Registered No litigation declared Residential / Group Housing project

SERENITY 2

By MAINCO REALTY LLP

RG-MH-73716 · RERA P52000017716 · Last updated on MahaRERA portal: 30 Apr 2025

Source: official MahaRERA filing

Red flags

  • 4 complaints at MahaRERA
  • Completion date moved by 48 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jul 2028Possession promisedmoved 48 months from the original
4 of 11Construction stages donefurthest along: Internal walls, 85%
4Complaints at MahaRERAon this registration
Jump to the 217 documents Report an error

SERENITY 2 is a Residential / Group Housing project by MAINCO REALTY LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000017716 on 6 Sep 2018. Possession is promised by 31 Jul 2028. The completion date has moved by 48 months from the original filing. 4 complaints are on record with the regulator.

At a glance

Project

  • NameSERENITY 2
  • TypeResidential / Group Housing
  • Location
    • KHOPOLI
    • Khalapur
    • Raigarh
    • 410203
  • Pincode410203
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000017716
  • ReraGenie IDRG-MH-73716

Builder

  • NameMAINCO REALTY LLP
  • Entity typePartnership
  • GSTIN27AAVFM7462K1ZE
  • PartnersESMAIL ALI MOHAMMED SHAFI MERCHANT, MARIAM MOHAMMED SHAFI MERCHANT, MOHAMMED SHAFI ISMAIL MERCHANT, PARVEEN SALIM MANSURI
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2018First promiseJul 2024Revised toJul 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on6 Sep 2018
  • Promised completion31 Jul 2028
  • Revised completionRevised to 31 Jul 2028 (originally 31 Jul 2024)
  • Buildings1 building record
  • Documents filed217 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SERENITY 2NA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 85%.

SERENITY 2: 62% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,629 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on3 Sep 2024

Approvals and building plan

Permissible FSI2279.92
Proposed, not sanctioned1,629 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVERSOVA MUMBAI 400 061

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
MAINCO REALTY LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000024468Jul 2024 → Jul 2028

Reason as filed by the promoterRespected Sir/Madam, We hereby submit our request for an extension of the registration for our project Serenity 2 due to unforeseen and unavoidable circumstances that have significantly impacted project progress. The primary reasons for the delay are as follows: 1. Non-Availability of Sand: The unavailability of construction-grade sand due to regulatory restrictions and supply chain disruptions has resulted in delays in critical construction activities. Despite our efforts to source alternative materials and suppliers, procurement challenges have persisted, leading to interruptions in the cons

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC12603066Mathew Anthony ThattilMAINCO REALTY LLP23/05/2026
CC12603069Mathew Anthony ThattilMAINCO REALTY LLP23/05/2026
CC12603070Mathew Anthony ThattilMAINCO REALTY LLP23/05/2026
CC12603072Mathew Anthony ThattilMAINCO REALTY LLP23/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Aug 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Aug 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Aug 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Aug 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Jul 2028

Documents filed217

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 217 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Affidavit SKM RERA_Final.pdf30 Apr 2025
Declaration in FORM BFile: Esmail Affidavit _Final.pdf30 Apr 2025
Declaration in FORM BFile: Mariam Affidavit _compressed_Final.pdf30 Apr 2025
Declaration in FORM BFile: Shafi Affidavit _compressed_Final.pdf30 Apr 2025
Declaration in FORM BFile: Affidavit PSM RERA_Final.pdf30 Apr 2025
Certificates of CA (Form 3)File: 16 Mainco Realty Form 3_Mar 22 FY 21-22 Q4_compressed.pdf30 Apr 2025
Certificates of CA (Form 3)File: Mainco Realty Form 3_June 22 Q1_compressed.pdf30 Apr 2025
Certificates of CA (Form 3)File: Mainco Realty Form 3_Sep 22 q2_compressed.pdf30 Apr 2025
Certificates of CA (Form 3)File: Mainco Realty Form 3_Dec 22 q3_compressed.pdf30 Apr 2025
Certificates of CA (Form 3)File: Mainco Realty Form 3_Mar 23_compressed.pdf30 Apr 2025
Certificates of CA (Form 3)File: 17 Certificates of CA (Form 3) FY 23-24 Q1.pdf30 Apr 2025
Certificates of CA (Form 3)File: 18 Certificates of CA (Form 3) FY 23-24 Q2.pdf30 Apr 2025
Certificates of CA (Form 3)File: 19 Certificates of CA (Form 3) FY 23-24 Q3.pdf30 Apr 2025
Certificates of CA (Form 3)File: 20 Certificates of CA (Form 3) FY 23-24 Q4.pdf30 Apr 2025
Certificates of CA (Form 3)File: 21 Certificates of CA (Form 3) FY 24-25 Q1.pdf30 Apr 2025
Certificates of CA (Form 3)File: 22 Certificates of CA (Form 3) FY 24-25 Q2.pdf30 Apr 2025
Certificates of CA (Form 3)File: 23 Certificates of CA (Form 3) FY 24-25 Q3.pdf30 Apr 2025
Certificates of CA (Form 3)File: 14 Form 3_Attested FY 21-22 Q2.pdf30 Apr 2025
Certificates of CA (Form 3)File: 4 Form 3_Attested FY 18-19 Q3.pdf30 Apr 2025
Certificates of CA (Form 3)File: 5 Form 3_Attested FY 18-19 Q4.pdf30 Apr 2025
Certificates of CA (Form 3)File: 6 Form 3_Attested FY 19-20 Q1.pdf30 Apr 2025
Certificates of CA (Form 3)File: 7 Form 3_Attested FY 19-20 Q2.pdf30 Apr 2025
Certificates of CA (Form 3)File: 8 Form 3_Attested FY 19-20 Q3.pdf30 Apr 2025
Certificates of CA (Form 3)File: 8 Form -3-FY 19-20-Q4.pdf30 Apr 2025
Certificates of CA (Form 3)File: 9 Form 3_Attested FY 20-21 Q1.pdf30 Apr 2025
Certificates of CA (Form 3)File: 10 Form 3_Attested FY 20-21 Q2.pdf30 Apr 2025
Certificates of CA (Form 3)File: 11 Form 3_Attested FY 20-21 Q3.pdf30 Apr 2025
Certificates of CA (Form 3)File: 12 Form 3_Attested FY 20-21 Q4.pdf30 Apr 2025
Certificates of CA (Form 3)File: 13 Form 3_Attested FY 21-22 Q1.pdf30 Apr 2025
Certificates of CA (Form 3)File: 15 Mainco Realty Form 3_Dec 21 FY 21-22 Q3_compressed.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 19-20_Q4 Form 2_Attested.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 23-24_Q2 Form 2_Attested.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 23-24_Q1 Form 2_Attested.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 22-23_Q4 Form 2_Attested.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 22-23_Q3 Form 2_Attested.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 22-23_Q2 Form 2_Attested.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 22-23_Q1 Form 2_Attested.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 21-22_Q2 11 Form 2_Attested.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 21-22_Q1 10 Form 2_Attested.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 18-19_Q3 1 Form 2_Attested.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 20-21_Q4 9 Form 2_Attested.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 18-19_Q4 2 Form 2_Attested.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 19-20_Q1 3 Form 2_Attested.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 19-20_Q2 4 Form 2_Attested.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 19-20_Q3 5 Form 2_Attested.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 20-21_Q1 6 Form 2_Attested.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 20-21_Q2 7 Form 2_Attested.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FY 20-21_Q3 8 Form 2_Attested.pdf30 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FY 18-19_Q3 - 31-12-2018_compressed.pdf30 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FY 18-19_Q4 - 31-03-2019_compressed.pdf30 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FY 19-20_Q1 - 30-06-2019_compressed.pdf30 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FY 19-20_Q2 - 30-09-2019_compressed.pdf30 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FY 19-20_Q3 - 31-12-2019_compressed.pdf30 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FY 19-20_Q4 - 31-03-2020_compressed.pdf30 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)_Attested.pdf30 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)_Attested.pdf30 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)_Attested.pdf30 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FY 20-21_Q1 - 30-06-2020_compressed.pdf30 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FY 20-21_Q2 - 30-09-2020_compressed.pdf30 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FY 20-21_Q3 - 31-12-2020_compressed.pdf30 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FY 20-21_Q4 - 31-03-2021_compressed.pdf30 Apr 2025
Other - TechnicalFile: CPM Report - Serenity II (1)_Attested.pdf30 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)_Attested.pdf30 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FY 21-22_Q1 - 30-06-2021_compressed.pdf30 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FY 21-22_Q2 - 30-09-2021_compressed.pdf30 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FY 21-22 - 31-03-2022_compressed.pdf30 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FY 22-23 - 31-03-2023_compressed.pdf30 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)_Attested.pdf30 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FY 23-24 - 31-03-2024_compressed.pdf30 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FY 24-25 - 31-03-2025_compressed.pdf30 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)_Attested.pdf30 Apr 2025
FY 21-22 Q3 12 Form 1-signed29 Apr 2025
FY 24-25 Q3 17 Form 1-signed29 Apr 2025
FY 24-25 Q2 16 Form 1-signed29 Apr 2025
FY 24-25 Q1 15 Form 1-signed29 Apr 2025
FY 23-24 Q4 16 Form 1-signed29 Apr 2025
FY 23-24 Q3 14 Form 1-signed29 Apr 2025
FY 23-24 Q2 Form 1-signed29 Apr 2025
FY 23-24 Q1 Form 1-signed29 Apr 2025
FY 22-23 Q4 Form 1-signed29 Apr 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SERENITY 1CHINCHAVALI SHEKIN KHOPOLI TALUKA KHALAPUR RAIGAD32CompletedApr 2016Apr 2016

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 48 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SERENITY 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KHOPOLI5,900+ in Raigarh

2 kmSERENITY 2Completed 18Lapsed / revoked 3Other 27Dot size: filed unitsN

Filed coordinates, straight-line distance. 48 registered projects within 2 km.

Builder: MAINCO REALTY LLP

MAINCO REALTY LLP has 1 registration on MahaRERA, including SERENITY 2. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if SERENITY 2 is delayed beyond 31 Jul 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SERENITY 2?

The registered promoter entity is MAINCO REALTY LLP, a partnership as per the filing. Its GSTIN 27AAVFM7462K1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SERENITY 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SERENITY 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SERENITY 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in SERENITY 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SERENITY 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SERENITY 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.