Home / Browse projects / Pune, Maharashtra / Shillim Residences - Phase 1

Registration lapsed No litigation declared Residential / Group Housing project

Shillim Residences - Phase 1

By Writer Lifestyle Pvt. Ltd.

RG-MH-26886 · RERA P52100015159 · Last updated on MahaRERA portal: 29 Jan 2018

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 82 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2019Possession promised82 months past this date
12 of 110Construction stages doneacross 10 buildings; furthest along: Excavation, 90%
0Complaints at MahaRERAon this registration
Jump to the 17 documents Report an error

Shillim Residences - Phase 1 is a Residential / Group Housing project by Writer Lifestyle Pvt. Ltd. in Pune, Maharashtra, registered with MahaRERA as P52100015159 on 2 Feb 2018. Possession was promised by 12 Dec 2019 and is now 82 months past that date.

At a glance

Project

  • NameShillim Residences - Phase 1
  • TypeResidential / Group Housing
  • Location
    • Javan Tungi Road
    • Shilimb Village
    • Shilimb
    • Mawal
    • Pune
    • 410406
  • Pincode410406
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100015159
  • ReraGenie IDRG-MH-26886

Builder

  • NameWriter Lifestyle Pvt. Ltd.
  • Entity typeCompany
  • DirectorsDayle de Souza, Garfield de Souza, Yazdi Hosi Desai, Subramaniam Ramachandran Iyer
  • Declared earlier projects11 →

Key dates

82 months past promisethis monthRegisteredFeb 2018PromisedDec 2019

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on2 Feb 2018
  • Promised completion12 Dec 2019
  • Revised completionNone
  • Buildings10 building records
  • Documents filed17 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Villa Number 12NA10000
Villa Number 13NA10000
Villa Number 14NA10000
Villa Number 15NA10000
Villa Number 16NA10000
Villa Number 11NA10000
Villa Number 10NA10000
Villa Number 8NA10000
Villa Number 7NA10000
Villa Number 6NA10000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building10

As on 29 Jan 2018, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 110 construction stages are filed complete across 10 buildings. The stage furthest along is Excavation, at 90%.

Villa Number 1227%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa Number 1327%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa Number 1427%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa Number 159%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa Number 168%
ActivityProgress
Excavation90%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa Number 1125%
ActivityProgress
Excavation100%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa Number 1025%
ActivityProgress
Excavation100%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa Number 80%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa Number 78%
ActivityProgress
Excavation90%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa Number 60%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 Jan 2018, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area18,143 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3113.3
Proposed, not sanctioned3,113 sq m
Buildings approved10
Buildings sanctioned10

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch1 - 14, Hiramani Supermarket, Near Lalbaug Police Chowki, Ambedkar Road, Lalbaug, Mumbai - 400012

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM/s. Alcove Designs
EngineerM/s. VMS CONSULTANTS PRIVATE LIMITED
PartnerRole in project
Writer Lifestyle Pvt. Ltd.-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Jan 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Jan 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Jan 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jan 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed17

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement Certificates / NA Order for plotted developmentFile: NA_Org_1st_Six_Pages - LR.pdf29 Jan 2018
Commencement Certificates / NA Order for plotted developmentFile: NA_Org_last_Six_Pages - LR.pdf29 Jan 2018
Commencement Certificates / NA Order for plotted developmentFile: NA_Org_last_Six_Pages - LR.pdf29 Jan 2018
Certificates of CA (Form 3)File: FORM_3_-PHASE_-_I - LR.pdf20 Jan 2018
Building plan approvalFile: Master Plan with 33 Villas TP approved JDA - LR.pdf19 Jan 2018
Layout approvalFile: Master Plan with 33 Villas TP approved JDA - LR.pdf19 Jan 2018
Copy of the legal title reportFile: Gat no 975.pdf19 Jan 2018
Copy of the legal title reportFile: Gat no 955.pdf19 Jan 2018
Copy of the legal title reportFile: Gat no 976.pdf19 Jan 2018
Copy of the legal title reportFile: Gat no 977.pdf19 Jan 2018
Details of encumbrancesFile: Shillim Residences - Phase 1 Affidavit.pdf19 Jan 2018
Copy of Layout Approval (in case of layout)File: Master Plan with 33 Villas TP approved JDA - LR.pdf19 Jan 2018
Building Plan Approval (IOD)File: Master Plan with 33 Villas TP approved JDA - LR.pdf19 Jan 2018
Declaration in FORM BFile: Shillim Residences - Phase 1 Affidavit.pdf19 Jan 2018
Proforma of Allotment letterFile: LETTER OF ALLOTMENT F.pdf19 Jan 2018
Proforma of Allotment letterFile: Draft Agreement F.pdf19 Jan 2018
PAN CardFile: Pancard of Writer Lifestyle Pvt Ltd.pdf4 Jan 2018

Promoter's earlier projects11

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

11 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Resort and Health FarmVillage Shilimb Chawsar Taluka Maval Dist Pune 41040693CompletedDec 2012Late, Jan 2015
St LeoWriter Residency St Leo Road Off Turner Road Bandra West Mumbai7CompletedOct 2008Late, Apr 2010
NNV3Plot no. Gen 72A TTC Industrial Area MIDC Mahape Navi Mumbai 4007094CompletedMar 2006Late, Apr 2008
Whitefield WarehousePlot No 272 upon 1 Hope Farm Circle Whitefield Bangalore 5600662CompletedOct 2003Late, Mar 2005
Gurgaon34 upon 1 to 7 42 Mile Stone Near NH8 Kherki Daula Sector 76 Gurugram4CompletedOct 2001Late, Apr 2004
Old MahapePlot no A 465 and466 TTC Industrial Area MIDC Pawne Village Dist Thane Navi Mumbai 4007091CompletedDec 2000Late, May 2002
Writer Corporate OfficeCTS no 1377 and 1378 Church Road Marol Andheri East Mumbai 4000587CompletedSep 2000Late, May 2002
VandalurNo. 159 1A GST Road Vandalur Chennai 6000484CompletedMay 2000Late, May 2002
New VashiD 506 TTC Industrial Area MIDC Shirwane Nerul Navi Mumbai 4007062CompletedDec 1999Late, May 2001
Old VashiPlot no D 178 upon 3 TTC Industrial Area MIDC Shiwane Behind London Pilsner Nerul Navi Mumbai 4007061CompletedOct 1998Late, Mar 2000
Writer Head Office105 Dr. B. Ambedkar Road Next to Voltas House Mumbai 4000333CompletedJun 1997Late, Dec 1998

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shillim Residences - Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shilimb Village13,700+ in Pune

Builder: Writer Lifestyle Pvt. Ltd.

Writer Lifestyle Pvt. Ltd. has 1 registration on MahaRERA, including Shillim Residences - Phase 1. Its filings disclose 11 earlier MahaRERA projects: declares 0 of 11 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Shillim Residences - Phase 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Shillim Residences - Phase 1 is delayed beyond 12 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shillim Residences - Phase 1?

The registered promoter entity is Writer Lifestyle Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shillim Residences - Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shillim Residences - Phase 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shillim Residences - Phase 1?

The professionals named in the filing: Architect: M/s. Alcove Designs; Engineer: M/s. VMS CONSULTANTS PRIVATE LIMITED. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shillim Residences - Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shillim Residences - Phase 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shillim Residences - Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.