SHANTIVAN
By SAIBABA SALES PRIVATE LIMITED
RG-MH-22519 · RERA P52100032130 · Last updated on MahaRERA portal: 2 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 2 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 17 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHANTIVAN is a Residential / Group Housing project by SAIBABA SALES PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100032130 on 14 Dec 2021. Possession was promised by 10 Aug 2026 and is now 2 months past that date. The completion date has moved by 17 months from the original filing. 15 of the 55 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameSHANTIVAN
- TypeResidential / Group Housing
- Location
- PIMPRI KALEWADI ROAD
- PIMPRI
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 411017
- Pincode411017
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100032130
- ReraGenie IDRG-MH-22519
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on14 Dec 2021
- Promised completion10 Aug 2026
- Revised completionRevised to 10 Aug 2026 (originally 31 Mar 2025)
- Buildings1 building record
- Documents filed119 files
Current status
Figures as on 2 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHANTIVAN | NA | 12 | 12 | 23 | 32 | 55 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 2 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
SHANTIVAN: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 2 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed88
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership3
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SAI BABA SALES PVT LTD | Pimpri Chinchawad (M Corp.) | Pune |
| SHANTIVAN COOP HSG SOCIETY LTD | Pimpri Chinchawad (M Corp.) | Pune |
| SHANTIVAN CO OP HSG SOC LTD | Pimpri Chinchawad (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SHANTIVAN | NA | Rs 19.55 cr | Rs 19.37 cr |
| - | NA | Rs 2.00 cr | Rs 2.00 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | UNUSUAL SPACES |
| Engineer | pramod u mahajan |
| Engineer | Anurag Mourya |
| Chartered Accountant | VBS AND COMPANY |
| Chartered Accountant | Rajeev Karandikar |
| Partner | Role in project |
|---|---|
| SAIBABA SALES PRIVATE LIMITED | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterthe construction of the project is currently ongoing, and we have encountered certain unforeseen circumstances that have affected the original timeline. These include legal issues owing to certain members/occupants of your society filing various legal proceedings against not only the Society but also us i.e. the Developer before various courts/tribunal/commissions, supply chain issues, labour shortages, adverse weather conditions, delays in obtaining required permissions, etc. Despite our best efforts, these challenges have caused delays in the project’s progress.
Reason as filed by the promoterProject is completed
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000269419 | Mahesh Gangaram Sugnani | Mr Kirpal Gehaney | 21/09/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Oct 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 1 Apr 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 1 Apr 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed119
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 119 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Shantivan 2024-25.pdf | 2 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 Shantivan 2024-25.pdf | 2 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 Shantivan 2024-25.pdf | 2 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 Shantivan 2024-25.pdf | 2 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 Shantivan 2024-25.pdf | 2 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 Shantivan 2024-25.pdf | 2 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 Shantivan 2024-25.pdf | 2 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 Shantivan 2024-25.pdf | 2 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 Shantivan 2024-25.pdf | 2 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 Shantivan 2024-25.pdf | 2 Aug 2026 |
| Withdrawal Update Form 3File: Final Shantivan Form 3 working - FY 2025-26 .pdf | 2 Aug 2026 |
| Withdrawal Update Form 3File: Final Shantivan Form 3 working - FY 2025-26 .pdf | 2 Aug 2026 |
| Withdrawal Update Form 3File: Final Shantivan Form 3 working - FY 2025-26 .pdf | 2 Aug 2026 |
| Withdrawal Update Form 3File: Final Shantivan Form 3 working - FY 2025-26 .pdf | 2 Aug 2026 |
| Withdrawal Update Form 3File: Final Shantivan Form 3 working - FY 2025-26 .pdf | 2 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 Shantivan 2024-25.pdf | 24 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Shantivan 2024-25.pdf | 24 Jul 2026 |
| Withdrawal Update Form 3File: Final Shantivan Form 3 working - FY 2025-26 .pdf | 24 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2A June 2025.pdf | 3 Jul 2026 |
| Layout approvalFile: Layout Plan.pdf | 1 Apr 2026 |
| Building plan approvalFile: dftt002.pdf | 1 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 Shantivan.pdf | 1 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 Shantivan.pdf | 1 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 Shantivan.pdf | 1 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 Shantivan 2024-25.pdf | 1 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 Shantivan 2024-25.pdf | 1 Apr 2026 |
| Withdrawal Update Form 2File: ENGG CERTIFICATE -1.pdf | 1 Apr 2026 |
| Withdrawal Update Form 2File: ENGG CERTIFICATE -1.pdf | 1 Apr 2026 |
| Withdrawal Update Form 2File: ENGG CERTIFICATE -1.pdf | 1 Apr 2026 |
| Withdrawal Update Form 2File: ENGG CERTIFICATE -1.pdf | 1 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 Shantivan 2024-25.pdf | 1 Apr 2026 |
| Withdrawal Update Form 3File: form_3 dated 6march 23.pdf | 1 Apr 2026 |
| Withdrawal Update Form 3File: Firm 3 march 2026.pdf | 1 Apr 2026 |
| Withdrawal Update Form 3File: Firm 3 march 2026.pdf | 1 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 28_3_2025.pdf | 1 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 28_3_2025.pdf | 1 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 Shantivan.pdf | 30 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 Shantivan.pdf | 30 Mar 2026 |
| Withdrawal Update Form 2File: ENGG CERTIFICATE -1.pdf | 30 Mar 2026 |
| Withdrawal Update Form 2File: ENGG CERTIFICATE -1.pdf | 30 Mar 2026 |
| Withdrawal Update Form 3File: form_3 dated 6march 23.pdf | 30 Mar 2026 |
| Withdrawal Update Form 3File: form_3 dated 6march 23.pdf | 30 Mar 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1, Shantivan 2024-25.pdf | 25 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 .pdf | 25 Jul 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2, Shantivan 2024-25.pdf | 25 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure Sold flat .pdf | 25 Jul 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality assurance FY 2023-24.pdf | 10 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 (2023-24).pdf | 17 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Shantivan.pdf | 13 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Shantivan.pdf | 13 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Shantivan.pdf | 13 Oct 2023 |
| Building plan approvalFile: SHANTIVAN COMMENCEMENT 2022.pdf | 12 Oct 2023 |
| Building plan approvalFile: SHANTIVAN GROUND FLOOR PLAN 2022-2_compressed (1).pdf | 12 Oct 2023 |
| Building plan approvalFile: SHANTIVAN 3RD AND EVEN FLOOR PLAN 2022-4_compressed.pdf | 12 Oct 2023 |
| Building plan approvalFile: SHANTIVAN ODD FLOOR PLAN 2022-5_compressed.pdf | 12 Oct 2023 |
| Building plan approvalFile: 3.pdf | 12 Oct 2023 |
| Building plan approvalFile: 6.pdf | 12 Oct 2023 |
| Building plan approvalFile: 7.pdf | 12 Oct 2023 |
| Building plan approvalFile: SHANTIVAN GROUND FLOOR PLAN 2022-2_compressed.pdf | 12 Oct 2023 |
| Building plan approvalFile: SHANTIVAN GROUND FLOOR PLAN 2022-2_compressed (1).pdf | 12 Oct 2023 |
| Layout approvalFile: SHANTIVAN LAYOUT PLAN 2022-1_compressed (1).pdf | 12 Oct 2023 |
| Building plan approvalFile: SHANTIVAN GROUND FLOOR PLAN 2022-2_compressed (1).pdf | 12 Oct 2023 |
| Copy of the legal title reportFile: shantivan search and title 2023_compressed.pdf | 12 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: SHANTIVAN LAYOUT PLAN 2022-1_compressed (1).pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: SHANTIVAN GROUND FLOOR PLAN 2022-2_compressed (1).pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: SHANTIVAN GROUND FLOOR PLAN 2022-2_compressed (1).pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: SHANTIVAN GROUND FLOOR PLAN 2022-2_compressed.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: SHANTIVAN COMMENCEMENT 2022.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: SHANTIVAN GROUND FLOOR PLAN 2022-2_compressed (1).pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: SHANTIVAN 3RD AND EVEN FLOOR PLAN 2022-4_compressed.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: SHANTIVAN ODD FLOOR PLAN 2022-5_compressed.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 3.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 6.pdf | 12 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 7.pdf | 12 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: SHANTIVAN COMMENCEMENT 2022.pdf | 12 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Sold inventory shantivan.pdf | 12 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Unsold inventory Shop, shantivan.pdf | 12 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 shantivan Oct 2023.pdf | 12 Oct 2023 |
| Proforma of Agreement for saleFile: DRAFT AGREEMENT.pdf | 12 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QUALITY ASSURANCE 2021-22.pdf | 8 Sep 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Sai Laxuria | S.No 50A Rahatni Pune 17 | 130 | Completed | Nov 2012 | Nov 2012 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 119 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SHANTIVAN on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PIMPRI13,700+ in Pune
Filed coordinates, straight-line distance. 249 registered projects within 2 km.
VARDHAMAN SKYTOWN
VARDHAMAN ASSOCIATES
Tamara
Goldfinger Kataria Urban Developments
Sindhu Skies
G K Wonders
Legacy Kairos A and B Building
Legacy Lifespaces LLP
Amberwood Phase 1
SMP NAMRATA ASSOCIATES
121 Paradise Phase I
Wamanbhau & Daga Realtors LLP
Builder: SAIBABA SALES PRIVATE LIMITED
SAIBABA SALES PRIVATE LIMITED has 5 registrations on MahaRERA, including SAIS LEELA and Sairaj Heights. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that SHANTIVAN shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SHANTIVAN is delayed beyond 10 Aug 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHANTIVAN?
The registered promoter entity is SAIBABA SALES PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHANTIVAN?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SHANTIVAN?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SHANTIVAN?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHANTIVAN?
The professionals named in the filing: Architect: UNUSUAL SPACES; Engineer: pramod u mahajan; Engineer: Anurag Mourya; Chartered Accountant: VBS AND COMPANY; Chartered Accountant: Rajeev Karandikar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHANTIVAN?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback