ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / SHANTIPURUSH APARTMENT

Registered No litigation declared Residential / Group Housing project

SHANTIPURUSH APARTMENT

By AARYA ASSOCIATES

RG-MH-98380 · RERA P50500053661 · Last updated on MahaRERA portal: 29 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedno revision filed
5 of 11Construction stages donefurthest along: Internal walls, 97%
19 of 20Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

SHANTIPURUSH APARTMENT is a Residential / Group Housing project by AARYA ASSOCIATES in Nagpur, Maharashtra, registered with MahaRERA as P50500053661 on 21 Nov 2023. Possession is promised by 31 Mar 2027. 1 of the 20 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHANTIPURUSH APARTMENT
  • TypeResidential / Group Housing
  • Location
    • AMBAZARI ROAD
    • AMBAZARI
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440010
  • Pincode440010
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500053661
  • ReraGenie IDRG-MH-98380

Builder

  • NameAARYA ASSOCIATES
  • Entity typePartnership
  • PartnerPARESH DATTATRAYA JOSHI
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredNov 2023PromisedMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Nov 2023
  • Promised completion31 Mar 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed70 files

Current status

5%1 of 20 units booked
84.4%Work done, per cost certificate

Figures as on 29 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHANTIPURUSH APARTMENTSNA8720020

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 97%.

SHANTIPURUSH APARTMENTS: 69% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes15%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed35

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots35
Closed/Covered19
Open Space16

Land and ownership11

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area604 sq m
Land owned byThe promoter, with other names on the file
Named landowners11
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Oct 2025
LandownerVillageDistrict
DATTATRAYA PURUSHOTTAM KARKARENagpur (M Corp.)Nagpur
YOGESH DATTATRAYA KARKARENagpur (M Corp.)Nagpur
NANDKISHOR SUDHAKAR BADHENagpur (M Corp.)Nagpur
SHRIRAM GANGADHAR CHINEYNagpur (M Corp.)Nagpur
KISHOR GOPALRAO BAPATNagpur (M Corp.)Nagpur
SHRIRANG ANILRAO KOTHENashik (M Corp.)Nashik
SHRIVALLABH ANILRAO KOTHENagpur (M Corp.)Nagpur
SUDHIR NARAYAN PHADKENagpur (M Corp.)Nagpur
NALINI DHANRAJ DAHATNagpur (M Corp.)Nagpur
KAVITA KISHOR BAPATNagpur (M Corp.)Nagpur
PRASHANT SURESH BAKHLENagpur (M Corp.)Nagpur

Approvals and building plan

Sanctioning authorityNAGPUR MUNICIPAL CORPORATION
Permissible FSI1932.3
Proposed, not sanctioned1,884 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHINGNA ROAD NAGPUR
Estimated costRs 4.40 cr
Cost incurredRs 3.71 cr
Work done84.43%
BuildingWingEstimatedIncurred
SHANTIPURUSH APARTMENTSNARs 4.40 crRs 3.71 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAURABH JAGDALE & ASSOCIATES
EngineerSA
EngineerNANDESH FIRKE
Chartered AccountantAshish Agrawal
Chartered AccountantSUMIT CHANDWANI
PartnerRole in project
AARYA ASSOCIATES-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Sep 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Sep 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Sep 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Architect Certificate March 2026.pdf29 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate March 2026.pdf29 Apr 2026
Withdrawal Update Form 3File: Form 3 CA Certificate March 2026.pdf29 Apr 2026
Withdrawal Update Form 1File: Architect Certificate Dec 25.pdf21 Jan 2026
Withdrawal Update Form 2File: Engineer Certificate Dec 25.pdf21 Jan 2026
Withdrawal Update Form 3File: CA Certificate Dec 25.pdf21 Jan 2026
Form 1File: Form 1 Architect certificate Sept 25.pdf29 Oct 2025
Form 2File: Form 2 Engineer Certificate Sept 25.pdf29 Oct 2025
Form 3File: Form 3 CA Certificate Sept 25.pdf29 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory Sept 25.pdf29 Oct 2025
Withdrawal Update Form 1File: Form 1 Architect certificate Sept 25.pdf29 Oct 2025
Withdrawal Update Form 2File: Form 2 Engineer Certificate Sept 25.pdf29 Oct 2025
Withdrawal Update Form 3File: Form 3 CA Certificate Sept 25.pdf29 Oct 2025
Form 5 (FY 2024-2025)File: form 5 24-25.pdf7 Oct 2025
Form 2A (FY 2024-2025)File: FORM 2A FY 24-25 SHANTIPURUSH.pdf29 Sep 2025
Form 1File: Form 1 Architect Certificate.pdf28 Jul 2025
Form 2File: Form 2 Engineer Certificate.pdf28 Jul 2025
Form 3File: Form 3 CA Certificate.pdf28 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory.pdf28 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf24 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf18 Apr 2025
Disclosure of sold/ booked inventoryFile: sold book.pdf18 Apr 2025
Disclosure of sold/ booked inventoryFile: sold book new final.pdf28 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch shantipurush dec24 final.pdf21 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg shanti final.pdf21 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Shantipurush Dec24 sign stamp.pdf18 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A SHANTIPURUSH.pdf23 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 30 Form 3 Aarya Associates june 24.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 31 Form 3 Aarya Associates sept 24.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER SEPT24.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: NEW sold june 24 shantipurush.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: NEW SOLD.pdf17 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 SHANTIPURUSH 23-24.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch june 24 shantipurush.pdf10 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer june 24 shantipurush.pdf10 Oct 2024
Disclosure of sold/ booked inventoryFile: SOLD BOOK SHANTIPURUSH.pdf27 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT SHANTIPURUSH.pdf27 Jun 2024
Declaration about Commencement CertificateFile: FORM D (AARYA ASSOCIATES)MAR24.pdf26 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERT (AARYA ASSOCIATES)MAR24.pdf26 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGI CERT (AARYA ASSOCIATES)MAR24.pdf26 Apr 2024
Disclosure of sold/ booked inventoryFile: SOLD BOOK (AARYA ASSOCIATES)MAR24.pdf26 Apr 2024
Other - LegalFile: 1 Other - Finance.pdf8 Oct 2023
Other - TechnicalFile: 1 Other - Finance.pdf8 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Narendra Gurve CA Cert 1_compressed.pdf29 Sep 2023
CERSAI detailsFile: Cersai.pdf19 Sep 2023
Layout approvalFile: sanction plan.pdf14 Sep 2023
Building plan approvalFile: sanction plan.pdf14 Sep 2023
PAN CardFile: pan card.pdf14 Sep 2023
Copy of the legal title reportFile: TITLE REPORT.pdf14 Sep 2023
Details of encumbrances concerned to FinanceFile: FINANCIAL ENCUMBRANCE.pdf14 Sep 2023
Details of encumbrances concerned to FinanceFile: LEGAL ENCUMBRANCE.pdf14 Sep 2023
Details of encumbrances concerned to LegalFile: FINANCIAL ENCUMBRANCE.pdf14 Sep 2023
Details of encumbrances concerned to LegalFile: LEGAL ENCUMBRANCE.pdf14 Sep 2023
Copy of Layout Approval (in case of layout)File: sanction plan.pdf14 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: sanction plan.pdf14 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: commencement certificate.pdf14 Sep 2023
Declaration about Commencement CertificateFile: Declaration About Commencement Certificate.pdf14 Sep 2023
Declaration in FORM BFile: form b.pdf14 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A PARESH JOSHI.pdf14 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A NARENDRA GURVE.pdf14 Sep 2023
Proforma of Agreement for saleFile: Model - AFS - AMENDED - STD - (1).pdf14 Sep 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf14 Sep 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK DECLARATION.pdf14 Sep 2023
Deviation Report with respect to Allotment letterFile: DEVIATION IN ALLOTMENT LETTER.pdf14 Sep 2023
Deviation Report with respect to model copy of AgreementFile: IMG-20231113-WA0058.pdf14 Sep 2023
Other - LegalFile: mail.pdf14 Sep 2023
Other - FinanceFile: mail.pdf14 Sep 2023
Other - TechnicalFile: mail.pdf14 Sep 2023

How this compares with Nagpur

5%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHANTIPURUSH APARTMENT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near AMBAZARI2,800+ in Nagpur

2 kmSHANTIPURUSH APARTMENTCompleted 29Lapsed / revoked 15Other 39Dot size: filed unitsN

Filed coordinates, straight-line distance. 83 registered projects within 2 km.

Builder: AARYA ASSOCIATES

AARYA ASSOCIATES has 3 registrations on MahaRERA, including SANDHYARANG APARTMENTS and VASUNANDAN APARTMENTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if SHANTIPURUSH APARTMENT is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHANTIPURUSH APARTMENT?

The registered promoter entity is AARYA ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHANTIPURUSH APARTMENT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHANTIPURUSH APARTMENT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHANTIPURUSH APARTMENT?

The professionals named in the filing: Architect: SAURABH JAGDALE & ASSOCIATES; Engineer: SA; Engineer: NANDESH FIRKE; Chartered Accountant: Ashish Agrawal; Chartered Accountant: SUMIT CHANDWANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHANTIPURUSH APARTMENT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHANTIPURUSH APARTMENT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHANTIPURUSH APARTMENT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.