Saukhya Residency
By B Square Builders And Developers
RG-MH-17068 · RERA P52600028215 · Last updated on MahaRERA portal: 25 Sep 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 20 months past the filed date
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Solapur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Saukhya Residency is a Residential / Group Housing project by B Square Builders And Developers in Solapur, Maharashtra, registered with MahaRERA as P52600028215 on 13 Feb 2021. Possession was promised by 19 Feb 2025 and is now 20 months past that date. The completion date has moved by 12 months from the original filing. 0 of the 10 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.
At a glance
Project
- NameSaukhya Residency
- TypeResidential / Group Housing
- Location
- Vasant Vihar
- Solapur (M Corp.)
- Solapur North
- Solapur
- 413005
- Pincode413005
- RERA no.P52600028215
- ReraGenie IDRG-MH-17068
Builder
- NameB Square Builders And Developers
- Entity typePartnership
- GSTIN27AAVFB9817F1ZX
- PartnerAhijit Sakharam Jadhav
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on13 Feb 2021
- Promised completion19 Feb 2025
- Revised completionRevised to 19 Feb 2025 (originally 20 Feb 2024)
- Buildings1 building record
- Documents filed24 files
Current status
Figures as on 25 Sep 2024, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Saukhya Residency | NA | 6 | 0 | 10 | 0 | 10 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 25 Sep 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.
Saukhya Residency: 83% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Progress on shared amenities15
As on 25 Sep 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Ashok Piraji Pawar | Solapur (M Corp.) | Solapur |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Saukhya Residency | NA | Rs 1.35 cr | Rs 1.32 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Arch Tauhid Shaikh Shaikh |
| Engineer | Tauhid Shaikh |
| Engineer | SAGAR G. PULLI Pulli |
| Chartered Accountant | CA Aditya Kondale |
| Chartered Accountant | Vaibhav Kambale and Company |
| Chartered Accountant | Sanadwala and associates |
| Partner | Role in project |
|---|---|
| B Square Builders And Developers | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe, B Square Builders and Developers, hereby apply for an extension of the registered project bearing vide no P52600028215. Due to site conditions and unavailability of labors during Covid 19 lockdown the project got delayed. The project is 80% complete as of today and we are confident to complete the project and acquire full occupancy certificate within a year. We hereby request you to please allow extension of the project till date 19/02/2025.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Jan 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Dec 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Dec 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Dec 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed24
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 - Architect Q223.pdf | 25 Sep 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Q123.pdf | 1 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Q223.pdf | 1 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Q323.pdf | 1 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Q423.pdf | 1 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Q124.pdf | 1 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Q224.pdf | 1 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Q123.pdf | 1 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Q223.pdf | 1 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Q323.pdf | 1 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Q423.pdf | 1 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Q124.pdf | 1 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Q224.pdf | 1 Aug 2024 |
| Declaration in FORM BFile: Form B Saukhya FInal m.pdf | 3 Feb 2021 |
| Copy of the legal title reportFile: BSquare Search Final.pdf | 20 Jan 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: BSquare CA.pdf | 9 Jan 2021 |
| Layout approvalFile: BSquare No Encumbrance.pdf | 25 Dec 2020 |
| Details of encumbrancesFile: BSquare Encumbrance.pdf | 25 Dec 2020 |
| Copy of Layout Approval (in case of layout)File: BSquare No Encumbrance.pdf | 25 Dec 2020 |
| Building plan approvalFile: BSquare BP Final.pdf | 24 Dec 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: BSquare BP Final.pdf | 24 Dec 2020 |
| PAN CardFile: BSquare PAN.pdf | 19 Dec 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: BSquare Commencement.pdf | 19 Dec 2020 |
| Proforma of Allotment letterFile: BSquare Alottment Letter.pdf | 19 Dec 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Solapur
Computed across the 550+ Solapur projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- All 24 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Saukhya Residency on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Vasant Vihar550+ in Solapur
Niyojit Shri Somvanshiya Sahastrarjun Kshatriy
Anukarati Homes Private Limited
NAKSHATRA HEIGHTS
GAYATRI BUILDERS AND DEVELOPERS
Kaveri Heights
Gayatri Developers
PADMAWATI REJENCY
GURAPPA MALLIKARJUN KAPSE
SURYA COMPLEX
SURESH AMBADAS MITTHAKOL
PRAJAY HEIGHTS
JAYKANT CONSTRUCTION
See every Solapur project, with the district possession charts
Builder: B Square Builders And Developers
B Square Builders And Developers has 1 registration on MahaRERA, including Saukhya Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Solapur district page.
Frequently asked questions
What does it mean that Saukhya Residency shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Saukhya Residency is delayed beyond 19 Feb 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Saukhya Residency?
The registered promoter entity is B Square Builders And Developers, a partnership as per the filing. Its GSTIN 27AAVFB9817F1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Saukhya Residency?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Saukhya Residency?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Saukhya Residency?
The professionals named in the filing: Architect: Arch Tauhid Shaikh Shaikh; Engineer: Tauhid Shaikh; Engineer: SAGAR G. PULLI Pulli; Chartered Accountant: CA Aditya Kondale; Chartered Accountant: Vaibhav Kambale and Company; Chartered Accountant: Sanadwala and associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Saukhya Residency?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback