ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / SAUBHAGYAM PHASE II

Registered No litigation declared Residential / Group Housing project

SAUBHAGYAM PHASE II

By TODAY GLOBAL PROPERTIES

RG-MH-18616 · RERA P52000077460 · Last updated on MahaRERA portal: 23 Sep 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 4 months
  • 1 extension taken
  • Rs 25.00 crore secured on the land, in favour of ADITYA BIRLA FINANCE LIMITED

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jan 2030Possession promisedmoved 4 months from the original
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 75%
5 of 182Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 78 documents Report an error

SAUBHAGYAM PHASE II is a Residential / Group Housing project by TODAY GLOBAL PROPERTIES in Raigarh, Maharashtra, registered with MahaRERA as P52000077460 on 16 Aug 2024. Possession is promised by 30 Jan 2030. The completion date has moved by 4 months from the original filing. 177 of the 182 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSAUBHAGYAM PHASE II
  • TypeResidential / Group Housing
  • Location
    • NA
    • Giravale
    • Panvel
    • Raigarh
    • 410221
  • Pincode410221
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000077460
  • ReraGenie IDRG-MH-18616

Builder

  • NameTODAY GLOBAL PROPERTIES
  • Entity typePartnership
  • PartnersRAJESH SHAH, BHADRESH SHAH
  • Other registrations1 more →

Key dates

this monthRegisteredAug 2024First promiseSep 2029Revised toJan 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on16 Aug 2024
  • Promised completion30 Jan 2030
  • Revised completionRevised to 30 Jan 2030 (originally 30 Sep 2029)
  • Buildings1 building record
  • Documents filed78 files

Current status

97%177 of 182 units booked
78.1%Work done, per cost certificate

Figures as on 23 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAUBHAGYAM PHASE IINA12121820182

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 75%.

SAUBHAGYAM PHASE II: 35% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises11%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed51

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots51
Closed/Covered51

Land and ownership3

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area5,330 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared present
Charge in favour ofADITYA BIRLA FINANCE LIMITED
Secured amountRs 25.00 crore
CERSAI search filedYes
Declared on16 Jul 2025
LandownerVillageDistrict
TODAY GLOBAL PROPERTIESNavi Mumbai (M Corp.)Thane
SHIRISH CHANGU HATMODEPanvelRaigarh
AMBAJI GANPAT HATMODEPanvelRaigarh

Approvals and building plan

Sanctioning authoritypanvel municipal corporation
Permissible FSI32200.72
Proposed, not sanctioned7,201 sq m
Buildings approved2
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., 121920,Kalindi Bldg,Apmc Mkt.Sector19,Vashi, Navi Mumbai.400705
Estimated costRs 26.33 cr
Cost incurredRs 20.57 cr
Work done78.13%
BuildingWingEstimatedIncurred
SAUBHAGYAM PHASE IINARs 24.33 crRs 20.57 cr
-NARs 2.00 cr-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Architectdesign today
EngineerStructural Concept designs pvt ltd.
EngineerVijay Muttur
Chartered AccountantMAIDAWAT AND ASSOCIATES
Chartered AccountantSwati Sudhendu Patel
Chartered AccountantBhavik J Velani
PartnerRole in project
TODAY GLOBAL PROPERTIES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P52000077460/WarSep 2029 → Jan 2030

Reason as filed by the promoterNA

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
SM12600059Bhakti AchrekarTODAY GLOBAL PROPERTIES12/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Aug 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Oct 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Aug 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Aug 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jan 2030

Documents filed78

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A _MARCH 2026_SAUBHAGYAM PHASE II.pdf23 Sep 2026
Withdrawal Update Form 1File: Form 01.pdf10 Aug 2026
Withdrawal Update Form 2File: 3370_001.pdf10 Aug 2026
Withdrawal Update Form 3File: 3371_001.pdf10 Aug 2026
Withdrawal Update Form 1File: form1 1 rera updated.pdf23 Jun 2026
Withdrawal Update Form 1File: ARCHITECTS CERTIFICATE P-II.pdf23 Jun 2026
Withdrawal Update Form 1File: Form-1 Saubhagyam II- Q-4.pdf23 Jun 2026
Withdrawal Update Form 2File: Form 2 rera upload.pdf23 Jun 2026
Withdrawal Update Form 2File: form 02 - 3rd qtr.pdf23 Jun 2026
Withdrawal Update Form 2File: form 02 - 4th qtr.pdf23 Jun 2026
Withdrawal Update Form 3File: 2618_001.pdf23 Jun 2026
Withdrawal Update Form 3File: form 3 - Q 3.pdf23 Jun 2026
Withdrawal Update Form 3File: form -3 4 th qtr.pdf23 Jun 2026
Form 5 (FY 2025-2026)File: 1 Scan Form-5 TGP 460.pdf16 Jun 2026
Layout approvalFile: 37-1, 37-2, 51-C-ACC DWG(20 SHEETS).pdf15 Oct 2025
Form 5 (FY 2024-2025)File: Scan Form-5 TGP-P-II 460.pdf9 Oct 2025
Withdrawal Update Form 1File: form 01.pdf16 Jul 2025
Withdrawal Update Form 2File: form 02.pdf16 Jul 2025
Withdrawal Update Form 3File: form 3 saubhgyam p ii.pdf16 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 P-II.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 P-I.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: TGP sold unsold Q4.pdf19 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf14 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 P-II.pdf11 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory Saubhgyam Phase II.pdf11 Jan 2025
Disclosure of sold/ booked inventoryFile: TGP_PII.pdf9 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 03 P2.pdf4 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 02 P2.pdf4 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 02 P2.pdf4 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM JHVDJH.pdf13 Aug 2024
Proforma of Agreement for saleFile: ANNEXURE AMENITIES (2).pdf12 Aug 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: tgp (1).pdf12 Aug 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: BANK LETTER.pdf12 Aug 2024
Details of encumbrances concerned to FinanceFile: 3 a Details of encumbrances concerned to Finance.pdf10 Aug 2024
Details of encumbrances concerned to FinanceFile: 4 b Details of encumbrances concerned to Legal.pdf10 Aug 2024
Details of encumbrances concerned to LegalFile: 3 a Details of encumbrances concerned to Finance.pdf10 Aug 2024
Details of encumbrances concerned to LegalFile: 4 b Details of encumbrances concerned to Legal.pdf10 Aug 2024
Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate (1).pdf10 Aug 2024
CERSAI detailsFile: CERSAI.pdf10 Aug 2024
Disclosure for secured/unsecured finance availed for the projectFile: DETAILS OF SECURED AND UNSECURED LOAN.pdf10 Aug 2024
Deviation Report with respect to Allotment letterFile: 24 Deviation Report with respect to AL.pdf10 Aug 2024
Deviation Report with respect to model copy of AgreementFile: 23 Deviation Report with respect to AFS.pdf10 Aug 2024
Other - LegalFile: 646 (3)_923_1070_merged.pdf10 Aug 2024
Other - LegalFile: 1_3 SALE DEED - TODAY GLOBAL_compressed.pdf10 Aug 2024
Other - LegalFile: 2_3 SALE DEED - TODAY GLOBAL_compressed.pdf10 Aug 2024
Other - LegalFile: 3_3 SALE DEED - TODAY GLOBAL_compressed.pdf10 Aug 2024
Other - LegalFile: 4_3 SALE DEED - TODAY GLOBAL_compressed.pdf10 Aug 2024
Other - LegalFile: 5_3 SALE DEED - TODAY GLOBAL_compressed.pdf10 Aug 2024
Other - LegalFile: 6_3 SALE DEED - TODAY GLOBAL_compressed.pdf10 Aug 2024
Other - TechnicalFile: 21 Technical Other.pdf10 Aug 2024
Layout approvalFile: 5 Copy of Layout Approval (in case of layout) 2.pdf9 Aug 2024
Building plan approvalFile: 6-1 Building Plan Approval 2.pdf9 Aug 2024
Building plan approvalFile: 6-2 Building Plan Approval 2.pdf9 Aug 2024
Building plan approvalFile: 6-3 Building Plan Approval 2.pdf9 Aug 2024
Building plan approvalFile: 6-4 Building Plan Approval 2.pdf9 Aug 2024
Building plan approvalFile: 6-5 Building Plan Approval 2.pdf9 Aug 2024
Building plan approvalFile: 6-6 Building Plan Approval 2.pdf9 Aug 2024
PAN CardFile: 1 PAN CARD.pdf9 Aug 2024
Copy of the legal title reportFile: 2 TITLE CERTIFICATE_compressed.pdf9 Aug 2024
Copy of Layout Approval (in case of layout)File: 5 Copy of Layout Approval (in case of layout) 2.pdf9 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: 6-1 Building Plan Approval 2.pdf9 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: 6-2 Building Plan Approval 2.pdf9 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: 6-3 Building Plan Approval 2.pdf9 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: 6-4 Building Plan Approval 2.pdf9 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: 6-5 Building Plan Approval 2.pdf9 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: 6-6 Building Plan Approval 2.pdf9 Aug 2024
Commencement Certificates / NA Order for plotted developmentFile: 7 Commencement Certificates NA Order for plotted development.pdf9 Aug 2024
Declaration in FORM BFile: 9 Declaration in FORM B.pdf9 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 14 Disclosure of Interest in Other Real Estate Organizations_compressed.pdf9 Aug 2024
Proforma of Agreement for saleFile: 15 Proforma of Agreement for sale.pdf9 Aug 2024
Proforma of Allotment letterFile: 16 Proforma of Allotment letter.pdf9 Aug 2024
Other - LegalFile: 19 Legal Other - Partnership DeeD.pdf9 Aug 2024
Other - LegalFile: 17 Legal Other- 7:12.pdf9 Aug 2024
Other - FinanceFile: 20 Finance - Partnership Deed.pdf9 Aug 2024
Other - TechnicalFile: 21 Technical - Partnership Deed.pdf9 Aug 2024

How this compares with Raigarh

97%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 4 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAUBHAGYAM PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NA5,900+ in Raigarh

2 kmSAUBHAGYAM PHASE IICompleted 1Lapsed / revoked 1Other 14Dot size: filed unitsN

Filed coordinates, straight-line distance. 16 registered projects within 2 km.

Builder: TODAY GLOBAL PROPERTIES

TODAY GLOBAL PROPERTIES has 2 registrations on MahaRERA, including SAUBHAGYAM and SAUBHAGYAM PHASE II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if SAUBHAGYAM PHASE II is delayed beyond 30 Jan 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAUBHAGYAM PHASE II?

The registered promoter entity is TODAY GLOBAL PROPERTIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAUBHAGYAM PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SAUBHAGYAM PHASE II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SAUBHAGYAM PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAUBHAGYAM PHASE II?

The professionals named in the filing: Architect: design today; Engineer: Structural Concept designs pvt ltd.; Engineer: Vijay Muttur; Chartered Accountant: MAIDAWAT AND ASSOCIATES; Chartered Accountant: Swati Sudhendu Patel; Chartered Accountant: Bhavik J Velani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAUBHAGYAM PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAUBHAGYAM PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAUBHAGYAM PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.