ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / SDPL Aashray Beltarodi

Completed No litigation declared Residential / Group Housing project

SDPL Aashray Beltarodi

By SANDEEP DWELLERS PVT. LTD.

RG-MH-35772 · RERA P50500023552 · Last updated on MahaRERA portal: 28 Nov 2024

Source: official MahaRERA filing

Red flags

  • 10 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
47 of 55Construction stages doneacross 5 buildings; furthest along: Installation of Lifts, 95%
10Complaints at MahaRERAon this registration
Jump to the 98 documents Report an error

SDPL Aashray Beltarodi is a Residential / Group Housing project by SANDEEP DWELLERS PVT. LTD. in Nagpur, Maharashtra, registered with MahaRERA as P50500023552 on 19 Dec 2019. The registration is recorded completed; possession was promised by 30 Dec 2025. 10 complaints are on record with the regulator.

At a glance

Project

  • NameSDPL Aashray Beltarodi
  • TypeResidential / Group Housing
  • Location
    • Beltarodi
    • Nagpur (Rural)
    • Nagpur
    • 440037
  • Pincode440037
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500023552
  • ReraGenie IDRG-MH-35772

Builder

  • NameSANDEEP DWELLERS PVT. LTD.
  • Entity typeCompany
  • CINU45200MH1990PTC058101
  • GSTIN27AACCS0133P1Z9
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Managing DirectorASHOK SUBHASKUMAR AGARWALA
  • Other registrations26 more →
  • Completed13 of 27
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

this monthRegisteredDec 2019PromisedDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on19 Dec 2019
  • Promised completion30 Dec 2025
  • Revised completionNone
  • Buildings5 building records
  • Documents filed98 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1NA80000
2NA80000
3ANA80000
3BNA80000
4NA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 28 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

47 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Installation of Lifts, at 95%.

191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
3A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
3B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
489%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities18

As on 28 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes95%
Street LightingNoNot applicable
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes90%
Society OfficeYes90%
LiftYes90%
Generator BackupYes100%

Parking filed108

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots108
Closed/Covered108
BuildingClosed/CoveredTotal
11818
22424
3A2424
3B2424
41818

Land and ownership9

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners9
LandownerVillageDistrict
Kunal Ashok AgarwalNagpur (M Corp.)Nagpur
Sharda Devi AgarwalaNagpur (M Corp.)Nagpur
Rahul Ashok AgarwalaNagpur (M Corp.)Nagpur
Kamlesh Harish DassNagpur (M Corp.)Nagpur
Sona Amit ChaturvediWardha (M Cl)Wardha
Ajay Jagdish Kumar SoodNagpur (M Corp.)Nagpur
Kanta Sodesh Kumar SoodNagpur (M Corp.)Nagpur
Sanjay Sodesh Kumar SoodNagpur (M Corp.)Nagpur
Ashish Malhotra-Raipur

Approvals and building plan

Permissible FSI20507.08
Proposed, not sanctioned16,853 sq m
Buildings approved5
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShankar Nagar Nagpur

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRahul Agarwala
EngineerPrasanna Kulkarni
EngineerAman Kumar Singh
EngineerAAJ ENGINEERS AND CONSULTANTS PVT. LTD.
EngineerAAJ ENGINEERS AND CONSULTANTS PVT. LTD.,
Chartered AccountantParesh Tank
Chartered AccountantPARESH JAIRAM TANK & CO
Chartered AccountantBC BHARTIA
PartnerRole in project
SANDEEP DWELLERS PVT. LTD.-

Complaints filed with MahaRERA10

Case no.ComplainantRespondentFiled
CC004000000030474Gaurav AgarwalaAMIT RAHANGDALE14/03/2023
CC004000000030478Gaurav AgarwalaAKSHAY MADAN KUMAR15/03/2023
CC004000000030479Gaurav AgarwalaASHISH NARAYAN BHUTE15/03/2023
CC004000000030480Gaurav AgarwalaASHISH DEWANAND NISWADE15/03/2023
CC004000000030481Gaurav AgarwalaRITESH KISHOR HARANKHEDE15/03/2023
CC004000000030482Gaurav AgarwalaKALPANA MAKODE16/03/2023
CC12602789SANDEEP DWELLERS PVT. LTD.Ashish Nilkanthrao Mawli13/05/2026
CC12602985SANDEEP DWELLERS PVT. LTD.Abhilash Khandare20/05/2026
CC12602986SANDEEP DWELLERS PVT. LTD.Praveen Nair20/05/2026
CC12602991SANDEEP DWELLERS PVT. LTD.Anand Gedam20/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Sep 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Dec 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Nov 2024

Documents filed98

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 98 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Occupation Certificate - 5-2 - Nov 24 - merged.pdf28 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate - 5-2 - Nov 24.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SDPL Aasharay Beltarodi_compressed.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SDPL Aashray Beltarodi_compressed.pdf17 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Aashray Beltarodi - Supervisor - 2024.pdf14 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SDPL Aashray Beltarodi_compressed.pdf18 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SDPL Aashray Beltarodi - Architect - 30Jun24.pdf13 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SDPL Aashray Beltarodi - Engineer - 30Jun24.pdf13 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SDPL Aashray Beltarodi - 31Mar24.pdf22 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AASHRAY BELTARODI-Annexure - 31Mar24_compressed (1).pdf22 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SDPL Aashray Beltarodi_compressed.pdf10 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SDPL Aashray Beltarodi.pdf10 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect - Aashray Beltarodi - Dec 23.pdf13 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer - SDPL Aashray Beltarodi- Dec23.pdf13 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA - Aashray Beltarodi - Dec23_compressed.pdf13 Jan 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ilovepdf_merged.pdf14 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SDPL Aashray Beltarodi_compressed.pdf14 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect- Aashray Beltarodi - 30Sep23.pdf12 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer - SDPL Aashray Beltarodi - Sep 23.pdf12 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SDPL Aashray Beltarodi.pdf26 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SDPL Aashray Beltarodi_compressed.pdf13 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect- SDPL Aashray Beltarodi- 30Jun23.pdf7 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer - SAB- 30Jun23.pdf7 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Aashray Beltarodi - Supervisor - 31 March 23.pdf19 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SDPL RERA CERTIFICATE - DSC_compressed (1)_compressed.pdf12 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SDPL Aashray Beltarodi_compressed.pdf6 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Beltarodi Engineer Rera Certificate_compressed.pdf6 Apr 2023
Details of encumbrancesFile: Adobe Scan 24-Feb-2023 (1).pdf24 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - 2020 - Beltarodi.pdf14 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SDPL Aashray Beltarodi_compressed (1).pdf10 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SDPL Aashray Beltarodi_compressed.pdf5 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SDPL Aashray Beltarodi .pdf5 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SDPL Aashray Beltarodi_compressed.pdf8 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: SDPL Aashray Beltarodi_compressed.pdf8 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SDPL Aashray Beltarodi_compressed.pdf7 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SDPL Aashray Beltarodi_compressed.pdf7 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: SDPL Aashray Beltarodi_compressed.pdf27 Sep 2022
Building plan approvalFile: 5-2 SAB July 22 Final Sanction-Part1.pdf1 Aug 2022
Building plan approvalFile: 5-2 SAB July 22 Final Sanction-Part2.pdf1 Aug 2022
Building plan approvalFile: SAB 6-1 Building Sanction July 22.pdf1 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: 5-2 SAB July 22 Final Sanction-Part1.pdf1 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: 5-2 SAB July 22 Final Sanction-Part2.pdf1 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: SAB 6-1 Building Sanction July 22.pdf1 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: 5-2 SAB Letter .pdf1 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: SAB 6-1 Letter.pdf1 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate- Beltarodi_compressed.pdf7 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engin Beltarodi_compressed.pdf7 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SDPL Aashray Beltarodi_compressed.pdf7 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SDPL Ashray Beltarodi Certificate.pdf11 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - Beltarodi_compressed.pdf7 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate -Beltarodi_compressed.pdf7 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Supervisor Certificate -Beltarodi_compressed.pdf7 Apr 2022
Disclosure of sold/ booked inventoryFile: Inventory- Beltarodi_compressed_compressed_compressed.pdf7 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: BELTARODI_merged_compressed.pdf6 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engi Beltarodi_compressed.pdf6 Jan 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SDPL Aashray Beltarodi (1).pdf6 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect - Aashray Beltarodi.pdf7 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer - Aashray Beltarodi.pdf7 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Supervisor - Aashray Beltarodi.pdf7 Oct 2021
Disclosure of sold/ booked inventoryFile: Sold unsold - Aashray Beltarodi.pdf7 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SDPL AASHRAY BELTARODI.pdf7 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: SDPL BELTARODI.pdf30 Sep 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect - Beltarodi - Jun 21_compressed.pdf20 Jul 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer - Beltarodi - Jun 21_compressed.pdf20 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SDPL Aasrhray Beltarodi - Supervisor .pdf20 Jul 2021
Disclosure of sold/ booked inventoryFile: Sold unsold - beltarodi - July 21.pdf20 Jul 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SDPL Beltarodi_compressed.pdf20 Jul 2021
Disclosure of sold/ booked inventoryFile: Form 3A - Sold unsold - Beltarodi - Mar 21 (1)_compressed.pdf27 May 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA BELTARODI_compressed.pdf12 Apr 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert-SDPL Aashray Beltarodi_compressed.pdf8 Apr 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Cert- SDPL Aashray Beltarodi--min.pdf8 Apr 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: SDPL Aasrhray Beltarodi - Supervisor .pdf8 Apr 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: aashray beltarodi.pdf14 Jan 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aashray Beltarodi - architect - dec 20-compressed.pdf9 Jan 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ashray Beltarodi - engineers- dec 20-compressed.pdf9 Jan 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: aashray beltarodi - supervisor- dec 20.pdf9 Jan 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aashray Beltarodi - CA Certificate - 30 Sept.pdf8 Oct 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aashray Beltarodi - Architect - 30 Sept.pdf7 Oct 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Beltarodi - Engineer - 30 Sept.pdf7 Oct 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Aashray Beltarodi - Supervisor -30 Sept.pdf3 Oct 2020

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
SDPL ClassicPlot no 35 Kh. No. 302 Chinchbhuvan Wardha Road Near Khapri Nagpur 44002543CompletedJun 2017Apr 2017
SDPL Greens Wing B and D and Convenience ShoppingKh No. 13-15 Opp. Star Motors Kamptee Road Nagpur 440026131CompletedMay 2017Nov 2016
SDPL Paradise Wing A and BBehind Water Tank Dabha Nagpur 44002372CompletedSep 2016Late, Oct 2016
Shree Swaminarayan EnclaveNext to Sadashiv Nagar Near Swaminarayan Temple Wathoda Nagpur 44000898CompletedDec 2014Late, Feb 2015
NILGIRIOpp. Transport Plaza Automotive Chowk Kamptee Road Nagpur 44002655CompletedSep 2014Late, Dec 2014

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is completed

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SDPL Aashray Beltarodi on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Beltarodi2,800+ in Nagpur

2 kmSDPL Aashray BeltarodiCompleted 17Lapsed / revoked 2Other 26Dot size: filed unitsN

Filed coordinates, straight-line distance. 45 registered projects within 2 km.

Builder: SANDEEP DWELLERS PVT. LTD.

SANDEEP DWELLERS PVT. LTD. has 27 registrations on MahaRERA, including SDPL Aashray Dabha and SDPL Paradise II. Its filings disclose 5 earlier MahaRERA projects: declares 2 of 5 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if SDPL Aashray Beltarodi is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SDPL Aashray Beltarodi?

The registered promoter entity is SANDEEP DWELLERS PVT. LTD., a company as per the filing. Its CIN U45200MH1990PTC058101 and GSTIN 27AACCS0133P1Z9 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SDPL Aashray Beltarodi?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SDPL Aashray Beltarodi?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SDPL Aashray Beltarodi?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SDPL Aashray Beltarodi?

The professionals named in the filing: Architect: Rahul Agarwala; Engineer: Prasanna Kulkarni; Engineer: Aman Kumar Singh; Engineer: AAJ ENGINEERS AND CONSULTANTS PVT. LTD.; Engineer: AAJ ENGINEERS AND CONSULTANTS PVT. LTD.,; Chartered Accountant: Paresh Tank. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SDPL Aashray Beltarodi?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SDPL Aashray Beltarodi. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SDPL Aashray Beltarodi to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.