SHALIGRAM TOWNSHIP
By SHREE YASHOMATI BUILDERS DEVELOPERS
RG-MH-28204 · RERA P99000025137 · Last updated on MahaRERA portal: 21 Apr 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 5 complaints at MahaRERA
- Completion date moved by 30 months
- 1 extension taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHALIGRAM TOWNSHIP is a Others project by SHREE YASHOMATI BUILDERS DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000025137 on 18 Mar 2020. Possession is promised by 30 Jun 2027. The completion date has moved by 30 months from the original filing. 18 of the 47 units on this registration are recorded sold or booked, and 9 of 33 construction stages are filed complete. 5 complaints are on record with the regulator.
At a glance
Project
- NameSHALIGRAM TOWNSHIP
- TypeOthers
- Location
- GENESIS INDUSTRIAL ROAD
- PADGHE
- Palghar
- 401501
- Pincode401501
- RERA no.P99000025137
- ReraGenie IDRG-MH-28204
Builder
- NameSHREE YASHOMATI BUILDERS DEVELOPERS
- Entity typePartnership
- PartnersCHANDRAKANT BALA MHATRE, KAMAL RAM JHA, GANESH NARAYAN PATIL, NIPEN CHANDRAMOHAN DEBNATH
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on18 Mar 2020
- Promised completion30 Jun 2027
- Revised completionRevised to 30 Jun 2027 (originally 30 Dec 2024)
- Buildings3 building records
- Documents filed18 files
Current status
Figures as on 21 Apr 2023, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING NO 1 WING-A TYPE-B2 | NA | 4 | 4 | 5 | 3 | 8 |
| BUILDING NO 1 WING-B TYPE-A | NA | 4 | 4 | 15 | 12 | 27 |
| BUILDING NO-1 WING-C TYPE-B3 | NA | 4 | 4 | 9 | 3 | 12 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 21 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 80%.
BUILDING NO 1 WING-A TYPE-B235%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 1 WING-B TYPE-A35%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO-1 WING-C TYPE-B335%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 21 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed7
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| BUILDING NO 1 WING-A TYPE-B2 | 1 | 2 | 3 |
| BUILDING NO 1 WING-B TYPE-A | 1 | 1 | 2 |
| BUILDING NO-1 WING-C TYPE-B3 | 1 | 1 | 2 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| SHALIGRAM BUILDERS AND DEVELOPERS | Vasai-Virar City (M Corp) | Palghar |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MR RAJESH Y SATGHARE |
| Engineer | MESHRAM & THUKRAL |
| Chartered Accountant | ASHWIN NAIR |
| Partner | Role in project |
|---|---|
| SHREE YASHOMATI BUILDERS DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDUE TO UNAVOIDABLE REASONS PROJECT COULD NOT BE COMPLETED BEFORE DUE DATE.
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000540747 | KUMUD ARJUN BHINGANIYA | UMESH NARENDRA RAI | 11/06/2024 |
| CC006000000231253 | sanjay ramkumar gupta | Umesh Rai | 21/05/2022 |
| CC006000000302994 | DURGA PRASAD RAJNARAYAN SHARMA | YASHWANT TEJBAHADUR SINGH | 09/12/2022 |
| CC006000000480313 | DURGA PRASAD RAJNARAYAN SHARMA | YASHWANT TEJBAHADUR SINGH | 30/04/2024 |
| CC12500642 | Dinesh Roshanlal Jain | SHREE YASHOMATI BUILDERS DEVELOPERS | 23/02/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 Mar 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Mar 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Mar 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Mar 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jun 2027
Documents filed18
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration about Commencement CertificateFile: FORM D.pdf | 21 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE-SHALIGRAM BUILDERS.pdf | 21 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE31032021.pdf | 21 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE31072022.pdf | 21 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE31032023.pdf | 21 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 21 Apr 2023 |
| Layout approvalFile: LAYOUT.pdf | 16 Mar 2020 |
| Building plan approvalFile: LAYOUT.pdf | 16 Mar 2020 |
| Copy of the legal title reportFile: TITLE CERTIFICATE_compressed.pdf | 16 Mar 2020 |
| Details of encumbrancesFile: loe.pdf | 16 Mar 2020 |
| Copy of Layout Approval (in case of layout)File: LAYOUT.pdf | 16 Mar 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: LAYOUT.pdf | 16 Mar 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: CC NEW_compressed.pdf | 16 Mar 2020 |
| Declaration in FORM BFile: form b COM.pdf | 16 Mar 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 16 Mar 2020 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 16 Mar 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3 COM.pdf | 16 Mar 2020 |
| Proforma of Allotment letterFile: PERFORMA.pdf | 16 Mar 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- All 18 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SHALIGRAM TOWNSHIP on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PADGHE3,200+ in Palghar
Birla Mrida
Birla Estates Private Limited
Roop Rajat Park Phase 3
MAHAVIR ASSOCIATES
AGAMI INFINITY PARK
MAYURESH REALTY PRIVATE LIMITED
Luxury Empire Township Phase I
VEENAA DEVELOPERS PRIVATE LIMITED
MAHAVIR ARCADE
MAHAVIR DEVELOPERS AND REALTORS
SHANTI VISTA - II
SHAH REALTY CORPORATION
See every Palghar project, with the district possession charts
Builder: SHREE YASHOMATI BUILDERS DEVELOPERS
SHREE YASHOMATI BUILDERS DEVELOPERS has 1 registration on MahaRERA, including SHALIGRAM TOWNSHIP. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if SHALIGRAM TOWNSHIP is delayed beyond 30 Jun 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHALIGRAM TOWNSHIP?
The registered promoter entity is SHREE YASHOMATI BUILDERS DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHALIGRAM TOWNSHIP?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SHALIGRAM TOWNSHIP?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SHALIGRAM TOWNSHIP?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHALIGRAM TOWNSHIP?
The professionals named in the filing: Architect: MR RAJESH Y SATGHARE; Engineer: MESHRAM & THUKRAL; Chartered Accountant: ASHWIN NAIR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHALIGRAM TOWNSHIP?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.