SANNIDHI ENCLAVE

By ROYAL BAWA BUILDERS

RG-KA-69052 · RERA PRM/KA/RERA/1257/334/PR/020822/005123

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Jump to the 68 documents Report an error

SANNIDHI ENCLAVE is a Mixed Development project by ROYAL BAWA BUILDERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/020822/005123 on 2 Aug 2022. Possession is promised by 31 Dec 2022.

At a glance

Project

  • NameSANNIDHI ENCLAVE
  • TypeMixed Development
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1257/334/PR/020822/005123
  • ReraGenie IDRG-KA-69052

Builder

  • NameROYAL BAWA BUILDERS
  • Entity typePartnership Firm
  • GSTIN29ABAFR7181C1Z5
  • Authorized SignatoryKODI ISMAIL
  • Other registrations3 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2022PromisedDec 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on2 Aug 2022
  • Promised completion31 Dec 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed68 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SANNIDHI ENCLAVE-----38

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes-
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallNoNot applicable
Open parking areasYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
M.B KULAKARNI AND OTHERS--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 7.50 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 7.50 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANTHOSH KUMAR SHETTY
EngineerH ANAND BHAT
Chartered AccountantMAXIM M.FERNANDES

Documents filed68

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/020822/005123 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RTC, survey 88/2A1-
Mutation, survey 88/2A1-
Encumbrance Certificate, survey 88/2A1-
Conversion/Alienation Order, survey 88/2A1-
Sale/Title/Gift Deed, survey 88/2A1-
JDA, survey 88/2A1-
Khatha, survey 88/2A1-
Registration CertificateFile: registration certficate_compressed.pdf-
Partnership DeedFile: partnership deed_compressed.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: form 1 ca certficate.pdf-
Certificate issued by Architect Form 2File: architect certificate.pdf-
Certificate issued by Engineer Form 3File: engineer certficate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: litigation affidaith.pdf-
Certificate from Chartered AccountFile: approval certficate.pdf-
Balance Sheet 2020 - 2021File: BS 2021-22.PDF-
Audited Profit and Loss Statement 2020 - 2021File: P&L ACCOUNT 2021-22.PDF-
Director's Report 2020 - 2021File: DR 21-22_compressed.pdf-
Cash Flow Statement 2020 - 2021File: IS 2021-22.pdf-
Cash Flow Statement 2019 - 2020File: IS 2020_compressed.pdf-
Auditor's Report 2020 - 2021File: AR 21-22_compressed.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR 2021-22.PDF-
Income Tax Return Acknowledgement 2019 - 2020File: ITR 2020-21_compressed.pdf-
building licence_compressed-
sanction plan_compressed-
single layout-
sanction plan_compressed-
sanction plan_compressed-
sanction plan_compressed-
specification_compressed-
single layout-
single layout-
stability certifcate-
SEARCH REPORT-
title deed-
conversion_compressed-
conversion_compressed-
proforma AOS-
proforma allotment letter-
broucher_compressed-
form b_compressed-
Affidavit 3(1)-
jda affidavith-
mescom noc-
water noc-
Unnamed document-
Unnamed document-
fire noc_compressed-
Unnamed document-
pollution noc-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
stp drawing-
guidance value-
MASTER PLAN-

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep SANNIDHI ENCLAVE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

Builder: ROYAL BAWA BUILDERS

ROYAL BAWA BUILDERS has 4 registrations on RERA Karnataka, including SANNIDHI ENCLAVE and RIVER ANKORA. Its filings declare 2 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if SANNIDHI ENCLAVE is delayed beyond 31 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SANNIDHI ENCLAVE?

The registered promoter entity is ROYAL BAWA BUILDERS, a partnership firm as per the filing. Its GSTIN 29ABAFR7181C1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SANNIDHI ENCLAVE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SANNIDHI ENCLAVE?

The professionals named in the filing: Architect: SANTHOSH KUMAR SHETTY; Engineer: H ANAND BHAT; Chartered Accountant: MAXIM M.FERNANDES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SANNIDHI ENCLAVE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SANNIDHI ENCLAVE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SANNIDHI ENCLAVE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.