Empire?

The registered promoter entity is Shiv Infra, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shiv Empire?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shiv Empire?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shiv Empire?

The professionals named in the filing: Architect: Destination Architecture and interior Designs. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shiv Empire?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shiv Empire. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shiv Empire to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.