SHANTHALA SHRUTHI

By GANESH M P

RG-KA-57256 · RERA PRM/KA/RERA/1257/334/PR/200811/003510 · Last updated on RERA Karnataka portal: 4 Aug 2020

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Jun 2021Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 92 documents Report an error

SHANTHALA SHRUTHI is a Residential/Group Housing project by GANESH M P in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/200811/003510 on 11 Aug 2020. Possession is promised by 10 Jun 2021. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameSHANTHALA SHRUTHI
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/200811/003510
  • ReraGenie IDRG-KA-57256

Builder

  • NameGANESH M P
  • Entity typeCompany
  • Authorized SignatoryGANESH MP
  • Other registrations6 more →
  • Declared earlier projects16 →

Key dates

this monthRegisteredAug 2020First promiseSep 2020Revised toJun 2021

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on11 Aug 2020
  • Promised completion10 Jun 2021
  • Revised completionRevised to 10 Jun 2021 (originally 10 Sep 2020)
  • Buildings1 building record
  • Documents filed92 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHANTHALA SHRUTHI---32032

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 4 Aug 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

As on 4 Aug 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,376 sq m
Named landowners2
LandownerVillageDistrict
M KUMARESH--
GANESH MP--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 5.56 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMahesh M Kulshekar
EngineerH.G.Naiker

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionSep 2020 → Jun 2021

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed92

As listed on the registration, under the names the promoter filed them with; the newest 80 of 92 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/200811/003510 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Bank account in in project nameFile: BANK DETAILS.png4 Aug 2020
Bank account in in project nameFile: bank detail.pdf4 Aug 2020
fees paid receiptFile: RERA Payment Receipt.pdf6 Jul 2020
Balance SheetFile: Balance Sheet-converted.pdf6 Jul 2020
Profit and Loss account statmentFile: P&L-converted.pdf6 Jul 2020
Cash Flow Statement - 2017File: Cash Flow Statement-2017.pdf6 Jul 2020
Cash Flow Statement - 2018File: Cash Flow Statement 2018.pdf6 Jul 2020
Cash Flow Statement - 2019File: Cash Flow Statement 2019.pdf6 Jul 2020
Audit Report - 2017File: Audit Report 17.pdf6 Jul 2020
Audit Report - 2018File: Audit Report 18.pdf6 Jul 2020
Audit Report - 2019File: Audit Report 2019.pdf6 Jul 2020
E.C.File: E.C - 07.01.2019 to 28.06.2020.pdf6 Jul 2020
NOC- KSPCBFile: KSPCB - Shruthi-1-converted.pdf6 Jul 2020
MESCOMFile: MESCOM Power Supply-Shruthi-converted.pdf6 Jul 2020
BANK ACCOUNT DETAILSFile: BANK ACCOUNT DETAILS-converted.pdf6 Jul 2020
RERA Payment ReceiptFile: RERA Payment Receipt.pdf1 Jul 2020
Balance SheetFile: Balance Sheet-converted.pdf1 Jul 2020
Cash Flow Statement-2017File: Cash Flow Statement-2017.pdf1 Jul 2020
Cash Flow Statement-2018File: Cash Flow Statement 2018.pdf1 Jul 2020
Cash Flow Statement-2019File: Cash Flow Statement 2019.pdf1 Jul 2020
Audit Report 17File: Audit Report 17.pdf1 Jul 2020
Audit Report 18File: Audit Report 18.pdf1 Jul 2020
Audit Report 19File: Audit Report 2019.pdf1 Jul 2020
ECFile: EC-07.01.1989 to 07.01.2019.pdf1 Jul 2020
ECFile: E.C - 07.01.2019 to 28.06.2020.pdf1 Jul 2020
NOV- KSPCBFile: KSPCB - Shruthi-1-converted.pdf1 Jul 2020
MESCOMFile: MESCOM Power Supply-Shruthi-converted.pdf1 Jul 2020
CertificateFile: Trade Licence.pdf-
Licence Shruthi-
MCC PLAN COMBINED-
Existing Layout Plan-
RERA Sle Ded - Shruthi-converted-
RERA Agreement-Shruthi-converted-
sale deed-
MCC PLAN COMBINED-
MCC PLAN COMBINED-
Allotment leter-
BROCHURE-
Specification-
Encumbrance certificate-
Affidavit-
JD AFFIDAVIT CUM DECLARATION-
KHATA-
Collaboration agreement development agreementJoint development agreement other agreement-
Any Other Document (Right,Title,Interest,Name)-
Conversion compresspd-
Approval NOC U S 14 of the KTCP Act-
Utilization Certificate-
Trasfer of Development Right Certificate-
Relinquishment Deed-
FIRE NOC compresspd-
Airport Authority of India-
BESCOM-
BWSSB-
KSPCB-
SEIAA-
BSNL-
NOC in case of Building Proposal abutting to neibouring properties-
Unnamed document-
URBAN LAND CEILING-
DMRCL-
Bangalore Urban Arts Commission-
Inspector of Factories Controller of Explosive railway's-
District Magistrate-
Costal Regulation Zone Authority-
Stability Certificate-
MCC PLAN COMBINED-
Existing Layout Plan-
MCC PLAN COMBINED-
Conversion compresspd-
Unnamed document-
Balance Sheet 2018 - 2019File: BALANCE SHEET 2018-19.pdf-
Balance Sheet 2017 - 2018File: BALANCE SHEET 2017-18.pdf-
Balance Sheet 2016 - 2017File: BALANCE SHEET 2016-17.jpeg-
Audited Profit and Loss Statement 2018 - 2019File: PROFIT AND LOSS ACCOUNT 2018-19.pdf-
Audited Profit and Loss Statement 2017 - 2018File: PROFIT AND LOSS ACCOUNT 2017-18.pdf-
Audited Profit and Loss Statement 2016 - 2017File: PROFIT AND LOSS ACCOUNT 2016-17.jpeg-
Cash Flow Statement 2018 - 2019File: CASH FLOW STATEMENT 2018-19.pdf-
Cash Flow Statement 2017 - 2018File: CASH FLOW STATEMENT 2017-18.pdf-
Auditor's Report 2018 - 2019File: AUDITORS REPORT 2018-19.pdf-

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one moved by 9 months
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep SHANTHALA SHRUTHI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmSHANTHALA SHRUTHIOther 79Dot size: filed unitsN

Filed coordinates, straight-line distance. 79 registered projects within 2 km.

Builder: GANESH M P

GANESH M P has 7 registrations on RERA Karnataka, including CAPT. VIKRAM BATRA RESIDENCY and SHANTHALA SHRIRAM. Its filings declare 16 earlier projects, 15 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if SHANTHALA SHRUTHI is delayed beyond 10 Jun 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SHANTHALA SHRUTHI?

The registered promoter entity is GANESH M P, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SHANTHALA SHRUTHI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHANTHALA SHRUTHI?

The professionals named in the filing: Architect: Mahesh M Kulshekar; Engineer: H.G.Naiker. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHANTHALA SHRUTHI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHANTHALA SHRUTHI. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHANTHALA SHRUTHI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.