ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / AARISH RESIDENCY

Registered No litigation declared Residential / Group Housing project

AARISH RESIDENCY

By AARISH INFRASTRUCTURE

RG-MH-03610 · RERA P50500028996 · Last updated on MahaRERA portal: 22 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
5 of 11Construction stages donefurthest along: Internal walls, 75%
132 of 140Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 94 documents Report an error

AARISH RESIDENCY is a Residential / Group Housing project by AARISH INFRASTRUCTURE in Nagpur, Maharashtra, registered with MahaRERA as P50500028996 on 23 Apr 2021. Possession is promised by 31 Dec 2026. 8 of the 140 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameAARISH RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • BESA
    • BESA NAGPUR
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440037
  • Pincode440037
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500028996
  • ReraGenie IDRG-MH-03610

Builder

  • NameAARISH INFRASTRUCTURE
  • Entity typePartnership
  • PartnersPRASHANT SHARAD KALI, KUNAL DEEPAK NARSAPURKAR

Key dates

this monthRegisteredApr 2021PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Apr 2021
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed94 files

Current status

6%8 of 140 units booked
89.6%Work done, per cost certificate

Figures as on 22 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AARISH RESIDENCYNA14141400140

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 75%.

AARISH RESIDENCY: 60% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes45%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered1
Open Space1

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,200 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
Vyankatesh KunawarNagpur (M Corp.)Nagpur
Chandrakant PadmawarNagpur (M Corp.)Nagpur
Neelesh ChandawarNagpur (M Corp.)Nagpur

Approvals and building plan

Sanctioning authorityNagpur Municipal Corporation
Permissible FSI9066.1
Proposed, not sanctioned9,066 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch190, NANDANVAN MAIN ROAD, NAGPUR
Estimated costRs 15.62 cr
Cost incurredRs 14.01 cr
Work done89.64%
BuildingWingEstimatedIncurred
AARISH RESIDENCYNARs 14.06 crRs 13.45 cr
-NARs 1.56 crRs 56.02 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectC D GIRIPUNJE Giripunje
ArchitectR.D. Architects & Consultants
EngineerMAHENDRA S BHANDARI Bhandari
EngineerAshish Gedam
Chartered AccountantAgrawal Saraf & associates
Chartered AccountantAgrawal Ankita & Co
PartnerRole in project
AARISH INFRASTRUCTURE-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Apr 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Mar 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Mar 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed94

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Withdrawal Application Form1.pdf22 May 2026
Withdrawal Update Form 2File: Withdrawal Application Form2.pdf22 May 2026
Withdrawal Update Form 3File: Withdrawal Application Form3.pdf22 May 2026
Withdrawal Update Form 1File: Withdrawal Application Form1.pdf21 May 2026
Withdrawal Update Form 1File: Withdrawal Application Form1 (2).pdf21 May 2026
Withdrawal Update Form 1File: Withdrawal Application Form1 (2).pdf21 May 2026
Withdrawal Update Form 1File: Withdrawal Application Form1 (2).pdf21 May 2026
Withdrawal Update Form 2File: Withdrawal Application Form2.pdf21 May 2026
Withdrawal Update Form 2File: Withdrawal Application Form2 (2).pdf21 May 2026
Withdrawal Update Form 2File: Withdrawal Application Form2 (2).pdf21 May 2026
Withdrawal Update Form 2File: Withdrawal Application Form2 (2).pdf21 May 2026
Withdrawal Update Form 3File: Withdrawal Application Form3 (2).pdf21 May 2026
Withdrawal Update Form 3File: Withdrawal Application Form3 (2).pdf21 May 2026
Withdrawal Update Form 3File: Withdrawal Application Form3 (2).pdf21 May 2026
Withdrawal Update Form 3File: Withdrawal Application Form3 (2).pdf21 May 2026
Form 5 (FY 2021-2022)File: Form 5 2021-22.pdf14 Apr 2026
Form 5 (FY 2022-2023)File: Form 5 2022-23.pdf14 Apr 2026
Form 5 (FY 2023-2024)File: Form 5 2023-24.pdf14 Apr 2026
Form 5 (FY 2024-2025)File: Form 5 2024-25.pdf14 Apr 2026
Form 1File: JUNE-21 FORM 01 .pdf30 Mar 2026
Form 2File: JUNE-21 FORM 02 .pdf30 Mar 2026
Form 3File: JUNE-21 FORM 03.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: JUNE-21 DISCLOSURE OF INVENTORY .pdf30 Mar 2026
Form 1File: SEP-21 FORM 01 .pdf30 Mar 2026
Form 2File: SEP-21 FORM 02 .pdf30 Mar 2026
Form 3File: SEP-21 FORM 03.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: SEP-21 DISCLOSURE OF INVENTORY .pdf30 Mar 2026
Form 1File: DEC-21 FORM 01 .pdf30 Mar 2026
Form 2File: DEC-21 FORM 02 .pdf30 Mar 2026
Form 3File: DEC-21 FORM 03.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: DEC-21 DISCLOSURE OF INVENTORY .pdf30 Mar 2026
Form 1File: MAR-22 FORM 01 .pdf30 Mar 2026
Form 2File: MAR-22 FORM 02 .pdf30 Mar 2026
Form 3File: MAR-22 FORM 03.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: MAR-22 DISCLOSURE OF INVENTORY .pdf30 Mar 2026
Form 1File: JUNE-22 FORM 01 .pdf30 Mar 2026
Form 2File: JUNE-22 FORM 02 .pdf30 Mar 2026
Form 3File: JUNE-22 FORM 03.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: JUNE-22 DISCLOSURE OF INVENTORY .pdf30 Mar 2026
Form 1File: SEP-22 FORM 01 .pdf30 Mar 2026
Form 2File: SEP-22 FORM 02 .pdf30 Mar 2026
Form 3File: SEP-22 FORM 03.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: SEP-22 DISCLOSURE OF INVENTORY .pdf30 Mar 2026
Form 1File: DEC-22 FORM 01 .pdf30 Mar 2026
Form 2File: DEC-22 FORM 02 .pdf30 Mar 2026
Form 3File: DEC-22 FORM 03.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: DEC-22 DISCLOSURE OF INVENTORY .pdf30 Mar 2026
Form 1File: MAR-23 FORM 01 .pdf30 Mar 2026
Form 2File: MAR-23 FORM 02 .pdf30 Mar 2026
Form 3File: MAr-23 FORM 03.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: MAR-23 DISCLOSURE OF INVENTORY .pdf30 Mar 2026
Form 1File: JUNE-23 FORM 01 .pdf30 Mar 2026
Form 2File: JUNE-23 FORM 02 .pdf30 Mar 2026
Form 3File: JUNE-23 FORM 03.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: JUNE-23 DISCLOSURE OF INVENTORY .pdf30 Mar 2026
Form 1File: SEP-23 FORM 01 .pdf30 Mar 2026
Form 2File: SEP-23 FORM 02 .pdf30 Mar 2026
Form 3File: SEP-23 FORM 03.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: SEP-23 DISCLOSURE OF INVENTORY .pdf30 Mar 2026
Form 1File: DEC-23 FORM 01 .pdf30 Mar 2026
Form 2File: DEC-23 FORM 02 .pdf30 Mar 2026
Form 3File: DEC-23 FORM 03.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: DEC-23 DISCLOSURE OF INVENTORY .pdf30 Mar 2026
Form 1File: MAR-24 FORM 01 .pdf30 Mar 2026
Form 2File: MAR-24 FORM 02.pdf30 Mar 2026
Form 3File: MAR-24 FORM 03.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: MAR-24 DISCLOSURE OF INVENTORY .pdf30 Mar 2026
Form 1File: JUNE-24 FORM 01 .pdf30 Mar 2026
Form 2File: JUNE-24 FORM 02 Signed.pdf30 Mar 2026
Form 3File: JUNE-24 FORM 03.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: JUNE-24 DISCLOSURE OF INVENTORY .pdf30 Mar 2026
Form 1File: SEP-24 FORM 01 .pdf30 Mar 2026
Form 2File: SEPTEMBER 24 Signed.pdf30 Mar 2026
Form 3File: SEP-24 FORM 03.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: SEP-24 DISCLOSURE OF INVENTORY .pdf30 Mar 2026
Form 1File: DEC-24 FORM 01 .pdf30 Mar 2026
Form 2File: DEC-24 FORM 02 Signed.pdf30 Mar 2026
Form 3File: DEC-24 FORM 03.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: DEC-24 DISCLOSURE OF INVENTORY .pdf30 Mar 2026
Form 1File: MAR-25 FORM 01 .pdf30 Mar 2026

How this compares with Nagpur

6%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AARISH RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BESA NAGPUR2,800+ in Nagpur

2 kmAARISH RESIDENCYCompleted 33Lapsed / revoked 11Other 44Dot size: filed unitsN

Filed coordinates, straight-line distance. 88 registered projects within 2 km.

Builder: AARISH INFRASTRUCTURE

AARISH INFRASTRUCTURE has 1 registration on MahaRERA, including AARISH RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if AARISH RESIDENCY is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AARISH RESIDENCY?

The registered promoter entity is AARISH INFRASTRUCTURE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AARISH RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AARISH RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AARISH RESIDENCY?

The professionals named in the filing: Architect: C D GIRIPUNJE Giripunje; Architect: R.D. Architects & Consultants; Engineer: MAHENDRA S BHANDARI Bhandari; Engineer: Ashish Gedam; Chartered Accountant: Agrawal Saraf & associates; Chartered Accountant: Agrawal Ankita & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AARISH RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AARISH RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AARISH RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.