Home / Browse projects / Pune, Maharashtra / SAVALI HEIGHTS

Registration lapsed No litigation declared Residential / Group Housing project

SAVALI HEIGHTS

By SAVALI PROMOTERS AND DEVELOPERS PVT. LTD

RG-MH-23894 · RERA P52100010488 · Last updated on MahaRERA portal: 9 Feb 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 54 months past the filed date
  • 4 complaints at MahaRERA
  • Completion date moved by 15 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Apr 2022Possession promised54 months past this date
15 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 95%
4Complaints at MahaRERAon this registration
Jump to the 27 documents Report an error

SAVALI HEIGHTS is a Residential / Group Housing project by SAVALI PROMOTERS AND DEVELOPERS PVT. LTD in Pune, Maharashtra, registered with MahaRERA as P52100010488 on 31 Aug 2017. Possession was promised by 9 Apr 2022 and is now 54 months past that date. The completion date has moved by 15 months from the original filing. 4 complaints are on record with the regulator.

At a glance

Project

  • NameSAVALI HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • RTO Road
    • Newale Vasti
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412114
  • Pincode412114
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100010488
  • ReraGenie IDRG-MH-23894

Builder

  • NameSAVALI PROMOTERS AND DEVELOPERS PVT. LTD
  • Entity typeCompany
  • ChairpersonSUNIL JAGANNATH JUMDE
  • DirectorsJALINDER PARVATI NEWALE, VITTHAL MARUTIRAO BIRADAR, SHANKAR CHIMAN NEWALE, ULHAS YADAVRAO DHONDJI

Key dates

54 months past promisethis monthRegisteredAug 2017First promiseJan 2021Revised toApr 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Aug 2017
  • Promised completion9 Apr 2022
  • Revised completionRevised to 9 Apr 2022 (originally 9 Jan 2021)
  • Buildings3 building records
  • Documents filed27 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA140000
BNA140000
CNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 9 Feb 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 95%.

A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
C0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 9 Feb 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsYes70%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
A11
B11

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,300 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
JALINDER PARVATI NEWALEPimpri Chinchawad (M Corp.)Pune
CHIMAN PARVATI NEWALEPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Permissible FSI9553.9
Proposed, not sanctioned9,554 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHREE SWAMI SAMARTH COMPLEX, INDRAYANINAGAR, BHOSARI, PUNE

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMAHENDRA THAKUR AND ASSOCIATES
PartnerRole in project
SAVALI PROMOTERS AND DEVELOPERS PVT. LTD-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100008727Jan 2021 → Jul 2021

Reason as filed by the promoterSavali Hights is MAHARERA Registered project dated 18/05/2020 with RERA No. P52100010488, Our Registration is valid from 31/08/2017 to 09/01/2021, which is expiring in next month. The completion letter for 24 Flats are pending from PCMC due to NOC of drainage system. Out of 136 flats completion for 112 flats are already obtained. We are taking rigorous follow up for the Drainage NOC, However, concerned office is working with very minimal staff strength and unable to provide Drainage NOC in due time, the said office may take some months and thereafter PCMC office will also take some time for is

EXT52100011356Jan 2021 → Apr 2022

Reason as filed by the promoterSavali Hights is MAHARERA Registered project dated 18/05/2020 with RERA No. P52100010488, Our Registration is valid from 31/08/2017 to 08/07/2021. All the NOC and relevant documentation are done, the only thing pending is the completion letter from PCMC, we have applied for the completion on 10/08/2021 and the proposal is pending at PCMC. It is informed by PCMC authority that, due to CoVID-19, issue of staff availability persist and hence application could not process in time and may require further 3 months to process. application filed with PCMC is attached herewith for your ready reference,

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC005000000023231Mr. Deepak Yashwant WalhekarMr. Shankar Chiman Newale14/07/2019
CC005000000023232Mr. Deepak Yashwant WalhekarMr. Shankar Chiman Newale14/07/2019
CC005000000023233Mr. Deepak Yashwant WalhekarMr. Jalindar Parvati Newale14/07/2019
CC005000000023234Mr. Deepak Yashwant WalhekarMr. Jalindar Parvati Newale14/07/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed27

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about Commencement CertificateFile: 01 Declaration about commencement certificate.pdf9 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 02 Quality Assurance Certificate.pdf9 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 02 Quality Assurance Certificate.pdf9 Feb 2022
CERSAI detailsFile: 05 CERSAI Report.pdf9 Feb 2022
Disclosure of sold/ booked inventoryFile: 03 Disclosure of sold and unsold.pdf9 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 04 Form 5.pdf9 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 04 Form 5.pdf9 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate_compressed.pdf29 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_compressed.pdf29 Nov 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5_compressed (1).pdf29 Nov 2019
Certificates of CA (Form 5)File: Savali- Form 5.pdf29 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate.pdf15 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate.pdf15 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers CertificateU.pdf15 May 2018
Certificates of CA (Form 3)File: CA Certificate.pdf15 May 2018
Layout approvalFile: plan.pdf31 Jul 2017
Building plan approvalFile: scan00321 (3 files merged)-min.pdf31 Jul 2017
Copy of the legal title reportFile: search 1-min (2).pdf31 Jul 2017
Details of encumbrancesFile: bank loan approval-min.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: plan.pdf31 Jul 2017
Building Plan Approval (IOD)File: scan00321 (3 files merged)-min.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: commencement.pdf31 Jul 2017
Declaration in FORM BFile: Ingale sir-min (1).pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Aechitect certificate-min.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: kumar certificate-min.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA Certificate_Savali.pdf31 Jul 2017
Proforma of Allotment letterFile: Proforma of Agreement.pdf31 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 15 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAVALI HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Newale Vasti13,700+ in Pune

2 kmSAVALI HEIGHTSCompleted 56Lapsed / revoked 30Other 37Dot size: filed unitsN

Filed coordinates, straight-line distance. 123 registered projects within 2 km.

Builder: SAVALI PROMOTERS AND DEVELOPERS PVT. LTD

SAVALI PROMOTERS AND DEVELOPERS PVT. LTD has 1 registration on MahaRERA, including SAVALI HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that SAVALI HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SAVALI HEIGHTS is delayed beyond 9 Apr 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAVALI HEIGHTS?

The registered promoter entity is SAVALI PROMOTERS AND DEVELOPERS PVT. LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAVALI HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SAVALI HEIGHTS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SAVALI HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAVALI HEIGHTS?

The professionals named in the filing: Architect: MAHENDRA THAKUR AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAVALI HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAVALI HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAVALI HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.