Registered No litigation declared Residential / Group Housing project

SAUHARD

By SHREENIWAS HOMEMAKERS

RG-MH-82117 · RERA P50500055620 · Last updated on MahaRERA portal: 31 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 12 months from the original
4 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 95%
5 of 14Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 76 documents Report an error

SAUHARD is a Residential / Group Housing project by SHREENIWAS HOMEMAKERS in Nagpur, Maharashtra, registered with MahaRERA as P50500055620 on 4 Apr 2024. Possession is promised by 31 Mar 2027. The completion date has moved by 12 months from the original filing. 9 of the 14 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameSAUHARD
  • TypeResidential / Group Housing
  • Location
    • DHARAMPETH
    • MOUZA LENDHRA
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440010
  • Pincode440010
  • RERA no.P50500055620
  • ReraGenie IDRG-MH-82117

Builder

  • NameSHREENIWAS HOMEMAKERS
  • Entity typePartnership
  • GSTIN27AEGFS0584R1Z8
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersASHUTOSH ARVIND NAIK, ABHISHEK KAMLESH DADHE
  • Other registrations1 more →

Key dates

this monthRegisteredApr 2024First promiseMar 2026Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Apr 2024
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed76 files

Current status

64%9 of 14 units booked
95.0%Work done, per cost certificate

Figures as on 31 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAUHARDNA9914014

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 31 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

SAUHARD: 79% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 31 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes95%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes95%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed60

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots60
Open Space60

Land and ownership7

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area688 sq m
Land owned byThe promoter, with other names on the file
Named landowners7
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on8 Jul 2025
LandownerVillageDistrict
RAVINDRA KATHALEPune (M Corp.)Pune
YOGENDRA KATHALENagpur (M Corp.)Nagpur
SATYENDRA KATHALENashik (M Corp.)Nashik
GAYATRI NAWARERamtekNagpur
AVANTI RALEGAONKARPune (M Corp.)Pune
AMRUTA SAHASTRABUDHEPune (M Corp.)Pune
ADITI MARATHENagpur (M Corp.)Nagpur

Approvals and building plan

Sanctioning authorityNMRDA
Permissible FSI1876.21
Proposed, not sanctioned1,876 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLAXMI NAGAR 8 RAASTA SQUARE NAGPUR-440010
Estimated costRs 4.90 cr
Cost incurredRs 4.66 cr
Work done95.0%
BuildingWingEstimatedIncurred
SAUHARDNARs 4.50 crRs 4.28 cr
-NARs 40.00 lakhRs 38.00 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHARISH KALIKAR
EngineerNARENDRA TANDULKAR
Chartered AccountantWS KORKE & CO CHARTERED ACCOUNTANTS
PartnerRole in project
SHREENIWAS HOMEMAKERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA01052620805Mar 2026 → Mar 2027

Reason as filed by the promoterWe, Shreeniwas Homemakers, are promoter of the project Sauhard, registered under MahaRERA vide registration number P50500055620. Sir the foresaid project was projected to be completed by 31/03/2026 but due to lesser response in bookings and technical problems raised in the project the project is now bound to be delayed. The project till date is about 90% completed which is also certified by the project architect in form 1 uploaded in MahaRERA portal. Currently out of total 14 units in the project, we have sold 10 units. Out of which 10 have already given their consent for extension of the proj

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Dec 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Dec 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Dec 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed76

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Kathale RERA FORM- June 26.pdf31 Jul 2026
Withdrawal Update Form 2File: Sauhard Engineerr.pdf31 Jul 2026
Withdrawal Update Form 3File: SAUHARD Q1 30062026 MERGE.pdf31 Jul 2026
Withdrawal Update Form 1File: Form 1.pdf1 May 2026
Withdrawal Update Form 2File: Form 2.pdf1 May 2026
Withdrawal Update Form 3File: Form 3.pdf1 May 2026
Form 2A (FY 2024-2025)File: Form 2A 2425.pdf1 May 2026
Form 2A (FY 2025-2026)File: Form 2A 2526.pdf1 May 2026
Form 5 (FY 2024-2025)File: Form 5.pdf1 May 2026
Withdrawal Update Form 1File: ARCHITECH CERTIFICATE 30092025.pdf13 Apr 2026
Withdrawal Update Form 1File: ARCHITECH CERTIFICATE 30092025.pdf13 Apr 2026
Withdrawal Update Form 1File: ARCHITECH CERTIFICATE 01012026.pdf13 Apr 2026
Withdrawal Update Form 2File: ENGG CERTIFICATE 30092025.pdf13 Apr 2026
Withdrawal Update Form 2File: ENGG CERTIFICATE 30092025.pdf13 Apr 2026
Withdrawal Update Form 2File: ENGG CERTIFICATE 01012026.pdf13 Apr 2026
Withdrawal Update Form 3File: CA CERTIFICATE SAUHARD 30092025.pdf13 Apr 2026
Withdrawal Update Form 3File: CA CERTIFICATE SAUHARD 30092025.pdf13 Apr 2026
Withdrawal Update Form 3File: CA CERTIFICATE SAUHARD 31122025.pdf13 Apr 2026
Withdrawal Update Form 1File: ARCHITECH CERTIFICATE 30092025.pdf1 Apr 2026
Withdrawal Update Form 1File: ARCHITECH CERTIFICATE 30092025.pdf1 Apr 2026
Withdrawal Update Form 1File: ARCHITECH CERTIFICATE 30092025.pdf1 Apr 2026
Withdrawal Update Form 2File: Withdrawal Application Form2.pdf1 Apr 2026
Withdrawal Update Form 2File: Withdrawal Application Form2.pdf1 Apr 2026
Withdrawal Update Form 2File: Withdrawal Application Form2.pdf1 Apr 2026
Withdrawal Update Form 3File: CA CERTIFICATE SAUHARD 30092025.pdf1 Apr 2026
Withdrawal Update Form 3File: CA CERTIFICATE SAUHARD 30092025.pdf1 Apr 2026
Withdrawal Update Form 3File: CA CERTIFICATE SAUHARD 30062025.pdf1 Apr 2026
Withdrawal Update Form 1File: Architect CERTIFICATE 30062025.pdf28 Jul 2025
Withdrawal Update Form 1File: Architect CERTIFICATE 30062025.pdf28 Jul 2025
Withdrawal Update Form 2File: Withdrawal Application Form2.pdf28 Jul 2025
Withdrawal Update Form 2File: Withdrawal Application Form2.pdf28 Jul 2025
Withdrawal Update Form 3File: Withdrawal Application Form3.pdf28 Jul 2025
Withdrawal Update Form 3File: CA CERTIFICATE SAUHARD 30062025.pdf28 Jul 2025
Form 1File: Architect, Engineer Forms - April 2025-1-3.pdf27 Jun 2025
Form 2File: Architect, Engineer Forms - April 2025-4-7.pdf27 Jun 2025
Form 3File: CA CERTIFICATE 28022025 (1).pdf27 Jun 2025
Disclosure of Sold and Booked InventoryFile: CA CERTIFICATE 28022025 (1).pdf27 Jun 2025
Form 1File: RERA FORM NO 1 04072024.pdf23 Jun 2025
Form 2File: RERA FORM NO2 04072024.pdf23 Jun 2025
Form 3File: CA CERTIFICATE 30062024.pdf23 Jun 2025
Disclosure of Sold and Booked InventoryFile: CA CERTIFICATE 30062024.pdf23 Jun 2025
Form 1File: RERA FORM NO 1 07102024.pdf23 Jun 2025
Form 2File: RERA FORM NO 2 07102024.pdf23 Jun 2025
Form 3File: CA CERTIFICVATE 30092024.pdf23 Jun 2025
Disclosure of Sold and Booked InventoryFile: CA CERTIFICVATE 30092024.pdf23 Jun 2025
Form 1File: RERA FORM NO 1 24012025.pdf23 Jun 2025
Form 2File: RERA FORM NO 24012025.pdf23 Jun 2025
Form 3File: CA CERTIFICATE 31122024.pdf23 Jun 2025
Disclosure of Sold and Booked InventoryFile: CA CERTIFICATE 31122024.pdf23 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE 30062024.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICVATE 30092024.pdf25 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE 31122024.pdf25 Mar 2025
Details of encumbrances concerned to FinanceFile: FINANCIAL ENCUMBRANCE.pdf29 Mar 2024
Details of encumbrances concerned to LegalFile: FINANCIAL ENCUMBRANCE.pdf29 Mar 2024
CERSAI detailsFile: CERSAI REPORT.pdf29 Mar 2024
Other - FinanceFile: CA CERTIFICATE (1).pdf29 Mar 2024
Proforma of Agreement for saleFile: AGREEMENT TO SELL RERA KATHALE NAIK (1).pdf4 Mar 2024
Declaration about Commencement CertificateFile: CC.pdf8 Feb 2024
PAN CardFile: PAN CARD.pdf2 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf5 Jan 2024
Layout approvalFile: Sanctioned Plan Sauhard.pdf16 Dec 2023
Building plan approvalFile: Sanctioned Plan Sauhard.pdf16 Dec 2023
Copy of the legal title reportFile: LEGAL SEARCH REPORT.pdf16 Dec 2023
Details of encumbrances concerned to FinanceFile: LEGAL ENCUMBRANCE.pdf16 Dec 2023
Details of encumbrances concerned to LegalFile: LEGAL ENCUMBRANCE.pdf16 Dec 2023
Copy of Layout Approval (in case of layout)File: Sanctioned Plan Sauhard.pdf16 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: Sanctioned Plan Sauhard.pdf16 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: Sanctioned Plan Sauhard.pdf16 Dec 2023
Declaration about Commencement CertificateFile: COMMENCEMENT CERTIFICATE.pdf16 Dec 2023
Declaration in FORM BFile: FORM B.pdf16 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE AD.pdf16 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE AN.pdf16 Dec 2023
Proforma of Allotment letterFile: PROFORAM ALLOTMENT.pdf16 Dec 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK DECLARATION.pdf16 Dec 2023
Deviation Report with respect to Allotment letterFile: DEVAIATION ALLOTMENT.pdf16 Dec 2023
Deviation Report with respect to model copy of AgreementFile: DEVIATION ATS.pdf16 Dec 2023

How this compares with Nagpur

64%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one moved by 12 months
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAUHARD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MOUZA LENDHRA2,800+ in Nagpur

Builder: SHREENIWAS HOMEMAKERS

SHREENIWAS HOMEMAKERS has 2 registrations on MahaRERA, including SAUHARD and SHREE LAXMI VYANKATESH APARTMENTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if SAUHARD is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAUHARD?

The registered promoter entity is SHREENIWAS HOMEMAKERS, a partnership as per the filing. Its GSTIN 27AEGFS0584R1Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAUHARD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAUHARD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAUHARD?

The professionals named in the filing: Architect: HARISH KALIKAR; Engineer: NARENDRA TANDULKAR; Chartered Accountant: WS KORKE & CO CHARTERED ACCOUNTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAUHARD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAUHARD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAUHARD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.