Home / Browse projects / Raigarh, Maharashtra / SANKALP MEADOWS
SANKALP MEADOWS
RG-MH-18588 · RERA P52000077315 · Last updated on MahaRERA portal: 30 Aug 2025
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SANKALP MEADOWS is a Plotted project by NEW PATH DEVELOPERS LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000077315 on 6 Aug 2024. The registration is recorded completed; possession was promised by 30 Jun 2025. 0 of the 142 units on this registration are recorded sold or booked.
At a glance
Project
- NameSANKALP MEADOWS
- TypePlotted
- Location
- NH-4
- MUMBAI PUNE HIGHWAY
- Village Nadhal
- Nadhal
- Khalapur
- Raigarh
- 410206
- Pincode410206
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000077315
- ReraGenie IDRG-MH-18588
Builder
- NameNEW PATH DEVELOPERS LLP
- Entity typeOthers
- LLPINAAW-4449
- LLPIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- Named personsSANGEETA SAINI, SUMAN DHAKED, LOKESH SINGH SHEKHAWAT
- Other registrations1 more →
- Completed1 of 2
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on6 Aug 2024
- Promised completion30 Jun 2025
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed50 files
Current status
Figures as on 30 Aug 2025, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 30 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities16
As on 30 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 5% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 5% |
| Open Parking | Yes | 0% |
| BLOCK BOUNDARY WORK | Yes | 5% |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | 7 Arch Associates |
| Architect | MR PRANAY P PASHILKAR |
| Engineer | Creator RCC Consultant LLP |
| Engineer | CREATOR RCC CONSULTANT LLP RUTVIJ PATEL |
| Chartered Accountant | Bharat A. Choudhary & Co. |
| Chartered Accountant | S D PARANJPE & ASSOCIATES CA SHANTANU PARANJAPE |
| Partner | Role in project |
|---|---|
| NEW PATH DEVELOPERS LLP | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 Jul 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Jul 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Jul 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 30 Aug 2025
Documents filed50
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Completion CertificateFile: copy of the acknowledgement as per land sub-division layout.pdf | 30 Aug 2025 |
| Completion CertificateFile: Completion SM.pdf | 26 Aug 2025 |
| Completion CertificateFile: CC Sankalp Medows MSRDC.pdf | 26 Jun 2025 |
| Form 1File: Form 1 Architect Certificate - NPDL.pdf | 28 May 2025 |
| Form 2File: Form 2 Engineer Certificate - NPDL.pdf | 28 May 2025 |
| Form 3File: Final Signed Form 3_31-3-2025_ CA Certificate - SM.pdf | 28 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclsoure of Sold and Booked Inventory_Sankalp Meadows.pdf | 28 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate - NPDL.pdf | 12 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Signed Form 3_31-3-2025_ CA Certificate - SM.pdf | 12 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate - NPDL.pdf | 12 May 2025 |
| Proforma of Agreement for saleFile: Agreement for Sale Final - amended.pdf | 29 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate NPDL - Final.pdf | 24 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca Certificate NDPLL Mumbai_0001_compressed.pdf | 24 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate NDPLL_0001.pdf | 24 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: R-1 2nd Quater NPDL.pdf | 7 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: R-3 2nd Quater NPDL_compressed.pdf | 7 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: R-3 2nd Quater NPDL_compressed.pdf | 7 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R-2 2nd Quater NPDL.pdf | 7 Nov 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 2 Other - Legal.pdf | 31 Jul 2024 |
| Other - LegalFile: 2.pdf | 29 Jul 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: p1.pdf | 25 Jul 2024 |
| Other - TechnicalFile: New path (1).pdf | 24 Jul 2024 |
| Other - TechnicalFile: NEW PATH.pdf | 24 Jul 2024 |
| Layout approvalFile: CC Layout.pdf | 19 Jul 2024 |
| Copy of the legal title reportFile: CC 13 acres_11zon.pdf | 19 Jul 2024 |
| Details of encumbrances concerned to FinanceFile: Finance_Legal_merged.pdf | 19 Jul 2024 |
| Details of encumbrances concerned to FinanceFile: Legal_Finance_merged.pdf | 19 Jul 2024 |
| Details of encumbrances concerned to LegalFile: Finance_Legal_merged.pdf | 19 Jul 2024 |
| Details of encumbrances concerned to LegalFile: Legal_Finance_merged.pdf | 19 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: CC Layout.pdf | 19 Jul 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Nadhal 13 Acres final CC Letter.pdf | 19 Jul 2024 |
| Declaration about Commencement CertificateFile: CC_0001.pdf | 19 Jul 2024 |
| Proforma of Agreement for saleFile: Agreement for Sale Final.pdf | 19 Jul 2024 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 19 Jul 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Bank Letter.pdf | 19 Jul 2024 |
| Deviation Report with respect to Allotment letterFile: Allotment Letter_0001.pdf | 19 Jul 2024 |
| Deviation Report with respect to model copy of AgreementFile: AFS DEVIATION FINAL.pdf | 19 Jul 2024 |
| Other - LegalFile: Board regulation_0001.pdf | 19 Jul 2024 |
| Other - FinanceFile: Board regulation_0001.pdf | 19 Jul 2024 |
| Other - TechnicalFile: Board regulation_0001.pdf | 19 Jul 2024 |
| Building plan approval or NA orderFile: 13 acre NA order.pdf | 18 Jul 2024 |
| PAN CardFile: PANCARD - New path.pdf | 18 Jul 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 13 acre NA order.pdf | 18 Jul 2024 |
| Declaration in FORM BFile: Form B_0001.pdf | 18 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate.pdf | 18 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate.pdf | 18 Jul 2024 |
| CERSAI detailsFile: CERSAI_Search_Report_200313592265_For_Asset_Based_Search_13_07_2024_15_44_26_031.pdf | 18 Jul 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: Secure_0001.pdf | 18 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate_11zon.pdf | 18 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Discloser 4_0001.pdf | 18 Jul 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 50 filed documents as one ZIP, foldered, with a manifest
Keep SANKALP MEADOWS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Village Nadhal5,900+ in Raigarh
Filed coordinates, straight-line distance. 11 registered projects within 2 km.
SHREE RAM DELTA
Shreenathji Enterprises
Brillante
Callista Realty Limited
SAI SUNCITY PHASE 3
Chariot Properties LLP
ANANDAM PHASE - II
TODAY GLOBAL HOMES
Maximus Residency Phase-I
Superb Maa Developers LLP
Sai Vrindavan Dham
KT & LK SWEET HOMES
See every Raigarh project, with the district possession charts
Builder: NEW PATH DEVELOPERS LLP
NEW PATH DEVELOPERS LLP has 2 registrations on MahaRERA, including SANKALP MEADOWS and MEADOWS SHOPPING CENTER. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if SANKALP MEADOWS is delayed beyond 30 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SANKALP MEADOWS?
The registered promoter entity is NEW PATH DEVELOPERS LLP, an others as per the filing. Its LLPIN AAW-4449 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SANKALP MEADOWS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SANKALP MEADOWS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SANKALP MEADOWS?
The professionals named in the filing: Architect: 7 Arch Associates; Architect: MR PRANAY P PASHILKAR; Engineer: Creator RCC Consultant LLP; Engineer: CREATOR RCC CONSULTANT LLP RUTVIJ PATEL; Chartered Accountant: Bharat A. Choudhary & Co.; Chartered Accountant: S D PARANJPE & ASSOCIATES CA SHANTANU PARANJAPE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SANKALP MEADOWS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback