ReraGenieLog inGet a buyer report

Home / Browse projects / Dakshina Kannada, Karnataka / Shalimar Eden

Registration approved Residential/Group Housing project

Shalimar Eden

By Shalimar Realty Holdings

RG-KA-44278 · RERA PRM/KA/RERA/1257/334/PR/180328/002452

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2019Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 22 documents Report an error

Shalimar Eden is a Residential/Group Housing project by Shalimar Realty Holdings in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/180328/002452 on 28 Mar 2018. Possession is promised by 25 Dec 2019.

At a glance

Project

  • NameShalimar Eden
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1257/334/PR/180328/002452
  • ReraGenie IDRG-KA-44278

Builder

  • NameShalimar Realty Holdings
  • Entity typePartnership Firm
  • Authorized SignatoryAbdul Rahiman K
  • DirectorBasheer Ahmed K
  • Other registrations5 more →
  • Declared earlier projects7 →

Key dates

this monthRegisteredMar 2018PromisedDec 2019

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on28 Mar 2018
  • Promised completion25 Dec 2019
  • Revised completionNone
  • Buildings1 building record
  • Documents filed22 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shalimar Eden-----22

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area688 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.91 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAlam
EngineerK.Anil Hegde

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed22

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/180328/002452 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Registration.pdf-
Layout Plan-
Plan with Signature & Seal-
Layout Plan-
Sales Deed-
Layout Plan-
Sales Deed 2-
Layout Plan-
Project Area-
Brochure-
Project Area-
EC-
Katha-
JDA-
Conversion Order-
Layout Plan-
Layout Plan-
Prospectus/BrochureFile: Brochure.pdf-
Advertisement Copy 1File: shalimar advstesment copy.jpg-
Tower Excel SheetFile: PRM_KA_RERA_1257_334_PR_180328_002452 (1).xlsx-
Occupancy CertificateFile: Occupency Certificate.pdf-
Completion certificate issued by the competent authorityFile: Occupency Certificate.pdf-

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep Shalimar Eden on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

Builder: Shalimar Realty Holdings

Shalimar Realty Holdings has 6 registrations on RERA Karnataka, including Shalimar Eden and SHALIMAR GARDEN. Its filings declare 7 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if Shalimar Eden is delayed beyond 25 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Shalimar Eden?

The registered promoter entity is Shalimar Realty Holdings, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Shalimar Eden?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Shalimar Eden?

The professionals named in the filing: Architect: Alam; Engineer: K.Anil Hegde. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shalimar Eden?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shalimar Eden. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shalimar Eden to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.