ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / SHEETAL VAIBHAV

Completed No litigation declared Residential / Group Housing project

SHEETAL VAIBHAV

By D.G.S TOWNSHIP PRIVATE LIMITED

RG-MH-54050 · RERA P51800019010 · Last updated on MahaRERA portal: 13 May 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 43 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
8 of 11Construction stages donefurthest along: Installation of Lifts, 95%
0Complaints at MahaRERAon this registration
Jump to the 78 documents Report an error

SHEETAL VAIBHAV is a Residential / Group Housing project by D.G.S TOWNSHIP PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800019010 on 28 Dec 2018. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 43 months from the original filing.

At a glance

Project

  • NameSHEETAL VAIBHAV
  • TypeResidential / Group Housing
  • Location
    • JUNCTION OF 18TH ROAD AND 13TH ROAD
    • KHAR WEST
    • Greater Mumbai (M Corp.) (Part) (802794)
    • Mumbai
    • Mumbai Suburban
    • 400052
  • Pincode400052
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800019010
  • ReraGenie IDRG-MH-54050

Builder

  • NameD.G.S TOWNSHIP PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorSURAJDEV DUDHNATH SHUKLA
  • DirectorISHWARDEV DUDHNATH SHUKLA
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredDec 2018First promiseMay 2022Revised toDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on28 Dec 2018
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 1 May 2022)
  • Buildings1 building record
  • Documents filed78 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHEETAL VAIBHAVNA150000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

SHEETAL VAIBHAV: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 13 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed24

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots24
Closed/Covered24

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area376 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1178.24
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAAREY ROAD, GOREGAON EAST, MUMBAI

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRASIK HINGOO
EngineerHIREN TANNA
PartnerRole in project
D.G.S TOWNSHIP PRIVATE LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800012765May 2022 → May 2023

Reason as filed by the promoterdue to covid-19 project got delayed

EXT51800024088May 2022 → Dec 2025

Reason as filed by the promoterWe are under process of getting occupancy certificate so we need extension till 31-12-2025

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Nov 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Nov 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Nov 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Nov 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 May 2025

Documents filed78

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2405703_OC_signed.pdf13 May 2025
Certificates of CA (Form 3)File: DGS VAIBHAV FORM 3_MAR-25.pdf6 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-Dec-24.pdf17 Feb 2025
Certificates of CA (Form 3)File: Form 3 Sheetal Vaibhav dec 2024.pdf6 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vaibhav Form 2 Dec 24.pdf1 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vaibhav Khar Form 1 Sept 24.pdf5 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vaibhav Khar Form 1 Sept 24.pdf5 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate- Sheetal Vaibhav_0001.pdf28 Nov 2024
Certificates of CA (Form 3)File: VAIBHAV form 3 SEPT 24_compressed.pdf14 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vaibhav Form 2 - June 24.pdf1 Aug 2024
Certificates of CA (Form 3)File: vaibhv form-3 june 2024_compressed (1).pdf24 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vaibhav Form 1 - June 24.pdf23 Jul 2024
Details of encumbrances concerned to FinanceFile: 1 Details of encumbrances (1).pdf20 Jun 2024
Details of encumbrances concerned to LegalFile: 1 Details of encumbrances (1).pdf20 Jun 2024
Declaration about Commencement CertificateFile: declaration about CC.pdf20 Jun 2024
Declaration in FORM BFile: FORM B.pdf20 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf20 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf20 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 22-23.pdf20 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 23-24.pdf20 Jun 2024
CERSAI detailsFile: Cersai_Declaration.pdf20 Jun 2024
Disclosure of sold/ booked inventoryFile: SOLD INV.pdf20 Jun 2024
Certificates of CA (Form 3)File: FORM 3.pdf20 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf20 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21).pdf20 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21).pdf20 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22.pdf20 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A bank account decla (20).pdf20 Jun 2024
Deviation Report with respect to Allotment letterFile: deviation-allotment.pdf20 Jun 2024
Deviation Report with respect to model copy of AgreementFile: deviation-draft sale.pdf20 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: VAIBHAV FORM 5 SIGNED.pdf16 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Sheetal Vaibhav Township Form 5 22-23 (2).pdf26 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2A vaibhav Khar.pdf25 Nov 2022
Disclosure of sold/ booked inventoryFile: Sold inventory vaibhav khar.pdf25 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: DGS township pvt ltd Form 5 M 2022.pdf25 Nov 2022
Proforma of Agreement for saleFile: Vaibhav khar Sale Agreement.pdf28 Oct 2022
Certificates of CA (Form 3)File: VISHAL DHARMRAJ - FROM 3 - 31-3-2021.pdf30 Oct 2021
Certificates of CA (Form 3)File: KHAR VAIBHAV - FORM 3 - 31-3-2021.pdf30 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: KHAR VAIBHAV-2A- 31-12-2018.pdf21 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: KHAR-VAIBHAV-2A-31-3-2019.pdf21 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: KHAR-VAIBHAV-2A- 31-3-2019.pdf21 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: KHAR-VAIBHAV-2A- 30-6-2019.pdf21 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: KHAR-VAIBHAV-2A- 30-9-2019.pdf21 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: KHAR VAIBHAV - 2A - 31-12-2019.pdf21 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: KHAR-VAIBHAV-2A- 31-3-2021.pdf21 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: KHAR-VAIBHAV-2A- 31-3-2020.pdf21 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: KHAR-VAIBHAV-2A- 30-6-2020.pdf21 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: KHAR-VAIBHAV-2A- 30-9-2020.pdf21 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: KHAR-VAIBHAV-2A - 31-12-2020.pdf21 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: KHAR-VAIBHAV-2A - 31-3-2021.pdf21 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: KHAR-VAIBHAV-2A- 30-6-2021.pdf21 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: KHAR-VAIBHAV-2A- 30-9-2021.pdf21 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: khar vaibhav form 5 march 2021.pdf23 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 SHEETAL TRIMURTI 2020-2021.pdf6 Aug 2021
Form 2AFile: scan286_compressed.pdf7 Jun 2019
Form 2AFile: scan286_compressed.pdf7 Jun 2019
Form 2AFile: scan286_compressed.pdf7 Jun 2019
Proforma of Allotment letterFile: PROFORMA OF ALLOTMENT LETTER.pdf17 Nov 2018
Proforma of Allotment letterFile: Konkanastha-Printed Sale Agreement-revised-RERA-Uploaded.pdf16 Nov 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2-kokanstha.pdf14 Nov 2018
Certificates of CA (Form 3)File: FORM-3-KOKANSTHA.pdf14 Nov 2018
Layout approvalFile: CONCESSION PLAN-1-ilovepdf-compressed.pdf6 Nov 2018
Layout approvalFile: CONCESSION PLAN-2-ilovepdf-compressed.pdf6 Nov 2018
Layout approvalFile: CONCESSION PLAN-3-ilovepdf-compressed.pdf6 Nov 2018
Copy of Layout Approval (in case of layout)File: CONCESSION PLAN-1-ilovepdf-compressed.pdf6 Nov 2018
Copy of Layout Approval (in case of layout)File: CONCESSION PLAN-2-ilovepdf-compressed.pdf6 Nov 2018
Copy of Layout Approval (in case of layout)File: CONCESSION PLAN-3-ilovepdf-compressed.pdf6 Nov 2018
Building plan approvalFile: KOKANSTHA-IOD.pdf5 Nov 2018
Building plan approvalFile: kokanstha-iod-plan.pdf5 Nov 2018
PAN CardFile: DGS TOWNSHIP PRIVATE LIMITED PAN.pdf5 Nov 2018
PAN CardFile: SURAJDEV SHUKLA PAN.pdf5 Nov 2018
Copy of the legal title reportFile: KOKANSTHA-TITLE CERTIFICATE.pdf5 Nov 2018
Details of encumbrancesFile: encumb-kOKANSTHA.pdf5 Nov 2018
Building Plan Approval (IOD)File: KOKANSTHA-IOD.pdf5 Nov 2018
Building Plan Approval (IOD)File: kokanstha-iod-plan.pdf5 Nov 2018
Commencement Certificates / NA Order for plotted developmentFile: Khar First CC.pdf5 Nov 2018
Declaration in FORM BFile: KOKANSTHA-FROM-B.pdf5 Nov 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: kOKANSTHA-FORM-1.pdf5 Nov 2018

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 43 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHEETAL VAIBHAV on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KHAR WEST6,700+ in Mumbai Suburban

2 kmSHEETAL VAIBHAVCompleted 116Lapsed / revoked 57Other 137Dot size: filed unitsN

Filed coordinates, straight-line distance. 310 registered projects within 2 km.

Builder: D.G.S TOWNSHIP PRIVATE LIMITED

D.G.S TOWNSHIP PRIVATE LIMITED has 6 registrations on MahaRERA, including SHEETAL VAIBHAV and SHEETAL SONA. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SHEETAL VAIBHAV is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHEETAL VAIBHAV?

The registered promoter entity is D.G.S TOWNSHIP PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHEETAL VAIBHAV?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHEETAL VAIBHAV?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHEETAL VAIBHAV?

The professionals named in the filing: Architect: RASIK HINGOO; Engineer: HIREN TANNA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHEETAL VAIBHAV?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHEETAL VAIBHAV. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHEETAL VAIBHAV to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.