Home / Browse projects / Sangli, Maharashtra / SHAKTI APARTMENT

Completed No litigation declared Residential / Group Housing project

SHAKTI APARTMENT

By DEEPAK GANESH PETKAR

RG-MH-16746 · RERA P53100029574 · Last updated on MahaRERA portal: 17 Feb 2023

Source: official MahaRERA filing

Red flags

  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.
Aug 2022Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 43 documents Report an error

SHAKTI APARTMENT is a Residential / Group Housing project by DEEPAK GANESH PETKAR in Sangli, Maharashtra, registered with MahaRERA as P53100029574 on 4 Jun 2021. The registration is recorded completed; possession was promised by 31 Aug 2022.

At a glance

Project

  • NameSHAKTI APARTMENT
  • TypeResidential / Group Housing
  • Location
    • TAKSHILA SCHOOL ROAD
    • KABAJ PLOT NEAR RAMKRISHNA PARMHANS SOCIETY
    • Sangli Miraj Kupwad (M Corp.)
    • Miraj
    • Sangli
    • 416416
  • Pincode416416
  • RERA no.P53100029574
  • ReraGenie IDRG-MH-16746

Builder

  • NameDEEPAK GANESH PETKAR
  • Entity typeIndividual
  • Named personsDEEPAK GANESH PETKAR, RATAN VISHWANATH YADAV

Key dates

this monthRegisteredJun 2021PromisedAug 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on4 Jun 2021
  • Promised completion31 Aug 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed43 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHAKTI APARTMENTNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

SHAKTI APARTMENT: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 17 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed10

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots10
Closed/Covered6
Open Space4

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area291 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
DEEPAK GANESH PETKARSangli Miraj Kupwad (M Corp.)Sangli
Ratan Vishwanath YadavMumbai CityMumbai City

Approvals and building plan

Permissible FSI366.3
Proposed, not sanctioned366 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNEAR GANPATI TEMPLE VISHRAMBAG

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAMBER M SHINDE
EngineerSWAPNIL RAJARAM PAWAR
Chartered AccountantSHAJMAL F MULLICK
Chartered AccountantRushabh M Lodha
PartnerRole in project
DEEPAK GANESH PETKAR-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT53100012793Aug 2022 → Mar 2023

Reason as filed by the promoterThe said project work could not be done on the time due to local labor and material problems. The said project is progressing towards the direction of completion. We estimate that it will take another 7 months to complete whole work. Due to completion date we have given before, we are facing difficulty for documentary work required for progress of said project. So I request you to give extension for above mentioned project. We assure that, we will complete said project in that period absolutely

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 May 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Mar 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Mar 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Jan 2023

Documents filed43

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: Shakti Declaration Deed.pdf17 Feb 2023
Status of ConveyanceFile: Shakti Declaration Deed.pdf17 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shakti Dec 22 Engineer Certificate .pdf11 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shakti Dec 22 CA Certificate Min.pdf11 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shakti Dec 22 Architect Certificate.pdf7 Jan 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Shakti Completion Certificate .pdf7 Jan 2023
Architect’s Certificate on Completion of Project (Form 4)File: Shakti Architect Completion Certificate .pdf7 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Shakti Annual Audit Report 2022.pdf24 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shakti June 22 CA Certificate.pdf23 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shakti Sep 22 CA Certificate.pdf23 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shakti June 22 Architect Certificate.pdf18 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shakti Sep 22 Architect Certificate.pdf18 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shakti June 22 Engineer Certificate.pdf18 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shakti Sep 22 Engineer Certificate.pdf18 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Shakti March 22 Quality Assurance Certificate.pdf18 Nov 2022
Disclosure of sold/ booked inventoryFile: Shakti Disclosure of Sold Inventory.pdf18 Nov 2022
Proforma of Agreement for saleFile: Shakti Agreement for sale.pdf9 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shakti Dec 21 Architect Certificate.pdf6 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shakti March 22 Architect Certificate.pdf6 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shakti June 22 Architect Certificate.pdf6 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shakti Dec 21 Engineer Certificate.pdf6 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shakti March 22 Engineer Certificate.pdf6 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Shakti March 22 Quality Assurance Certificate.pdf6 Oct 2022
CERSAI detailsFile: CERSAI_Search_Report_200249053995_For_Asset_Based_Search_06_10_2022_21_12_52_519.pdf6 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shakti Dec 21 CA Certificate min.pdf6 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shakti March 22 CA Certificate min.pdf6 Oct 2022
Declaration about Commencement CertificateFile: Shakti Declaration of Commencement.pdf30 Nov 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shakti Architect Certificate sep 21 final.pdf30 Nov 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shakti Engineer Certificate sep 21.pdf30 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Shakti Quality Assurance Certificate Sep 21.pdf30 Nov 2021
PAN CardFile: Shakti PAN Deepak Cor1.pdf23 May 2021
Copy of the legal title reportFile: Shakti Revised Search Report Cor1.pdf23 May 2021
Declaration in FORM BFile: Shakti Yadav Form B Cor1.pdf23 May 2021
Details of encumbrancesFile: Shakti Encumbrances Certificate.pdf9 Mar 2021
Building plan approvalFile: Shakti Blueprint.pdf5 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: Shakti Blueprint.pdf5 Mar 2021
Declaration in FORM BFile: Shakti Declaration Form B.pdf5 Mar 2021
Layout approvalFile: Shakti Sanctioned Layout.pdf4 Mar 2021
Copy of the legal title reportFile: Shakti Search Report.pdf4 Mar 2021
Copy of Layout Approval (in case of layout)File: Shakti Sanctioned Layout.pdf4 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: Shakti Commencement Certificate.pdf4 Mar 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shakti CA Certificate.pdf4 Mar 2021
Proforma of Allotment letterFile: Shakti Allotment and Agreement Draft.pdf4 Mar 2021

How this compares with Sangli

11%of Sangli projects moved their completion datethis one has not
29%of Sangli registrations have lapsed or been cancelledthis one is completed

Computed across the 790+ Sangli projects on ReraGenie, from their own filings.

Keep SHAKTI APARTMENT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KABAJ PLOT NEAR RAMKRISHNA PARMHANS SOCIETY790+ in Sangli

Builder: DEEPAK GANESH PETKAR

DEEPAK GANESH PETKAR has 1 registration on MahaRERA, including SHAKTI APARTMENT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sangli district page.

Frequently asked questions

What are my rights if SHAKTI APARTMENT is delayed beyond 31 Aug 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHAKTI APARTMENT?

The registered promoter entity is DEEPAK GANESH PETKAR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHAKTI APARTMENT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHAKTI APARTMENT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHAKTI APARTMENT?

The professionals named in the filing: Architect: AMBER M SHINDE; Engineer: SWAPNIL RAJARAM PAWAR; Chartered Accountant: SHAJMAL F MULLICK; Chartered Accountant: Rushabh M Lodha. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHAKTI APARTMENT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHAKTI APARTMENT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHAKTI APARTMENT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.