Home / Browse projects / Mumbai Suburban, Maharashtra / SAPTARSHI CLASSIC

Registration lapsed No litigation declared Others project

SAPTARSHI CLASSIC

By ROCKFORD VENTURES LLP

RG-MH-14446 · RERA P51800024794 · Last updated on MahaRERA portal: 13 Dec 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 20%
0Complaints at MahaRERAon this registration
Jump to the 59 documents Report an error

SAPTARSHI CLASSIC is a Others project by ROCKFORD VENTURES LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800024794 on 9 Mar 2020. Possession was promised by 30 Dec 2025 and is now 10 months past that date.

At a glance

Project

  • NameSAPTARSHI CLASSIC
  • TypeOthers
  • Location
    • 7 NEHRU NAGAR
    • KURLA EAST MUMBAI
    • Kurla
    • Mumbai Suburban
    • 400024
  • Pincode400024
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800024794
  • ReraGenie IDRG-MH-14446

Builder

  • NameROCKFORD VENTURES LLP
  • Entity typePartnership
  • PartnersJITENDRA KANTILAL SHAH, KANTILAL ACCHLAJI SHAH

Key dates

10 months past promisethis monthRegisteredMar 2020PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Mar 2020
  • Promised completion30 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed59 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAPTARSHI CLASSICNA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 20%.

SAPTARSHI CLASSIC: 29% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 13 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,830 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
NEHRU NAGAR SAPTARSHI CHS LTDKurlaMumbai Suburban
RELIANCE REALTORS & ESTATE DEVELOPERSBorivaliMumbai Suburban

Approvals and building plan

Permissible FSI6076.6
Proposed, not sanctioned6,077 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR ROCKFORD HOUSE 444 P B MARG GRANT ROAD EAST MUMBAI 400004

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSACHIN RAKSHE
EngineerSANJAY PATIL
Chartered AccountantASHWIN OZA
PartnerRole in project
ROCKFORD VENTURES LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Dec 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jan 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jan 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 17 Aug 2024

Documents filed59

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf13 Dec 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf11 Dec 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Reg Certificate.pdf11 Dec 2024
Foreclosure of the ProjectFile: Form 4.pdf11 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5 14-10-24.PDF8 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FORM 4.pdf17 Aug 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate.pdf16 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf26 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf26 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf26 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 ARCHITECT CERTI-11-7-23.PDF12 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 ARCHITECT CERTI-10-10-23.PDF12 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 AMEY 7-7-23.PDF12 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 AMEY CONS 6-10-23.PDF12 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 CA CERIFICATE 9-12-23.pdf12 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.PDF12 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.PDF12 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf5 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf5 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3.pdf5 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Rera form 3 final.pdf1 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA FORM-1.PDF27 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA FORM-2.PDF27 Feb 2023
Disclosure of sold/ booked inventoryFile: Disclosure Inventory.pdf23 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf21 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: 6808_furthercc_signed.pdf21 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: 6808_furthercc_signed.pdf16 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: 6808_furthercc_signed.pdf16 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: 6808_furthercc_signed.pdf16 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf3 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf3 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A.pdf3 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A.pdf3 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf3 May 2022
Disclosure of sold/ booked inventoryFile: Inventory 31032022.pdf2 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: rocford venture llp CAform 5_compressed.pdf2 Apr 2022
Proforma of Allotment letterFile: Final Agreement for Sale.pdf15 Dec 2021
Proforma of Allotment letterFile: Final Agreement 30112021.pdf1 Dec 2021
Proforma of Allotment letterFile: Classic Saptarshi - Draft Allotment Letter.pdf23 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: C C Kurla.pdf7 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 FY 21_compressed.pdf5 May 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 FY 21.pdf5 May 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 FY 21.pdf5 May 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 6-4-21.pdf9 Apr 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019-2020.pdf9 Apr 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certificate.PDF11 Feb 2020
Layout approvalFile: Plot layout Build no 7.pdf30 Jan 2020
Building plan approvalFile: IOD Copy_compressed.pdf30 Jan 2020
Details of encumbrancesFile: No Encumbrances.pdf30 Jan 2020
Details of encumbrancesFile: No Encumbrances.pdf30 Jan 2020
Copy of Layout Approval (in case of layout)File: Plot layout Build no 7.pdf30 Jan 2020
Building Plan Approval / NA Order for plotted developmentFile: IOD Copy_compressed.pdf30 Jan 2020
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf30 Jan 2020
Proforma of Allotment letterFile: Draft Allotment Letter 19022020.pdf30 Jan 2020
PAN CardFile: Pan card Rockford Ventures LLP_20200108123211.pdf8 Jan 2020
Declaration in FORM BFile: Form B Kurla.pdf8 Jan 2020
Copy of the legal title reportFile: Title Certificate.pdf26 Dec 2019
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf26 Dec 2019
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.PDF26 Dec 2019

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAPTARSHI CLASSIC on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KURLA EAST MUMBAI6,700+ in Mumbai Suburban

2 kmSAPTARSHI CLASSICCompleted 43Lapsed / revoked 13Other 17Dot size: filed unitsN

Filed coordinates, straight-line distance. 73 registered projects within 2 km.

Builder: ROCKFORD VENTURES LLP

ROCKFORD VENTURES LLP has 1 registration on MahaRERA, including SAPTARSHI CLASSIC. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that SAPTARSHI CLASSIC shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SAPTARSHI CLASSIC is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAPTARSHI CLASSIC?

The registered promoter entity is ROCKFORD VENTURES LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAPTARSHI CLASSIC?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAPTARSHI CLASSIC?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAPTARSHI CLASSIC?

The professionals named in the filing: Architect: SACHIN RAKSHE; Engineer: SANJAY PATIL; Chartered Accountant: ASHWIN OZA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAPTARSHI CLASSIC?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAPTARSHI CLASSIC. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAPTARSHI CLASSIC to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.