Home / Browse projects / Mysore, Karnataka / SANKALP SKY VILLAS
SANKALP SKY VILLAS
By SANKALP CONSTRUCTIONS PRIVATE LIMITED
RG-KA-90127 · RERA PRM/KA/RERA/1268/378/PR/190724/002728
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
SANKALP SKY VILLAS is a Residential/Group Housing project by SANKALP CONSTRUCTIONS PRIVATE LIMITED in Mysore, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1268/378/PR/190724/002728 on 24 Jul 2019. Possession is promised by 30 Apr 2024. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NameSANKALP SKY VILLAS
- TypeResidential/Group Housing
- Location
- MYSORE
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1268/378/PR/190724/002728
- ReraGenie IDRG-KA-90127
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on24 Jul 2019
- Promised completion30 Apr 2024
- Revised completionRevised to 30 Apr 2024 (originally 31 Jul 2023)
- Buildings1 building record
- Documents filed48 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SANKALP SKY VILLAS | - | - | - | 12 | 0 | 12 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VERNEKAR ASSOCIATES PRIVATE LIMITED |
| Engineer | K VENKATESH BABU REDDY |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed48
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1268/378/PR/190724/002728 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Incorporation Certificate.pdf | - |
| 11 Form of Sanction | - |
| 13 Sanctioned Drawings | - |
| 13 Sanctioned Drawings | - |
| 22 Sale Deed | - |
| 21 Agreement for Sale | - |
| 8 Sale Deeds | - |
| 13 Sanctioned Drawings | - |
| 13 Sanctioned Drawings | - |
| 20 Pro-Forma of Allotment Letter | - |
| 23 Specifications | - |
| 1 EC | - |
| 16 SKV Affidavit RERA 3 | - |
| 15 SKV affidavit cum Declaration | - |
| 10 Khata Certificate & Abstract | - |
| 9 JDA | - |
| 8 Sale Deeds | - |
| 8 Sale Deeds | - |
| 4 Fire NOC | - |
| 6 Airport NOC | - |
| 5 KSPCB NOC | - |
| 2 BSNL | - |
| 13 Sanctioned Drawings | - |
| 13 Sanctioned Drawings | - |
| 8 Sale Deeds | - |
| 12 Opinion of Sky Villas | - |
| Balance Sheet 2017 - 2018File: 1 Balance Sheet 17-18-min.pdf | - |
| Balance Sheet 2016 - 2017File: Balance Sheet 16-17.pdf | - |
| Balance Sheet 2015 - 2016File: 1 Balance sheet 2016.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: 2 Profit & Loss Ac-min.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: P&L 16-17.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: 2 Profit and Loss 2016.pdf | - |
| Director's Report 2017 - 2018File: 3 Directors Report-min.pdf | - |
| Director's Report 2016 - 2017File: Directors Report.pdf | - |
| Director's Report 2015 - 2016File: 3 Directors report 2016.pdf | - |
| Cash Flow Statement 2017 - 2018File: 5 Cash flow statement.pdf | - |
| Cash Flow Statement 2016 - 2017File: Cash flow statement.pdf | - |
| Auditor's Report 2017 - 2018File: 4 Auditors Report-min.pdf | - |
| Auditor's Report 2016 - 2017File: Auditors Report.pdf | - |
| Auditor's Report 2015 - 2016File: 4 Auditor Report 2016.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: 6 ITR V.PDF | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ITR AY 2017-18.PDF | - |
| Income Tax Return Acknowledgement 2015 - 2016File: 6 ITR-V 2016-17.pdf | - |
| 14 SKV Affidavit Form B | - |
| Tower Excel SheetFile: PRM_KA_RERA_1268_378_PR_190724_002728.xlsx | - |
| Loan raised documentFile: LOAN DETAILS.pdf | - |
| Occupancy CertificateFile: SKV CR.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: SSV Affidavit for Completion of the Project.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mysore
Computed across the 700+ Mysore projects on ReraGenie, from their own filings.
Keep SANKALP SKY VILLAS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mysore700+ in Mysore
Filed coordinates, straight-line distance. 10 registered projects within 2 km.
Construction of 2446 Dus at Mandakalli Mysore
MCC
Construction of 1440 houses at lalithadripura
City Corporation Myuru
Construction of 843 G+2 Houses
Chief Officer
JAL VAYU TOWERS
AIR FORCE NAVAL HOUSING BOARD
Sanaklp Temple Tree
Sankalp Constructions private limited
SANKALP CROWN PHASE 1
SANKALP CONSTRUCTIONS PRIVATE LIMITED
See every Mysore project, with the district possession charts
Builder: SANKALP CONSTRUCTIONS PRIVATE LIMITED
SANKALP CONSTRUCTIONS PRIVATE LIMITED has 12 registrations on RERA Karnataka, including SANKALP WELLINGTON PARK and Sankalp Magnum. Its filings declare 19 earlier projects, 13 of them declared completed. Read the full track record. See more projects on the Mysore district page.
Frequently asked questions
What are my rights if SANKALP SKY VILLAS is delayed beyond 30 Apr 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SANKALP SKY VILLAS?
The registered promoter entity is SANKALP CONSTRUCTIONS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SANKALP SKY VILLAS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SANKALP SKY VILLAS?
The professionals named in the filing: Architect: VERNEKAR ASSOCIATES PRIVATE LIMITED; Engineer: K VENKATESH BABU REDDY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SANKALP SKY VILLAS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback