SHAKTI ENCLAVE PHASE II

By SHAKTI PROPERTY DEVELOPERS PVT LTD

RG-MH-45758 · RERA P51800013105 · Last updated on MahaRERA portal: 24 Jun 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • 18 complaints at MahaRERA
  • Completion date moved by 15 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
5 of 11Construction stages donefurthest along: Internal walls, 90%
78 of 145Units unsoldnot recorded sold or booked
18Complaints at MahaRERAon this registration
Jump to the 97 documents Report an error

SHAKTI ENCLAVE PHASE II is a Commercial project by SHAKTI PROPERTY DEVELOPERS PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800013105 on 14 Sep 2017. Possession was promised by 11 Jun 2025 and is now 16 months past that date. The completion date has moved by 15 months from the original filing. 67 of the 145 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 18 complaints are on record with the regulator.

At a glance

Project

  • NameSHAKTI ENCLAVE PHASE II
  • TypeCommercial
  • Location
    • JAN KALYAN NAGAR
    • MALAD
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800013105
  • ReraGenie IDRG-MH-45758

Builder

  • NameSHAKTI PROPERTY DEVELOPERS PVT LTD
  • Entity typeCompany
  • GSTIN27AAECS8479E1ZX
  • Managing DirectorJITENDRA JAINATH MISHRA

Key dates

16 months past promisethis monthRegisteredSep 2017First promiseMar 2024Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Sep 2017
  • Promised completion11 Jun 2025
  • Revised completionRevised to 11 Jun 2025 (originally 30 Mar 2024)
  • Buildings1 building record
  • Documents filed97 files

Current status

46%67 of 145 units booked

Figures as on 24 Jun 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
R WINGNA28281450145

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

R WING: 94% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)80%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 24 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes60%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes60%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes10%
Open ParkingNoNot applicable

Parking filed5

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots5
Closed/Covered1
Open Space4

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,425 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
KAMALA MILLS LTDMumbai CityMumbai City
M/S DOTOM REALESTATEKurlaMumbai Suburban
M/S. DOTOM REALESTATEKurlaMumbai Suburban

Approvals and building plan

Sanctioning authoritySRA
Permissible FSI12730.52
Proposed, not sanctioned8,279 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKANDIVALI WEST

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDOT Architects
EngineerHM Raje Structural Consultants Pvt Ltd
Chartered AccountantMEHUL JAIN
PartnerRole in project
SHAKTI PROPERTY DEVELOPERS PVT LTD-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800018584Mar 2024 → Mar 2025

Reason as filed by the promoterBIGGER LAYOUT

EA02072501921Mar 2024 → Jun 2025

Reason as filed by the promoterOnly Full OC was pending which has been obtained. post facto.

Complaints filed with MahaRERA18

Case no.ComplainantRespondentFiled
CC006000000100245Samit JhaSHAKTI ENCLAVE / MR RAMESH GOVANI / MR RAVI BHANDARI22/07/2019
CC006000000110814Samit JhaRamesh Govani / Ravi Bhandari09/09/2019
CC006000000110825Mrs Rama JhaRamesh Govani / Ravi Bhandari09/09/2019
CC006000000110835Ramesh RaniRamesh Govani / Ravi Bhandari09/09/2019
CC006000000110831Kailash KanthariaRamesh Govani / Ravi Bhandari09/09/2019
CC006000000110838Maurice A FernadesRamesh Govani / Ravi Bhandari12/09/2019
CC006000000110841Nishant MahantaRamesh Govani / Ravi Bhandari09/09/2019
CC006000000110842Ajay AryaRamesh Govani / Ravi Bhanddari11/09/2019
CC006000000110852Rajesh PhansekarRamesh Govani / Ravi Bhandari10/09/2019
CC006000000110870Ashok Veljee IsharaniRamesh Govani / Ravi Bhandari11/09/2019
CC006000000110879Dilip G GandhiRamesh Govani / Ravi Bhandari12/09/2019
CC006000000110880Dilip G GandhiRamesh Govani / Ravi Bhandari12/09/2019
CC006000000195878Ketan Indravadan BhagatKamala Mills Limited05/02/2021
CC006000000197058Samit JhaRavi Bhandari26/05/2021
CC006000000303076GAUTAM G BHATIAKAMALA MILLS & MS SHAKTI PROPERTIES DEVELOPERS PVT LTD17/10/2022
CC12400972Pratap Janardan PawarKamala Mills Ltd02/12/2024
CC12500347Dotom Real Estate Through is Authorized SignatoryRatan Ramesh Gohil31/01/2025
CC12501346SUNITA G PATILSHAKTI PROPERTY DEVELOPERS PVT LTD23/04/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jan 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed97

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 97 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf24 Jun 2025
Form 2File: 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf24 Jun 2025
Disclosure of Sold and Booked InventoryFile: 7 Disclosure of sold_ booked inventory.pdf24 Jun 2025
Form 3File: 14 Certificates of CA (Form 3).pdf24 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 R.pdf17 Feb 2025
Certificates of CA (Form 3)File: Annexure D Form 3 - T Wing new.pdf17 Feb 2025
Certificates of CA (Form 3)File: Annexure D Form 3 - R Wing New.pdf17 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 R WING.pdf17 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA AR CERT- TOWER-R-5-4-2024.pdf6 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA CERT- TOWER-R-5-4-2024.pdf6 Jun 2024
Certificates of CA (Form 3)File: Annexure D Form 3 - R Wing Final.pdf6 Jun 2024
Certificates of CA (Form 3)File: Form 3 - Dotom Shakti Enclave.pdf6 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Cert - R Wing.pdf16 Jan 2024
Certificates of CA (Form 3)File: Annexure D Form 3 - R Wing Final (1).pdf16 Jan 2024
Details of encumbrancesFile: RERA encumberence letter R Wing.pdf9 Jan 2024
Proforma of Agreement for saleFile: UPDATE_2 (2) (1).pdf9 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ilovepdf_merged (32).pdf30 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) (1).pdf29 Dec 2023
Declaration in FORM BFile: Affidavit- R Wing Extension.pdf20 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf12 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf12 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf12 Oct 2023
Certificates of CA (Form 3)File: form 3 r.pdf12 Oct 2023
Certificates of CA (Form 3)File: form 3 r.pdf12 Oct 2023
Disclosure of sold/ booked inventoryFile: SK.pdf10 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Tower R - Ar Certificate - Jan March 23.pdf3 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: TOWER-R-Engineer CERT-Jan March 23.pdf3 Jul 2023
Certificates of CA (Form 3)File: Annexure D Form 3 - R Wing Final signed_compressed.pdf24 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: R Wing Certificate ASA.pdf24 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert Tower R.pdf14 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality assurance - Shakti Tower R_compressed.pdf14 Feb 2023
Certificates of CA (Form 3)File: Form 3 - R Wing_merged (1).pdf14 Feb 2023
Disclosure of sold/ booked inventoryFile: Dislosure of Sold Inventory- Shakti Enclave Phase II from 1st Aug, 2022 to 31st Aug, 2022.8 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's certificate (Shakti) R.pdf4 Nov 2022
Certificates of CA (Form 3)File: Form 3 - R Wing_merged.pdf4 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - DRE R wing Final (1).pdf4 Nov 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory- Shakti Enclave Phase II from 1st April to 31st March 2022.pd30 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Tower R - Architect Certificate_compressed.pdf23 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Tower R - Engineer Certificate.pdf23 Jul 2022
Certificates of CA (Form 3)File: ilovepdf_merged (4).pdf23 Jul 2022
Certificates of CA (Form 3)File: Annexure D Form 3 - R Wing Final_compressed.pdf22 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - DRE R wing Final.pdf22 May 2022
Disclosure of sold/ booked inventoryFile: Shakti Enclave Phase II.pdf5 May 2022
Disclosure of sold/ booked inventoryFile: r.pdf14 Mar 2022
CERSAI detailsFile: 1 CERSAI details.pdf14 Mar 2022
Proforma of Allotment letterFile: Draft Agreement for Sale- Shakti Enclave Phase II- pdf_compressed.pdf24 Jan 2022
Building plan approvalFile: ilovepdf_merged (4)_compressed.pdf22 Jan 2022
Building plan approvalFile: ilovepdf_merged (5)_compressed.pdf22 Jan 2022
Building plan approvalFile: ilovepdf_merged (6)_compressed.pdf22 Jan 2022
Building plan approvalFile: ilovepdf_merged (7)_compressed.pdf22 Jan 2022
Building plan approvalFile: AMENDED IOA .pdf22 Jan 2022
Building Plan Approval (IOD)File: AMENDED IOA .pdf22 Jan 2022
Building Plan Approval (IOD)File: ilovepdf_merged (4)_compressed.pdf22 Jan 2022
Building Plan Approval (IOD)File: ilovepdf_merged (5)_compressed.pdf22 Jan 2022
Building Plan Approval (IOD)File: ilovepdf_merged (6)_compressed.pdf22 Jan 2022
Building Plan Approval (IOD)File: ilovepdf_merged (7)_compressed.pdf22 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archi.pdf21 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG.pdf21 Jan 2022
Certificates of CA (Form 3)File: FORM 3.pdf21 Jan 2022
Details of encumbrancesFile: Kaagaz-20220105-123050607345 (2).pdf5 Jan 2022
Disclosure of sold/ booked inventoryFile: disclosure_compressed.pdf9 Nov 2021
OtherFile: undertaking.pdf9 Nov 2021
Disclosure of sold/ booked inventoryFile: ilovepdf_merged (4).pdf30 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 - 2017-18_page-0001.pdf30 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - 2018-19_page-0001.pdf30 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 -2019-20_page-0001.pdf30 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - 2020-21_page-0001.pdf30 Oct 2021
Declaration about Commencement CertificateFile: DECLARATION.pdf29 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance for Tower R_compressed.pdf29 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance for Tower R_compressed.pdf29 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: Extended CC.pdf20 Aug 2020
Layout approvalFile: Malad shakt phase plan.pdf31 Aug 2017
Layout approvalFile: IOD Layout plan.pdf31 Aug 2017
Building plan approvalFile: IOD1.pdf31 Aug 2017
Building plan approvalFile: IOD2.pdf31 Aug 2017
Building plan approvalFile: IOD Plan 1.pdf31 Aug 2017
Building plan approvalFile: IOD Plan 3.pdf31 Aug 2017
Building plan approvalFile: IOD Plan 4.pdf31 Aug 2017
Copy of the legal title reportFile: Malad Shakti - Title Certificate.pdf31 Aug 2017
Details of encumbrancesFile: SHAKTI - ENCUMBRANCE.pdf31 Aug 2017

How this compares with Mumbai Suburban

46%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 15 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHAKTI ENCLAVE PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MALAD6,700+ in Mumbai Suburban

2 kmSHAKTI ENCLAVE PHASE IICompleted 72Lapsed / revoked 49Other 95Dot size: filed unitsN

Filed coordinates, straight-line distance. 216 registered projects within 2 km.

Builder: SHAKTI PROPERTY DEVELOPERS PVT LTD

SHAKTI PROPERTY DEVELOPERS PVT LTD has 1 registration on MahaRERA, including SHAKTI ENCLAVE PHASE II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that SHAKTI ENCLAVE PHASE II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHAKTI ENCLAVE PHASE II is delayed beyond 11 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHAKTI ENCLAVE PHASE II?

The registered promoter entity is SHAKTI PROPERTY DEVELOPERS PVT LTD, a company as per the filing. Its GSTIN 27AAECS8479E1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHAKTI ENCLAVE PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SHAKTI ENCLAVE PHASE II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SHAKTI ENCLAVE PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHAKTI ENCLAVE PHASE II?

The professionals named in the filing: Architect: DOT Architects; Engineer: HM Raje Structural Consultants Pvt Ltd; Chartered Accountant: MEHUL JAIN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHAKTI ENCLAVE PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHAKTI ENCLAVE PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHAKTI ENCLAVE PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.