Registration approved Residential/Group Housing project

Shalimar Ashraya

By Shalimar Realty Holdings

RG-KA-26753 · RERA PRM/KA/RERA/1257/334/PR/191031/002983

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Sep 2023Possession promisedmoved 21 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 47 documents Report an error

Shalimar Ashraya is a Residential/Group Housing project by Shalimar Realty Holdings in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/191031/002983 on 31 Oct 2019. Possession is promised by 30 Sep 2023. The completion date has moved by 21 months from the original filing.

At a glance

Project

  • NameShalimar Ashraya
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1257/334/PR/191031/002983
  • ReraGenie IDRG-KA-26753

Builder

  • NameShalimar Realty Holdings
  • Entity typePartnership Firm
  • Authorized SignatoryBasheer Ahmed K
  • OthersAbdul Rahiman K
  • Other registrations5 more →
  • Declared earlier projects7 →

Key dates

this monthRegisteredOct 2019First promiseDec 2021Revised toSep 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on31 Oct 2019
  • Promised completion30 Sep 2023
  • Revised completionRevised to 30 Sep 2023 (originally 31 Dec 2021)
  • Buildings1 building record
  • Documents filed47 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shalimar Ashraya---35035

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities42

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes-
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Water Tanks, Sumps And Other Electrical EquipmentYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,618 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 8.26 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAlams Associates
EngineerKrishna Shetty

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2021 → Sep 2022

No reason recorded in the filing

EX/PRM/KA/RERA/1257/334/PR/240306/002983Sep 2022 → Sep 2023

Reason as filed by the promoterShortage of Building Materials, Concrete, Jalli etc

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed47

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/191031/002983 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Incorporation Certificate.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Architect Completed Work Aashraya.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Completed Work Aashraya.pdf-
CA Certificate for Funds UtilizationFile: Shalimar Ashraya-Ex-3.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect Pending Work Aashraya.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer Pending Work Aashraya.pdf-
CA Certificate for Funds required for Project CompletionFile: Shalimar Ashraya-Ex-4.pdf-
AffidavitFile: Shalimar Ashraya-Affidavt-2.pdf-
Latest Encumbrance CertificateFile: Shalimar Ashraya-EC.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
BUILDING LICENCE-
APPROVED PLAN-3-
BUILDING LICENSE WITH PLAN-
WILLS-
APPROVED PLAN-3-
APPROVED PLAN-3-
Brochure-
SPECIFICATION-
EC (1)-
Sec 3(1) Non-violation affidavit-
JOINT DECLARATION AFFIDAVIT-
Katha-
JDA-
partnership deed and GPA-
Conversion order-
LICENSE PLAN WITH SPECIFICATION-
LICENSE PLAN WITH SPECIFICATION-
Balance Sheet 2018 - 2019File: Balance sheet 2017-18.pdf-
Balance Sheet 2017 - 2018File: Clarification about account.pdf-
Balance Sheet 2016 - 2017File: Clarification about account.pdf-
Audited Profit and Loss Statement 2018 - 2019File: P&L Statement 2017-18.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Clarification about account.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Clarification about account.pdf-
Director's Report 2018 - 2019File: Director Report-NA WITH CLARIFICATION - Copy.pdf-
Director's Report 2017 - 2018File: Clarification about account.pdf-
Director's Report 2016 - 2017File: Clarification about account.pdf-
Cash Flow Statement 2018 - 2019File: Cash Flow-NA WITH CLARIFICATION.pdf-
Cash Flow Statement 2017 - 2018File: Clarification about account.pdf-
Auditor's Report 2018 - 2019File: Auditor-NA WITH CLARIFICATION.pdf-
Auditor's Report 2017 - 2018File: Clarification about account.pdf-
Auditor's Report 2016 - 2017File: Clarification about account.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: ITRV 2017-18.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: Clarification about account.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: Clarification about account.pdf-
Form B-
Prospectus/BrochureFile: Broucher.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1257_334_PR_191031_002983.xlsx-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
Shalimar Garden-OngoingDec 2020Not delivered

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one moved by 21 months
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep Shalimar Ashraya on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

Builder: Shalimar Realty Holdings

Shalimar Realty Holdings has 6 registrations on RERA Karnataka, including Shalimar Eden and SHALIMAR GARDEN. Its filings declare 7 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if Shalimar Ashraya is delayed beyond 30 Sep 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Shalimar Ashraya?

The registered promoter entity is Shalimar Realty Holdings, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Shalimar Ashraya?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Shalimar Ashraya?

The professionals named in the filing: Architect: Alams Associates; Engineer: Krishna Shetty. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shalimar Ashraya?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shalimar Ashraya. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shalimar Ashraya to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.