ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / SANDESH PARK VIEW - 2

Completed No litigation declared Plotted project

SANDESH PARK VIEW - 2

By AMPLE MERCANTILE PRIVATE LIMITED

RG-MH-80672 · RERA P50500054312 · Last updated on MahaRERA portal: 27 Feb 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedregistration recorded completed
3 of 24Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 57 documents Report an error

SANDESH PARK VIEW - 2 is a Plotted project by AMPLE MERCANTILE PRIVATE LIMITED in Nagpur, Maharashtra, registered with MahaRERA as P50500054312 on 15 Jan 2024. The registration is recorded completed; possession was promised by 31 Dec 2026. 21 of the 24 units on this registration are recorded sold or booked.

At a glance

Project

  • NameSANDESH PARK VIEW - 2
  • TypePlotted
  • Location
    • WARDHA ROAD
    • JAMTHA
    • Nagpur (Rural)
    • Nagpur
    • 441108
  • Pincode441108
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500054312
  • ReraGenie IDRG-MH-80672

Builder

  • NameAMPLE MERCANTILE PRIVATE LIMITED
  • Entity typeCompany
  • DirectorsRAMDEO PRALHADRAI AGRAWAL, DILIP PRALHADRAI AGRAWAL
  • Other registrations3 more →
  • Completed3 of 4
  • Declared earlier projects3 →

Key dates

this monthRegisteredJan 2024PromisedDec 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on15 Jan 2024
  • Promised completion31 Dec 2026
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed57 files

Current status

88%21 of 24 units booked
100.0%Work done, per cost certificate

Figures as on 27 Feb 2026, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 27 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,130 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityNagpur Metropolitan Region Development Authority

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDHANTOLI, NAGPUR
Estimated costRs 96.64 lakh
Cost incurredRs 96.64 lakh
Work done100.0%
BuildingWingEstimatedIncurred
-NARs 96.64 lakhRs 96.64 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Kalyani Adhau Design Studio
ArchitectUMESH LAMGE
EngineerSanjay Birla
Chartered AccountantGAD & ASSOCIATES
PartnerRole in project
AMPLE MERCANTILE PRIVATE LIMITED-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Jul 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Mar 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Jul 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 27 Feb 2026

Documents filed57

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Completion CertificateFile: SANDESH PARK VIEW-2 OC MERGE.pdf27 Feb 2026
Withdrawal Update Form 1File: FORM 1 Sandesh Park View-2_Dec-2025.pdf20 Jan 2026
Withdrawal Update Form 2File: FORM 2 Sandesh Park View-2_Dec-2025.pdf20 Jan 2026
Withdrawal Update Form 3File: FORM 3 Sandesh Park View-2_Dec-2025.pdf20 Jan 2026
Withdrawal Update Form 1File: FORM-1 SEPT-25.pdf18 Oct 2025
Withdrawal Update Form 1File: FORM-1 SEPT-25.pdf18 Oct 2025
Withdrawal Update Form 2File: FORM-2 SEPT-25.pdf18 Oct 2025
Withdrawal Update Form 2File: FORM-2 SEPT-25.pdf18 Oct 2025
Withdrawal Update Form 3File: FORM-3 SEPT-25 SANDESH PARK VIEW 2 SCANNED COMPRESSED.pdf18 Oct 2025
Withdrawal Update Form 3File: FORM-3 SEPT-25 SANDESH PARK VIEW 2 SCANNED COMPRESSED.pdf18 Oct 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3.pdf5 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2.pdf5 Feb 2025
Disclosure of sold/ booked inventoryFile: SOLD-INVENTORY.pdf5 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sandesh Park View-2_Form-1- Architect Certificate_Dec-24.pdf4 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sandesh Park View-2_Form-1- Architect Certificate_Dec-24.pdf4 Jan 2025
Disclosure of sold/ booked inventoryFile: M-24.pdf26 Dec 2024
Disclosure of sold/ booked inventoryFile: J-24.pdf26 Dec 2024
Disclosure of sold/ booked inventoryFile: s-24.pdf26 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Sandesh Park View 2 Form 5.pdf10 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_Mar-24-A.pdf27 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_June-24-A.pdf27 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_Sep-24.pdf27 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: RL -2.pdf26 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: RL PLOT KH 169 1St Sandesh Park View-2.pdf18 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sandesh Park View-2_Form-2-Engineers Certificate JUNE 24.pdf25 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sandesh Park View-2_Form-2-Engineers Certificate_Sept 24.pdf25 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sandesh Park View-2_Form-2-Engineers Certificate MAR 24.pdf25 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1.pdf19 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Sandesh Park View-2_Form-2A_Mar-24.pdf20 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_June-24.pdf22 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sandesh Park View-2_Form-1- Architect Certificate_Mar-24.pdf16 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sandesh Park View-2_Form-1- Architect Certificate_June-24.pdf16 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_Mar-24.pdf20 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: NA ORDER.pdf3 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: form dV1_Sandesh Park View-2.pdf3 Jan 2024
Other - TechnicalFile: form dV1_Sandesh Park View-2.pdf3 Jan 2024
Other - TechnicalFile: EMAIL.pdf27 Dec 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf27 Jul 2023
Building plan approval or NA orderFile: NA SANAD.pdf26 Jul 2023
Details of encumbrances concerned to FinanceFile: ENCUMBRANCES CERTIFICATE.pdf26 Jul 2023
Details of encumbrances concerned to LegalFile: ENCUMBRANCES CERTIFICATE.pdf26 Jul 2023
Building Plan Approval / NA Order for plotted developmentFile: NA SANAD.pdf26 Jul 2023
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf26 Jul 2023
Declaration in FORM BFile: FORM B.pdf26 Jul 2023
CERSAI detailsFile: Cersai Report_merged.pdf26 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_compressed.pdf26 Jul 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Ramdeo P Agrawal.pdf26 Jul 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annnexure A Dilip p Agrawal.pdf26 Jul 2023
Proforma of Agreement for saleFile: AGREEMENT TO SALE.pdf26 Jul 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK DECLARATION.pdf26 Jul 2023
Deviation Report with respect to Allotment letterFile: Allotment Letter Declaration.pdf26 Jul 2023
Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT.pdf26 Jul 2023
Copy of the legal title reportFile: LEGAL TITLE REPORT_compressed.pdf19 Jul 2023
Layout approvalFile: LAYOUT PLAN KH NO 169.pdf2 Mar 2023
PAN CardFile: PAN - AMPLE.pdf2 Mar 2023
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN KH NO 169.pdf2 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: NA SANAD.pdf2 Mar 2023

How this compares with Nagpur

88%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is completed

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SANDESH PARK VIEW - 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near JAMTHA2,800+ in Nagpur

2 kmSANDESH PARK VIEW - 2Completed 25Lapsed / revoked 1Other 15Dot size: filed unitsN

Filed coordinates, straight-line distance. 41 registered projects within 2 km.

Builder: AMPLE MERCANTILE PRIVATE LIMITED

AMPLE MERCANTILE PRIVATE LIMITED has 4 registrations on MahaRERA, including SANDESH PARK VIEW and SANDESH PARK VIEW - 2. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if SANDESH PARK VIEW - 2 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SANDESH PARK VIEW - 2?

The registered promoter entity is AMPLE MERCANTILE PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SANDESH PARK VIEW - 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SANDESH PARK VIEW - 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SANDESH PARK VIEW - 2?

The professionals named in the filing: Architect: Ar Kalyani Adhau Design Studio; Architect: UMESH LAMGE; Engineer: Sanjay Birla; Chartered Accountant: GAD & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SANDESH PARK VIEW - 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SANDESH PARK VIEW - 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SANDESH PARK VIEW - 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.