RG-KA-33795 · RERA PRM/KA/RERA/1257/334/PR/220521/004885 · Last updated on RERA Karnataka portal: 31 Jan 2022

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Nov 2020Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 76 documents Report an error

SHAFCON RESIDENCY is a Residential/Group Housing project by SHAFCON in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/220521/004885 on 21 May 2022. Possession is promised by 18 Nov 2020.

At a glance

Project

  • NameSHAFCON RESIDENCY
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/220521/004885
  • ReraGenie IDRG-KA-33795

Builder

  • NameSHAFCON
  • Entity typePartnership Firm
  • Authorized SignatorySafi Umar Rehaman
  • OthersAyisha Shahanaz
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

Registered
21 May 2022
Promised
18 Nov 2020

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 May 2022
  • Promised completion18 Nov 2020
  • Revised completionNone
  • Buildings1 building record
  • Documents filed76 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHAFCON RESIDENCY---32032

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 31 Jan 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

As on 31 Jan 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes-
Outer WallNoNot applicable
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,215 sq m
Named landowners1
LandownerVillageDistrict
B K Mohammed Hassan--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 5.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSafi Umar Rehaman
EngineerMohammed Rahil Azeez

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed76

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/220521/004885 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Requesting letter for violation of RERA actFile: RERA (Violation) letter.pdf31 Jan 2022
proforma of Agreement of SaleFile: proforma AOS.pdf27 Jan 2022
proforma sale deedFile: proforma sale deed.pdf27 Jan 2022
Proforma of Allotment LetterFile: proforma allotment.pdf27 Jan 2022
Brochure of Current ProjectFile: SHAFCON Residency broucher.pdf27 Jan 2022
Sold and unsold detailsFile: sold&unsold unit.pdf27 Jan 2022
self-attested copy of KSPCB NOCFile: NOC PCB.pdf27 Jan 2022
specificationFile: SPECIFICATIONS (1).pdf27 Jan 2022
water nocFile: WATERNOC SHAFCON.pdf27 Jan 2022
clarificationFile: clarification.pdf27 Jan 2022
Bank account name should be as per bank account direction circularFile: bank passbook.jpg18 Jan 2022
EC FROM 2004 TO 2021File: EC 2004 to 2021.pdf18 Jan 2022
POLLUTION NOCFile: pollution noc.pdf18 Jan 2022
STP IN APPROVED PLANFile: shafcon-approved-plan.jpg18 Jan 2022
STP DRAWINGFile: STP drawing.pdf18 Jan 2022
WATER NOCFile: Water NOC Shafcon.pdf18 Jan 2022
APPROVED PLAN PDFFile: shafcon-approved-plan.pdf18 Jan 2022
BANK PASSBOOKFile: bank passbook.pdf18 Jan 2022
CLARIFICATIONFile: Clarification.pdf18 Jan 2022
previous project detailsFile: project details.pdf6 Oct 2021
bank account name should be as per bank account direction circularFile: BANK Declaration SHAFCON.pdf6 Oct 2021
form-bFile: form b.pdf6 Oct 2021
bank account name should be as per bank account direction circularFile: BANK Declaration SHAFCON.pdf22 Sep 2021
EC from 01-04-2005 to till dateFile: SHAFCON Clarification.pdf22 Sep 2021
project end date in form- BFile: Form B SHAFCON.pdf22 Sep 2021
list of allottees, sold and unsold details of allotteesFile: SHAFCON Affidavit.pdf22 Sep 2021
KSPCBFile: SHAFCON - KSPCB.pdf22 Sep 2021
Water supplyFile: WATER NOC.jpeg22 Sep 2021
Power supply authoritiesFile: Power supply NOC SHAFCON.pdf22 Sep 2021
clarification by promoterFile: SHAFCON Clarification.pdf22 Sep 2021
previous project detailsFile: SHAFCON Clarification.pdf22 Sep 2021
JD declarationFile: JD Declaration Shafcon.pdf6 Sep 2021
Approved planFile: Licence Plan Shafco.pdf6 Sep 2021
Form BFile: FORM B Shafcon.pdf6 Sep 2021
Occupancy certificateFile: Occupancy Shafcon.pdf6 Sep 2021
Power Board inspectionFile: Electrical Inspection Shafcon.pdf6 Sep 2021
AffidavitFile: Affidavit Shafcon.pdf6 Sep 2021
Area ChartFile: Area chart Shafcon.pdf6 Sep 2021
CertificateFile: REGISTRATION FIRM CERTIFICATE.pdf-
Bldg License Shafcon-
Licence Plan Shafcon Residency-1-
Sale deed & RTC-
SHAFCON Residency-
Shafcon Specification-
EC Shafcon-
KATHA-
JD Agreement Shafcon-
Occupancy Shafcon-
CC Shafcon-
Unnamed document-
Single site-
Fire NOC Shafcon-
Unnamed document-
Unnamed document-
CC Shafcon-
Legal opinion Shafcon-
Balance Sheet 2019 - 2020File: Balance sheet 03-20.pdf-
Balance Sheet 2018 - 2019File: Balance Sheet 03-19.pdf-
Balance Sheet 2017 - 2018File: Balance sheet 03-18.pdf-
Audited Profit and Loss Statement 2019 - 2020File: PL 03-20.pdf-
Audited Profit and Loss Statement 2018 - 2019File: PL 03-19.pdf-
Audited Profit and Loss Statement 2017 - 2018File: IT 18-19.pdf-
Auditor's Report 2019 - 2020File: Audit 19-20.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: IT 20-21.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: IT 19-20.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: IT 18-19.pdf-
Appeal 1 Order CopyFile: 5155.jpeg-
Appeal 2 Order CopyFile: safcon.pdf-
Prospectus/BrochureFile: SHAFCON Residency broucher.pdf-
Tower Excel SheetFile: PRMKARERA1257334PR220521004885.xlsx-
Occupancy CertificateFile: Occupancy Shafcon.pdf-
Architect certificate for having completed the work(in format no 5)File: FORM 5 COMPLETION.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: FORM 4CC SR.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit-declaration SR.pdf-
ENGINEER CERTIFICATEFile: FORM 6 COMPLETION.pdf-
COMPLETION CERTIIFCATEFile: completion certificate.pdf-

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep SHAFCON RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmSHAFCON RESIDENCYOther 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: SHAFCON

SHAFCON has 2 registrations on RERA Karnataka, including SHAFCON EDEN GARDEN and SHAFCON RESIDENCY. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if SHAFCON RESIDENCY is delayed beyond 18 Nov 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SHAFCON RESIDENCY?

The registered promoter entity is SHAFCON, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SHAFCON RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHAFCON RESIDENCY?

The professionals named in the filing: Architect: Safi Umar Rehaman; Engineer: Mohammed Rahil Azeez. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHAFCON RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHAFCON RESIDENCY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHAFCON RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.