Home / Browse projects / Thane, Maharashtra / Shashwat Vaastu
Shashwat Vaastu
RG-MH-66293 · RERA P51700014018 · Last updated on MahaRERA portal: 15 May 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 58 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Shashwat Vaastu is a Residential / Group Housing project by M/s Shashwat Vaastu in Thane, Maharashtra, registered with MahaRERA as P51700014018 on 7 Nov 2017. Possession was promised by 30 Dec 2021 and is now 58 months past that date.
At a glance
Project
- NameShashwat Vaastu
- TypeResidential / Group Housing
- Location
- Mumbai Nashik Highway
- Asangaon
- Asangaon (CT)
- Shahapur
- Thane
- 421601
- Pincode421601
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700014018
- ReraGenie IDRG-MH-66293
Builder
- NameM/s Shashwat Vaastu
- Entity typePartnership
- PartnersLAXMAN ARJUN VISPUTE, Chandrashekhar Damodar Bhide, Deepika Chandrashekhar Bhide, Jatin Laxman Vispute
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on7 Nov 2017
- Promised completion30 Dec 2021
- Revised completionNone
- Buildings2 building records
- Documents filed39 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building D | NA | 5 | 0 | 0 | 0 | 0 |
| Building E | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 15 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
22 of 22 construction stages are filed complete across 2 buildings.
Building D100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building E100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 15 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Land and ownership4
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| LAHU DAJI CHANDE | Asangaon (CT) | Thane |
| Maruti Daji Chande | Asangaon (CT) | Thane |
| Archana Ram Chande | Asangaon (CT) | Thane |
| JAYASHRI MOHAN PANSARE | Thane (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sanjay D Wadile |
| Engineer | Pramod Kamble |
| Partner | Role in project |
|---|---|
| M/s Shashwat Vaastu | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Oct 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Oct 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Oct 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 15 May 2023
Documents filed39
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: VASTU LETTER_compressed.pdf | 15 May 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY WING E.pdf | 15 May 2023 |
| Other - LegalFile: VASTU LETTER_compressed.pdf | 15 May 2023 |
| Other - TechnicalFile: appliction for completion.pdf | 29 Mar 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Certificate pdf D.pdf | 4 Feb 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architech cert d wing.pdf | 13 Nov 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architech cert e wing.pdf | 13 Nov 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ArchitechCertVaastuBldgE.pdf | 9 Aug 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ArchtechCertVaastuBldgD.pdf | 9 Aug 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architech certificate wing d.pdf | 18 Jun 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architech certificate wing e.pdf | 18 Jun 2019 |
| Certificates of CA (Form 3)File: CA CERTIFICAT D E (1).pdf | 18 Jun 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERT WING D DEC2018.pdf | 5 Apr 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERTI WING E DEC2018.pdf | 5 Apr 2019 |
| Certificates of CA (Form 5)File: shaswat vaastu.pdf | 15 Oct 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Asangaon N A Building Permission.pdf | 12 Apr 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vaastu D Architect Cer.PDF | 31 Mar 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vaastu E Architect Certificate.PDF | 31 Mar 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vaastu D Wing Eng Cer.pdf | 31 Mar 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vaastu E Engeer Certiuficate.PDF | 31 Mar 2018 |
| Certificates of CA (Form 3)File: CA Certificate SASHWAT VASTU.pdf | 31 Mar 2018 |
| Building plan approvalFile: SHASHWAT VAASTU D WING SANCTION PLAN.pdf | 28 Oct 2017 |
| Building plan approvalFile: SHASHWAT VASTU ( E ) WING PLAN.pdf | 28 Oct 2017 |
| Layout approvalFile: layout.pdf | 28 Oct 2017 |
| PAN CardFile: Full page photo.pdf | 28 Oct 2017 |
| Copy of the legal title reportFile: Title latest.PDF | 28 Oct 2017 |
| Details of encumbrancesFile: Title latest.PDF | 28 Oct 2017 |
| Copy of Layout Approval (in case of layout)File: layout.pdf | 28 Oct 2017 |
| Building Plan Approval (IOD)File: SHASHWAT VAASTU D WING SANCTION PLAN.pdf | 28 Oct 2017 |
| Building Plan Approval (IOD)File: SHASHWAT VASTU ( E ) WING PLAN.pdf | 28 Oct 2017 |
| Declaration in FORM BFile: Affiavit Shashwat Vaastu.PDF | 28 Oct 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: E Wing Architect Certificate New.pdf | 28 Oct 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: D WIng Architect Certificate New.pdf | 28 Oct 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Certificate D Vastu New.pdf | 28 Oct 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Certificate E Vastu New.pdf | 28 Oct 2017 |
| Certificates of CA (Form 3)File: CA Certificate D and E New.PDF | 28 Oct 2017 |
| Proforma of Allotment letterFile: Allotment letter Asangaon Rera.pdf | 28 Oct 2017 |
| Proforma of Allotment letterFile: Agreement Drat as per RERA D wing.pdf | 28 Oct 2017 |
| Proforma of Allotment letterFile: Agreement Drat as per RERA E wing.pdf | 28 Oct 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Shashwat Vaastu | Shashwat Vaastu Shri Krishna Nagar Asangaon West | 140 | Completed | Oct 2015 | Late, Oct 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 39 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Shashwat Vaastu on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Asangaon7,600+ in Thane
Filed coordinates, straight-line distance. 14 registered projects within 2 km.
BELLA VISTA PHASE 8
INDO ASIAN BUILDCON PVT LTD
RUSTOMJEE BELLE VUE
KEYSTONE REALTORS LIMITED
THE VENISCAPE
MIVAAN BUILDCON PRIVATE LIMITED
VISION SKY WORLD
M/S VISION SKY WORLD
Sunteck FORESTWorld 1
SUNTECK REALTY HOLDINGS PVT LTD
Sunteck FORESTWorld 2
SUNTECK REALTY HOLDINGS PVT LTD
See every Thane project, with the district possession charts
Builder: M/s Shashwat Vaastu
M/s Shashwat Vaastu has 1 registration on MahaRERA, including Shashwat Vaastu. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that Shashwat Vaastu shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Shashwat Vaastu is delayed beyond 30 Dec 2021?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Shashwat Vaastu?
The registered promoter entity is M/s Shashwat Vaastu, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Shashwat Vaastu?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Shashwat Vaastu?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Shashwat Vaastu?
The professionals named in the filing: Architect: Sanjay D Wadile; Engineer: Pramod Kamble. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Shashwat Vaastu?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback