SARANGI PARADISE

By SAI PROPKING REALITY

RG-MH-92276 · RERA P52100054384 · Last updated on MahaRERA portal: 24 Jan 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedno revision filed
6 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 85%
45 of 84Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

SARANGI PARADISE is a Others project by SAI PROPKING REALITY in Pune, Maharashtra, registered with MahaRERA as P52100054384 on 18 Jan 2024. Possession is promised by 30 Jun 2027. 39 of the 84 units on this registration are recorded sold or booked, and 6 of 22 construction stages are filed complete.

At a glance

Project

  • NameSARANGI PARADISE
  • TypeOthers
  • Location
    • PUNE NASHIK ROAD
    • DHADAGE MALA
    • Chakan (CT)
    • Khed
    • Pune
    • 410501
  • Pincode410501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100054384
  • ReraGenie IDRG-MH-92276

Builder

  • NameSAI PROPKING REALITY
  • Entity typePartnership
  • PartnersRAJU ULHAS SHIRKE, PANKAJ SAHEBRAO KARANDE

Key dates

this monthRegisteredJan 2024PromisedJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Jan 2024
  • Promised completion30 Jun 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed54 files

Current status

46%39 of 84 units booked
68.6%Work done, per cost certificate

Figures as on 24 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING A1 AND WING B1NA87561268
WING C1NA5416016

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 24 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 85%.

WING A1 AND WING B161%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor50%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
WING C127%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed17

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots17
Closed/Covered17
BuildingClosed/CoveredTotal
WING A1 AND WING B11515
WING C122

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,200 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
TARABAI GANPAT DHADGEChakan (CT)Pune
ABHIMANYU GANPAT DHADGEChakan (CT)Pune
RAMCHANDRA ALIAS RAMBHAU VITTHAL DHADGEChakan (CT)Pune
RAJENDRA GANPAT DHADGEChakan (CT)Pune

Approvals and building plan

Sanctioning authorityCHAKAN NAGAR PARISHAD CHAKAN
Permissible FSI4192.25
Proposed, not sanctioned4,192 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 22-23-35 TO 41, KOHINOOR CENTRE BUILDING B TALEGAON CHOWK CHAKAN 410501
Estimated costRs 6.20 cr
Cost incurredRs 4.25 cr
Work done68.6%
BuildingWingEstimatedIncurred
WING A1 AND WING B1NARs 5.00 crRs 3.73 cr
WING C1NARs 1.20 crRs 52.80 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKD ARCHITECTURE AND STRUCTURAL CONSUTANT
EngineerPANKAJ SAHEBRAO KARANDE
Chartered AccountantPANKAJ SURANA AND COMPANY
PartnerRole in project
SAI PROPKING REALITY-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Dec 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Dec 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Dec 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 saragi p.pdf24 Jan 2026
Withdrawal Update Form 2File: FORM 3 sarangi p.pdf24 Jan 2026
Withdrawal Update Form 3File: FORM 3_compressed (2).pdf24 Jan 2026
Withdrawal Update Form 1File: FORM 1 (5).pdf28 Oct 2025
Withdrawal Update Form 2File: form 2 .pdf28 Oct 2025
Withdrawal Update Form 3File: FORM 3_compressed (2).pdf28 Oct 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf15 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf12 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf12 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf12 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf29 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf31 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf31 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf15 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf15 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf15 Jan 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf24 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf23 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf23 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf23 Oct 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf5 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf23 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_compressed (1).pdf23 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed (2).pdf23 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf24 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf24 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 (1).pdf24 May 2024
Other - LegalFile: sai propking भागीदारी पत्र_compressed.pdf2 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Adobe Scan 18-Dec-2023 (1).pdf20 Dec 2023
Building plan approvalFile: PLAN 1.pdf16 Dec 2023
Building plan approvalFile: PLAN 2.pdf16 Dec 2023
Building plan approvalFile: PLAN 3.pdf16 Dec 2023
Layout approvalFile: SARANGI PARADISE LAYOUT FINAL.pdf16 Dec 2023
PAN CardFile: PAN CARD.pdf16 Dec 2023
Copy of the legal title reportFile: Rera search Report.pdf16 Dec 2023
Details of encumbrances concerned to FinanceFile: NO ENCUMBRANCE SARANGI PARADISE.pdf16 Dec 2023
Details of encumbrances concerned to LegalFile: NO ENCUMBRANCE SARANGI PARADISE.pdf16 Dec 2023
Copy of Layout Approval (in case of layout)File: SARANGI PARADISE LAYOUT FINAL.pdf16 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: PLAN 1.pdf16 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: PLAN 2.pdf16 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: PLAN 3.pdf16 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf16 Dec 2023
Declaration about Commencement CertificateFile: CC DECLARATION SARANGI PARADISE.pdf16 Dec 2023
Declaration in FORM BFile: Declaration 1.pdf16 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE.pdf16 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf16 Dec 2023
CERSAI detailsFile: NO CERSAI SARANGI PARADISE.pdf16 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: OTHER ORGANISATIONS RAJU SIR SARANGI PARADISE.pdf16 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A_1.pdf16 Dec 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf16 Dec 2023
Proforma of Agreement for saleFile: AGREEMENT TO SELL.pdf16 Dec 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK DECLARATION SARANGI PARADISE.pdf16 Dec 2023
Deviation Report with respect to Allotment letterFile: DEVIATION REPORT SARANGI PARADISE.pdf16 Dec 2023
Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT SARANGI PARADISE.pdf16 Dec 2023

How this compares with Pune

46%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SARANGI PARADISE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DHADAGE MALA13,700+ in Pune

2 kmSARANGI PARADISECompleted 20Lapsed / revoked 24Other 31Dot size: filed unitsN

Filed coordinates, straight-line distance. 75 registered projects within 2 km.

Builder: SAI PROPKING REALITY

SAI PROPKING REALITY has 1 registration on MahaRERA, including SARANGI PARADISE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SARANGI PARADISE is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SARANGI PARADISE?

The registered promoter entity is SAI PROPKING REALITY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SARANGI PARADISE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SARANGI PARADISE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SARANGI PARADISE?

The professionals named in the filing: Architect: KD ARCHITECTURE AND STRUCTURAL CONSUTANT; Engineer: PANKAJ SAHEBRAO KARANDE; Chartered Accountant: PANKAJ SURANA AND COMPANY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SARANGI PARADISE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SARANGI PARADISE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SARANGI PARADISE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.