Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
SHAMBHAVI HEIGHTS is a Residential/Group Housing project by MAMATHA DEVELOPERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/180313/002645 on 13 Mar 2018. Possession is promised by 30 Sep 2021. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NameSHAMBHAVI HEIGHTS
- TypeResidential/Group Housing
- Location
- Mangalore
- Dakshina Kannada
- PincodeNot stated
- RERA no.PRM/KA/RERA/1257/334/PR/180313/002645
- ReraGenie IDRG-KA-58454
Builder
- NameMAMATHA DEVELOPERS
- Entity typePartnership Firm
- Authorized SignatoryPREMNATH R SHETTY
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on13 Mar 2018
- Promised completion30 Sep 2021
- Revised completionRevised to 30 Sep 2021 (originally 31 Dec 2020)
- Buildings1 building record
- Documents filed32 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHAMBHAVI HEIGHTS | - | - | - | 99 | 0 | 99 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | No | Not applicable |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | No | Not applicable |
| Emergency Evacuation services | Yes | - |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | No | Not applicable |
| Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | GOKULRAJ ASSOCIATES |
| Engineer | VIMAL ANIL |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed32
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/180313/002645 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: PAN198.pdf | - |
| BUILDING LICENSE199 | - |
| approved plan | - |
| approved plan | - |
| SALE DEED204 | - |
| sale agreement | - |
| Land Document | - |
| approved plan | - |
| single site layout226 | - |
| BROCHURE-SHAMBHAVI HEIGHTS217 | - |
| PROJECT-HIGH LIGHTS218 | - |
| EC200 | - |
| KHATHA | - |
| Land Document | - |
| conversion order | - |
| fire | - |
| single site layout226 | - |
| approved plan | - |
| Balance Sheet 2016 - 2017File: BALANCE SHEET 2016-17216.pdf | - |
| Balance Sheet 2015 - 2016File: BALANCE SHEET FY 2015-16212.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: INOME AND EXP 2016-17215.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: PROFIT AND LOSS FY2015-16213.pdf | - |
| Director's Report 2016 - 2017File: BALANCE SHEET 2016-17216.pdf | - |
| Director's Report 2015 - 2016File: BALANCE SHEET FY 2015-16212.pdf | - |
| Cash Flow Statement 2016 - 2017File: BALANCE SHEET 2016-17216.pdf | - |
| Cash Flow Statement 2015 - 2016File: BALANCE SHEET FY 2015-16212.pdf | - |
| Auditor's Report 2016 - 2017File: BALANCE SHEET 2016-17216.pdf | - |
| Auditor's Report 2015 - 2016File: BALANCE SHEET FY 2015-16212.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: IT ACK FY 2016-17214.pdf | - |
| Prospectus/BrochureFile: BROCHURE-SHAMBHAVI HEIGHTS217.pdf | - |
| Advertisement Copy 1File: BROCHURE-SHAMBHAVI HEIGHTS217.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1257_334_PR_180313_002645.xlsx | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dakshina Kannada
Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.
Keep SHAMBHAVI HEIGHTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dakshina Kannada620+ in Dakshina Kannada
ROHAN CITY
ROHAN CORPORATION INDIA PRIVATE LIMITED
Bearys Turning Point
Bearys Properties and Developments Private
YAMUNA SKY CITY
YAMUNA HOMES AND DESIGN PRIVATE LIMITED
The Marian Park
Marian Projects Pvt Ltd
Sai Matha Garden
Matha Developers Pvt Ltd
ROHAN MARINA ONE
ROHAN PLAZA PRIVATE LIMITED
See every Dakshina Kannada project, with the district possession charts
Builder: MAMATHA DEVELOPERS
MAMATHA DEVELOPERS has 1 registration on RERA Karnataka, including SHAMBHAVI HEIGHTS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.
Frequently asked questions
What are my rights if SHAMBHAVI HEIGHTS is delayed beyond 30 Sep 2021?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SHAMBHAVI HEIGHTS?
The registered promoter entity is MAMATHA DEVELOPERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SHAMBHAVI HEIGHTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SHAMBHAVI HEIGHTS?
The professionals named in the filing: Architect: GOKULRAJ ASSOCIATES; Engineer: VIMAL ANIL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHAMBHAVI HEIGHTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback