Home / Browse projects / Mumbai City, Maharashtra / SHAHID NAGAR
SHAHID NAGAR
RG-MH-23957 · RERA P51900002527 · Last updated on MahaRERA portal: 16 Jan 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 42 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHAHID NAGAR is a Others project by NEUMEC AND SANGAM JV in Mumbai City, Maharashtra, registered with MahaRERA as P51900002527 on 1 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 42 months from the original filing. 18 of the 39 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.
At a glance
Project
- NameSHAHID NAGAR
- TypeOthers
- Location
- 207 REGENT CHAMBER
- NARIMAN POINT
- Mumbai City
- 400021
- Pincode400021
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900002527
- ReraGenie IDRG-MH-23957
Builder
- NameNEUMEC AND SANGAM JV
- Entity typeOthers
- Named personsNEUMEC BUILDER AND DEVELOPER`, Neumec Development & Allied Services Pvt Ltd
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on1 Aug 2017
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 30 Jun 2024)
- Buildings1 building record
- Documents filed160 files
Current status
Figures as on 16 Jan 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHAHID NAGAR | NA | 8 | 3 | 0 | 39 | 39 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 16 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 95%.
SHAHID NAGAR: 90% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 95% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 16 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 95% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed55
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Chartered Accountant | Rutuja Narsingh & Associates |
| Partner | Role in project |
|---|---|
| NEUMEC AND SANGAM JV | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe delay in the completion of the project has occurred due to several unforeseen challenges, primarily: 1. Impact of the COVID-19 Pandemic: The pandemic caused significant disruptions, including delays in the remobilization of workers after the lockdowns and travel restrictions were lifted, resulting in labor shortages and hindering the progress of the project. In addition to the above, the delay has also been caused by procurement issues, unforeseen site conditions, coordination challenges. We are pleased to inform you that the project is now 100% completed. We are in the process of applying
Reason as filed by the promoterI, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P51900002527. As per HEARING DATED 3rd November 2025, Hon'ble Shri Manoj Saunik Sir granted Extension upto 31.12.2027. The order is uploaded in Other Tab for your reference
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 14 Nov 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 11 Sep 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 11 Sep 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed160
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 160 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Dec 2024.pdf | 16 Jan 2026 |
| Withdrawal Update Form 2File: _Form_2__Mar_24.pdf | 16 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 - Shahid Nagar as on June 2025 (SIGNED).pdf | 16 Jan 2026 |
| Commencement certificateFile: NB___D_Shahid_Nagar_CC_Composit_Bldg_No1_31-07-2024 (2).pdf | 11 Sep 2025 |
| Building plan approvalFile: N_B_D_Shahid_Nagar_Bldg_NO-1_IOD_with_Plan_31-07-2024.pdf | 11 Sep 2025 |
| Withdrawal Update Form 1File: Form 1 Dec 2024.pdf | 11 Sep 2025 |
| Withdrawal Update Form 1File: Form 1 Dec 2024.pdf | 11 Sep 2025 |
| Withdrawal Update Form 2File: _Form_2__Mar_24.pdf | 11 Sep 2025 |
| Withdrawal Update Form 2File: _Form_2__Mar_24.pdf | 11 Sep 2025 |
| Withdrawal Update Form 3File: Form 3 - Shahid Nagar as on June 2025.pdf | 11 Sep 2025 |
| Withdrawal Update Form 3File: Form 3 - Shahid Nagar as on June 2025 (SIGNED).pdf | 11 Sep 2025 |
| Certificates of CA (Form 3)File: Form 3 - Shahid Nagar as on March 2025.pdf | 2 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Shahid Nagar as on March 2025.pdf | 2 May 2025 |
| Disclosure of sold/ booked inventoryFile: Circular_-_29.pdf | 29 Mar 2025 |
| Other - TechnicalFile: PERT Shahid nagar.pdf | 29 Mar 2025 |
| Other - TechnicalFile: Pert chart.pdf | 29 Mar 2025 |
| Declaration in FORM BFile: Form-B.pdf | 28 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec 2024.pdf | 28 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3 Dec 2024_compressed.pdf | 28 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 December 2024.pdf | 28 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Circular 29 Dec 2024.pdf | 28 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3 of Shahid Nagar as on 30-09-2024.pdf | 18 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3 of Shahid Nagar as on 31-12-2024.pdf | 18 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Shahid Nagar as on 31-12-2024.pdf | 18 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Shahid Nagar as on 30-09-2024.pdf | 18 Jan 2025 |
| Layout approvalFile: Copy of Layout.pdf | 14 Nov 2024 |
| Building plan approvalFile: 1.pdf | 14 Nov 2024 |
| Building plan approvalFile: 2.pdf | 14 Nov 2024 |
| Building plan approvalFile: 3.pdf | 14 Nov 2024 |
| Building plan approvalFile: 4.pdf | 14 Nov 2024 |
| Building plan approvalFile: 5.pdf | 14 Nov 2024 |
| Building plan approvalFile: 6.pdf | 14 Nov 2024 |
| Building plan approvalFile: 7.pdf | 14 Nov 2024 |
| Building plan approvalFile: 8.pdf | 14 Nov 2024 |
| Building plan approvalFile: 9.pdf | 14 Nov 2024 |
| Copy of Layout Approval (in case of layout)File: Copy of Layout.pdf | 14 Nov 2024 |
| Building Plan Approval (IOD)File: 2.pdf | 14 Nov 2024 |
| Building Plan Approval (IOD)File: 9.pdf | 14 Nov 2024 |
| Building Plan Approval (IOD)File: 8.pdf | 14 Nov 2024 |
| Building Plan Approval (IOD)File: 7.pdf | 14 Nov 2024 |
| Building Plan Approval (IOD)File: 6.pdf | 14 Nov 2024 |
| Building Plan Approval (IOD)File: 5.pdf | 14 Nov 2024 |
| Building Plan Approval (IOD)File: 4.pdf | 14 Nov 2024 |
| Building Plan Approval (IOD)File: 3.pdf | 14 Nov 2024 |
| Building Plan Approval (IOD)File: 1.pdf | 14 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Shahid Nagar as on Sep 2024.pdf | 29 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form_5_-_Shahid_Nagar_for_FY_2018-19_11zon.pdf | 25 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form_5_-_Shahid_Nagar_for_FY_2019-20_11zon.pdf | 25 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form_5_-_Shahid_Nagar_for_FY_2020-21_11zon.pdf | 25 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Oct 24.pdf | 23 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 Jun 24 (2)_11zon.pdf | 17 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Jun 24 (2).pdf | 17 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf | 17 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Circular 29.pdf | 17 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22_11zon.pdf | 17 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23_11zon.pdf | 17 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24.pdf | 17 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Shahid Nagar as on June 2024.pdf | 15 Oct 2024 |
| Building plan approvalFile: pl.pdf | 14 Oct 2024 |
| Building plan approvalFile: plm.pdf | 14 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 of Shahid Nagar as on 30-06-2024.pdf | 14 Oct 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Binder1_11zon.pdf | 14 Oct 2024 |
| Building Plan Approval (IOD)File: plm.pdf | 14 Oct 2024 |
| Building Plan Approval (IOD)File: pl.pdf | 14 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form2A-2019-20.pdf | 12 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form2A-2021-22.pdf | 12 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2A-2023-24.pdf | 12 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A-2022-23.pdf | 12 Aug 2024 |
| Certificates of CA (Form 5)File: Form 5 17-18.pdf | 12 Aug 2024 |
| Declaration in FORM BFile: AFFIDAVIT_CUM_DECLARATION_-_SANGAM_JV.pdf | 9 Aug 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: _Form_2__Mar_24.pdf | 9 Aug 2024 |
| Certificates of CA (Form 3)File: _Form_3__Mar_24.pdf | 9 Aug 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE_A_FORMAT_N.pdf | 9 Aug 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: _Form_5___FY_2021-22_.pdf | 9 Aug 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: _Form_5___FY_2022-23_.pdf | 9 Aug 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT_A.pdf | 9 Aug 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf | 20 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf | 20 Jul 2024 |
| Certificates of CA (Form 3)File: 12 Certificates of CA (Form 3).pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Circular 29 - Shahid Nagar as on March 2024.pdf | 10 Jun 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai City
Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 160 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SHAHID NAGAR on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NARIMAN POINT780+ in Mumbai City
Filed coordinates, straight-line distance. 8 registered projects within 2 km.
COMPOSITE BUILDING NO2
NEUMEC AND SANGAM JV
Mittal Avenue
Vedaang Builders LLP
Netarwala Compound
Mukon Constructions Pvt. Ltd.
OM GuruKrupa SRA CHS Prop Phase 1
Moss Realtors Pvt Ltd
NATHANI HEIGHTS SALE
Nathani Parekh Constructions Private Limit
AARADHYA AVAAN
SHREEPATI SKIES (R R CHATURVEDI)
See every Mumbai City project, with the district possession charts
Builder: NEUMEC AND SANGAM JV
NEUMEC AND SANGAM JV has 2 registrations on MahaRERA, including SHAHID NAGAR and COMPOSITE BUILDING NO2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.
Frequently asked questions
What are my rights if SHAHID NAGAR is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHAHID NAGAR?
The registered promoter entity is NEUMEC AND SANGAM JV, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHAHID NAGAR?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHAHID NAGAR?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHAHID NAGAR?
The professionals named in the filing: Chartered Accountant: Rutuja Narsingh & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHAHID NAGAR?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback