ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Satguru SRA Co-op Hsg. Society

Registration lapsed No litigation declared Residential / Group Housing project

Satguru SRA Co-op Hsg. Society

By SURJIT BHOJSINGH AILSINGHANI

RG-MH-24492 · RERA P51800012379 · Last updated on MahaRERA portal: 8 Aug 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
1 of 11Construction stages donefurthest along: Basement (if any), 75%
0Complaints at MahaRERAon this registration
Jump to the 165 documents Report an error

Satguru SRA Co-op Hsg. Society is a Residential / Group Housing project by SURJIT BHOJSINGH AILSINGHANI in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800012379 on 1 Sep 2017. Possession was promised by 30 Dec 2025 and is now 10 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameSatguru SRA Co-op Hsg. Society
  • TypeResidential / Group Housing
  • Location
    • Kurla
    • Mumbai Suburban
    • 400074
  • Pincode400074
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800012379
  • ReraGenie IDRG-MH-24492

Builder

  • NameSURJIT BHOJSINGH AILSINGHANI
  • Entity typeIndividual
  • Other registrations2 more →
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

10 months past promisethis monthRegisteredSep 2017First promiseDec 2024Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Sep 2017
  • Promised completion30 Dec 2025
  • Revised completionRevised to 30 Dec 2025 (originally 30 Dec 2024)
  • Buildings1 building record
  • Documents filed165 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Satguru SRA Co-op Hsg SocietyNA230000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 Aug 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 75%.

Satguru SRA Co-op Hsg Society: 39% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)75%
Podiums (if any)0%
Plinth75%
Stilt Floor52%
Slabs of Super Structure36%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises28%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks29%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.29%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.7%

Progress on shared amenities15

As on 8 Aug 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed76

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots76
Closed/Covered76

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,562 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI11596.02
Proposed, not sanctioned10,396 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFort Mumbai

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJAYANT RATILAL KATIRA
EngineerJAYANT RATILAL KATIRA
PartnerRole in project
SURJIT BHOJSINGH AILSINGHANI-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800024491Dec 2024 → Dec 2025

Reason as filed by the promoterDue to covid, slow construction and financial issues we will surely try to complete it within a year.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Aug 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Aug 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Aug 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed165

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 165 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: img05598.pdf8 Aug 2024
Layout approvalFile: 02.pdf1 Aug 2024
Building plan approvalFile: 28.pdf1 Aug 2024
Building plan approvalFile: 915.pdf1 Aug 2024
Details of encumbrances concerned to FinanceFile: No legal encumbrances.pdf1 Aug 2024
Details of encumbrances concerned to LegalFile: No legal encumbrances.pdf1 Aug 2024
Copy of Layout Approval (in case of layout)File: 02.pdf1 Aug 2024
Building Plan Approval (IOD)File: 28.pdf1 Aug 2024
Building Plan Approval (IOD)File: 915.pdf1 Aug 2024
Commencement Certificates / NA Order for plotted developmentFile: IOA letter 27122024.pdf1 Aug 2024
Declaration about Commencement CertificateFile: CC declaration.pdf1 Aug 2024
Certificates of CA (Form 3)File: Form 3 ( Dec 2022 ).pdf1 Aug 2024
Certificates of CA (Form 3)File: Form 3 ( March 2023 ).pdf1 Aug 2024
Certificates of CA (Form 3)File: Form 3 (June 2023).pdf1 Aug 2024
Certificates of CA (Form 3)File: Form 3 (Sept 2023).pdf1 Aug 2024
Certificates of CA (Form 3)File: Form 3 ( Dec 2023).pdf1 Aug 2024
Certificates of CA (Form 3)File: Form 3 ( March 2024).pdf1 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other projects_rotated.pdf1 Aug 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration about separate bank ac.pdf1 Aug 2024
Deviation Report with respect to Allotment letterFile: No deviation with respect to allotment.pdf1 Aug 2024
Deviation Report with respect to model copy of AgreementFile: No deviation with respect to model copy of agreement.pdf1 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec-22.pdf24 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Mar-23.pdf24 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Jun-23.pdf24 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Sep-23.pdf24 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec-23.pdf24 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Mar-24.pdf24 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec-22.pdf24 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Mar-23.pdf24 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Jun-23.pdf24 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Sep-23.pdf24 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Dec-23.pdf24 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Mar-24.pdf24 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A- Mar 20.pdf24 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A-Mar 21.pdf24 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A-Mar 22.pdf24 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FROM 2A-Mar 23.pdf24 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A- Mar 24.pdf24 Jul 2024
Disclosure of sold/ booked inventoryFile: Unsold declaration Dec-22.pdf24 Jul 2024
Disclosure of sold/ booked inventoryFile: Unsold declaratio June-23.pdf24 Jul 2024
Disclosure of sold/ booked inventoryFile: Unsold declaration Mar-23.pdf24 Jul 2024
Disclosure of sold/ booked inventoryFile: Unsold declaration Sep-23.pdf24 Jul 2024
Disclosure of sold/ booked inventoryFile: Unsold declaration Dec-23.pdf24 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: 2017-18.pdf24 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2018-19.pdf24 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-20.pdf24 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 2020-21.pdf24 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2223.pdf24 Jul 2024
Proforma of Agreement for saleFile: Draft AFS.pdf24 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2324.pdf24 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Satguru form 5 17-18.pdf5 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Satguru form 5 18-19.pdf5 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Satguru form 5 19-20.pdf5 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Satguru form 5 20-21.pdf5 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Satguru form 5 21-22.pdf5 Apr 2023
Building plan approvalFile: Amended IOD.pdf27 Dec 2021
Layout approvalFile: LAYOUT PLAN.pdf27 Dec 2021
Layout approvalFile: TYPICAL FLOOR REHAB WING 'A' WING (11TH TO 14TH FLOOR).pdf27 Dec 2021
Layout approvalFile: SERVICE FLOOR FOR WING B and C PLAN.pdf27 Dec 2021
Layout approvalFile: SECTION A1-.pdf27 Dec 2021
Layout approvalFile: SECTION B1-.pdf27 Dec 2021
Layout approvalFile: SECTION C1-.pdf27 Dec 2021
Layout approvalFile: LAYOUT PLAN.pdf27 Dec 2021
Layout approvalFile: LOWER GROUND FLOOR PLAN.pdf27 Dec 2021
Layout approvalFile: UPPER GROUND FLOOR PLAN.pdf27 Dec 2021
Layout approvalFile: FIRST FLOOR PLAN.pdf27 Dec 2021
Layout approvalFile: SECOND FLOOR PLAN.pdf27 Dec 2021
Layout approvalFile: THIRD FLOOR PLAN.pdf27 Dec 2021
Layout approvalFile: FOURTH FLOOR PLAN.pdf27 Dec 2021
Layout approvalFile: FIFTH FLOOR PLAN.pdf27 Dec 2021
Layout approvalFile: TYPICAL FLOOR (6TH, 8TH TO 10TH PLAN.pdf27 Dec 2021
Layout approvalFile: LAYOUT PLAN.pdf27 Dec 2021
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf27 Dec 2021
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf27 Dec 2021
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf27 Dec 2021
Copy of Layout Approval (in case of layout)File: LOWER GROUND FLOOR PLAN.pdf27 Dec 2021
Copy of Layout Approval (in case of layout)File: UPPER GROUND FLOOR PLAN.pdf27 Dec 2021
Copy of Layout Approval (in case of layout)File: FIRST FLOOR PLAN.pdf27 Dec 2021
Copy of Layout Approval (in case of layout)File: SECOND FLOOR PLAN.pdf27 Dec 2021
Copy of Layout Approval (in case of layout)File: THIRD FLOOR PLAN.pdf27 Dec 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
BABA PEARL HEIGHTPlot No. 17 Sector 20 kamothe Navi Mumbai26CompletedDec 2012Dec 2012

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Satguru SRA Co-op Hsg. Society on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmSatguru SRA Co-op Hsg. SCompleted 9Lapsed / revoked 8Other 18Dot size: filed unitsN

Filed coordinates, straight-line distance. 35 registered projects within 2 km.

Builder: SURJIT BHOJSINGH AILSINGHANI

SURJIT BHOJSINGH AILSINGHANI has 3 registrations on MahaRERA, including EKTA CO-OP HSG SOCIETY and Satguru SRA Co-op Hsg. Society. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Satguru SRA Co-op Hsg. Society shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Satguru SRA Co-op Hsg. Society is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Satguru SRA Co-op Hsg. Society?

The registered promoter entity is SURJIT BHOJSINGH AILSINGHANI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Satguru SRA Co-op Hsg. Society?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Satguru SRA Co-op Hsg. Society?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Satguru SRA Co-op Hsg. Society?

The professionals named in the filing: Architect: JAYANT RATILAL KATIRA; Engineer: JAYANT RATILAL KATIRA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Satguru SRA Co-op Hsg. Society?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Satguru SRA Co-op Hsg. Society. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Satguru SRA Co-op Hsg. Society to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.