ReraGenieLog inGet a buyer report

Home / Browse projects / Jalgaon, Maharashtra / SHAKUNTALA HEIGHTS

Completed No litigation declared Others project

SHAKUNTALA HEIGHTS

By SHIV CONSTRUCTION

RG-MH-05115 · RERA P49900025213 · Last updated on MahaRERA portal: 21 Sep 2021

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.

See what the report covers Free either way: or have every new Jalgaon registration emailed to you, free during the pilot beta.
Mar 2022Possession promisedregistration recorded completed
8 of 11Construction stages donefurthest along: Installation of Lifts, 20%
0Complaints at MahaRERAon this registration
Jump to the 30 documents Report an error

SHAKUNTALA HEIGHTS is a Others project by SHIV CONSTRUCTION in Jalgaon, Maharashtra, registered with MahaRERA as P49900025213 on 23 Mar 2020. The registration is recorded completed; possession was promised by 30 Mar 2022.

At a glance

Project

  • NameSHAKUNTALA HEIGHTS
  • TypeOthers
  • Location
    • PIMPRALA SHIVAR
    • Pimprala
    • Jalgaon
    • 425001
  • Pincode425001
  • RERA no.P49900025213
  • ReraGenie IDRG-MH-05115

Builder

  • NameSHIV CONSTRUCTION
  • Entity typePartnership
  • PartnersHEMANT JAGANNATH NYATI, MANOJKUMAR GHANSHYAMDAS LADDHA, SHARMILA HEMANT NAYTI, SONALI PRASHANT MANTRI, ARUNA MANOJKUMAR LADHE, KAILAS RAMLAL KABARA
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredMar 2020PromisedMar 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Mar 2020
  • Promised completion30 Mar 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed30 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHAKUNTALA HEIGHTSNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Sep 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 20%.

SHAKUNTALA HEIGHTS: 75% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 21 Sep 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Open Space1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area497 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1267.35
Proposed, not sanctioned1,267 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCTS NO 2117/3, NAVI PETH , JALGAON 425001

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANAND MUKUND
EngineerUJVALCHAUDHARI
EngineerHEMANT NYATI
Chartered AccountantDARSHAN RAMESH JAIN
PartnerRole in project
SHIV CONSTRUCTION-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Dec 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Feb 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Feb 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Feb 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 21 Sep 2021

Documents filed30

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ground floor commercial with appendix I.pdf21 Sep 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 1st floor with appendix I.pdf21 Sep 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 1st floor with appendix I.pdf21 Sep 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2nd floor with appendix I.pdf21 Sep 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 3rd floor with appendix I.pdf21 Sep 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf2 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SIGN COPY FORM 1_20210428_151122.pdf2 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SIGN COPY FORM 2_20210428_151718.pdf2 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf2 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SIGN COPY FORM 2A_20210428_151506.pdf2 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf7 Nov 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf7 Nov 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A.pdf7 Nov 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf25 Jul 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf25 Jul 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A.pdf25 Jul 2020
Declaration in FORM BFile: form B sign.pdf11 Mar 2020
Details of encumbrancesFile: ENCUMBERANCE CERTIFICATE.pdf22 Feb 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf22 Feb 2020
Layout approvalFile: LAYOUT SHAKUNTALA HEIGHTS.pdf19 Feb 2020
Building plan approvalFile: BUILDING PLAN.pdf19 Feb 2020
Copy of Layout Approval (in case of layout)File: LAYOUT SHAKUNTALA HEIGHTS.pdf19 Feb 2020
Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN.pdf19 Feb 2020
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf19 Feb 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 arc certificate.pdf19 Feb 2020
PAN CardFile: PAN.pdf10 Dec 2019
Copy of the legal title reportFile: TITLE REPORT.pdf10 Dec 2019
Declaration in FORM BFile: AUTHORIZATION LETTERS.pdf10 Dec 2019
Proforma of Allotment letterFile: ANNEXURE A AFS.pdf10 Dec 2019
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf10 Dec 2019

How this compares with Jalgaon

5%of Jalgaon projects moved their completion datethis one has not
32%of Jalgaon registrations have lapsed or been cancelledthis one is completed

Computed across the 230+ Jalgaon projects on ReraGenie, from their own filings.

Keep SHAKUNTALA HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PIMPRALA SHIVAR230+ in Jalgaon

Builder: SHIV CONSTRUCTION

SHIV CONSTRUCTION has 2 registrations on MahaRERA, including NARAYANI PARK and SHAKUNTALA HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Jalgaon district page.

Frequently asked questions

What are my rights if SHAKUNTALA HEIGHTS is delayed beyond 30 Mar 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHAKUNTALA HEIGHTS?

The registered promoter entity is SHIV CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHAKUNTALA HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHAKUNTALA HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHAKUNTALA HEIGHTS?

The professionals named in the filing: Architect: ANAND MUKUND; Engineer: UJVALCHAUDHARI; Engineer: HEMANT NYATI; Chartered Accountant: DARSHAN RAMESH JAIN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHAKUNTALA HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHAKUNTALA HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHAKUNTALA HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.