ReraGenieLog inGet a buyer report

Home / Browse projects / Ahmednagar, Maharashtra / SAMRUDDHI NAGAR

Registration lapsed No litigation declared Residential / Group Housing project

SAMRUDDHI NAGAR

By SAMRUDDHI CONSTRUCTION

RG-MH-59339 · RERA P52200015362 · Last updated on MahaRERA portal: 12 Jun 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date
  • Completion date moved by 58 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ahmednagar registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
0 of 66Construction stages doneacross 6 buildings; furthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 161 documents Report an error

SAMRUDDHI NAGAR is a Residential / Group Housing project by SAMRUDDHI CONSTRUCTION in Ahmednagar, Maharashtra, registered with MahaRERA as P52200015362 on 20 Feb 2018. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 58 months from the original filing.

At a glance

Project

  • NameSAMRUDDHI NAGAR
  • TypeResidential / Group Housing
  • Location
    • WAKODI
    • AHMEDNAGAR
    • Ahmadnagar (M Corp.)
    • Nagar
    • 414001
  • Pincode414001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52200015362
  • ReraGenie IDRG-MH-59339

Builder

  • NameSAMRUDDHI CONSTRUCTION
  • Entity typePartnership
  • PartnersRAJENDRA SURYABHAN PACHE, POPATLAL KASTURCHAND KATARIYA, NITIN POPATLAL SHINGAVI, SUBHASH LAXMANRAO KALE, SAGAR SUBHASH KALE
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live2 lapsed, de-registered or revoked

Key dates

7 months past promisethis monthRegisteredFeb 2018First promiseMay 2021Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on20 Feb 2018
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 28 May 2021)
  • Buildings6 building records
  • Documents filed161 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA90000
WING BNA50000
WING CNA60000
WING FNA60000
WING DNA60000
WING ENA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 12 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Excavation, at 0%.

WING A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING C0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING F0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING D0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING E0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 12 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed6

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots6
Closed/Covered6
BuildingClosed/CoveredTotal
WING A11
WING B11
WING C11
WING F11
WING D11
WING E11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,206 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authoritytown planning
Permissible FSI7208.0
Proposed, not sanctioned7,835 sq m
Buildings approved6
Buildings sanctioned6

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchM GM ROAD AHMEDNAGAR

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCHANDRAKANT TAGAD
ArchitectKALYAN NAMDEV SONAWANE
EngineerSATISH SHINDE
Chartered Accountantp m bhandari and co
PartnerRole in project
SAMRUDDHI CONSTRUCTION-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52200009598May 2021 → Mar 2026

Reason as filed by the promoterDUE TO PANDEMIC SITUATION ONLY WING C AND WING D WERE COMPLETED ALONGWITH COMPLETION WHEREAS THE CONSTRUCTION FOR WING A WING B WING E AND WING F HAS NOT BEEN STARTED NOT BOOKING FOR THE SAME HAS BEEN TAKEN.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Feb 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Feb 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Feb 2018
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed161

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 161 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: form1.pdf12 Jun 2026
Form 2File: form 2.pdf12 Jun 2026
Form 3File: Form 3.pdf12 Jun 2026
Disclosure of Sold and Booked InventoryFile: unit details.pdf12 Jun 2026
Form 1File: form1.pdf12 Jun 2026
Form 2File: form 2.pdf12 Jun 2026
Form 3File: Form 3.pdf12 Jun 2026
Disclosure of Sold and Booked InventoryFile: unit details.pdf12 Jun 2026
Form 2A (FY 2017-2018)File: FORM-2A_compressed.pdf13 Oct 2025
Form 2A (FY 2018-2019)File: FORM-2A_compressed.pdf13 Oct 2025
Form 2A (FY 2019-2020)File: FORM-2A_compressed.pdf13 Oct 2025
Form 2A (FY 2020-2021)File: FORM-2A_compressed.pdf13 Oct 2025
Form 2A (FY 2021-2022)File: FORM-2A_compressed.pdf13 Oct 2025
Form 2A (FY 2022-2023)File: FORM-2A_compressed.pdf13 Oct 2025
Form 2A (FY 2023-2024)File: FORM-2A_compressed.pdf13 Oct 2025
Form 2A (FY 2024-2025)File: FORM-2A_compressed.pdf13 Oct 2025
Form 1File: ARCHITECT CERTIFICATE.pdf12 Oct 2025
Form 2File: ENGINEERS CERTIFICATE.pdf12 Oct 2025
Form 3File: FORM 3.pdf12 Oct 2025
Disclosure of Sold and Booked InventoryFile: UNIT DETAILS.pdf12 Oct 2025
Form 1File: ARCHITECT CERTIFICATE.pdf12 Oct 2025
Form 2File: ENGINEERS CERTIFICATE.pdf12 Oct 2025
Form 3File: FORM 3.pdf12 Oct 2025
Disclosure of Sold and Booked InventoryFile: UNIT DETAILS.pdf12 Oct 2025
Form 1File: ARCHITECT CERTIFICATE.pdf12 Oct 2025
Form 2File: ENGINEERS CERTIFICATE.pdf12 Oct 2025
Form 3File: FORM 3.pdf12 Oct 2025
Disclosure of Sold and Booked InventoryFile: UNIT DETAILS.pdf12 Oct 2025
Form 1File: ARCHITECT CERTIFICATE.pdf12 Oct 2025
Form 2File: ENGINEERS CERTIFICATE.pdf12 Oct 2025
Form 3File: FORM 3.pdf12 Oct 2025
Disclosure of Sold and Booked InventoryFile: UNIT DETAILS.pdf12 Oct 2025
Form 1File: ARCHITECT CERTIFICATE.pdf12 Oct 2025
Form 2File: ENGINEERS CERTIFICATE.pdf12 Oct 2025
Form 3File: FORM 3.pdf12 Oct 2025
Disclosure of Sold and Booked InventoryFile: UNIT DETAILS.pdf12 Oct 2025
Form 1File: ARCHITECT CERTIFICATE.pdf12 Oct 2025
Form 2File: ENGINEERS CERTIFICATE.pdf12 Oct 2025
Form 3File: FORM 3.pdf12 Oct 2025
Disclosure of Sold and Booked InventoryFile: UNIT DETAILS.pdf12 Oct 2025
Form 1File: ARCHITECT CERTIFICATE.pdf12 Oct 2025
Form 2File: ENGINEERS CERTIFICATE.pdf12 Oct 2025
Form 3File: FORM 3.pdf12 Oct 2025
Disclosure of Sold and Booked InventoryFile: UNIT DETAILS.pdf12 Oct 2025
Form 1File: ARCHITECT CERTIFICATE.pdf12 Oct 2025
Form 2File: ENGINEERS CERTIFICATE.pdf12 Oct 2025
Form 3File: FORM 3.pdf12 Oct 2025
Disclosure of Sold and Booked InventoryFile: UNIT DETAILS.pdf12 Oct 2025
Form 1File: ARCHITECT CERTIFICATE.pdf12 Oct 2025
Form 2File: ENGINEERS CERTIFICATE.pdf12 Oct 2025
Form 3File: FORM 3.pdf12 Oct 2025
Disclosure of Sold and Booked InventoryFile: UNIT DETAILS.pdf12 Oct 2025
Form 1File: ARCHITECT CERTIFICATE.pdf12 Oct 2025
Form 2File: ENGINEERS CERTIFICATE.pdf12 Oct 2025
Form 3File: FORM 3.pdf12 Oct 2025
Disclosure of Sold and Booked InventoryFile: UNIT DETAILS.pdf12 Oct 2025
Form 1File: ARCHITECT CERTIFICATE.pdf12 Oct 2025
Form 2File: ENGINEERS CERTIFICATE.pdf12 Oct 2025
Form 3File: FORM 3.pdf12 Oct 2025
Disclosure of Sold and Booked InventoryFile: UNIT DETAILS.pdf12 Oct 2025
Form 1File: ARCHITECT CERTIFICATE.pdf12 Oct 2025
Form 2File: ENGINEERS CERTIFICATE.pdf12 Oct 2025
Form 3File: FORM 3.pdf12 Oct 2025
Disclosure of Sold and Booked InventoryFile: UNIT DETAILS.pdf12 Oct 2025
Form 1File: ARCHITECT CERTIFICATE.pdf12 Oct 2025
Form 2File: ENGINEERS CERTIFICATE.pdf12 Oct 2025
Form 3File: FORM 3.pdf12 Oct 2025
Disclosure of Sold and Booked InventoryFile: UNIT DETAILS.pdf12 Oct 2025
Form 1File: ARCHITECT CERTIFICATE.pdf12 Oct 2025
Form 2File: ENGINEERS CERTIFICATE.pdf12 Oct 2025
Form 3File: FORM 3.pdf12 Oct 2025
Disclosure of Sold and Booked InventoryFile: UNIT DETAILS.pdf12 Oct 2025
Form 1File: ARCHITECT CERTIFICATE.pdf12 Oct 2025
Form 2File: ENGINEERS CERTIFICATE.pdf12 Oct 2025
Form 3File: FORM 3.pdf12 Oct 2025
Disclosure of Sold and Booked InventoryFile: UNIT DETAILS.pdf12 Oct 2025
Form 1File: ARCHITECT CERTIFICATE.pdf12 Oct 2025
Form 2File: ENGINEERS CERTIFICATE.pdf12 Oct 2025
Form 3File: FORM 3.pdf12 Oct 2025
Disclosure of Sold and Booked InventoryFile: UNIT DETAILS.pdf12 Oct 2025

How this compares with Ahmednagar

7%of Ahmednagar projects moved their completion datethis one moved by 58 months
28%of Ahmednagar registrations have lapsed or been cancelledthis one is among them

Computed across the 490+ Ahmednagar projects on ReraGenie, from their own filings.

Keep SAMRUDDHI NAGAR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near AHMEDNAGAR490+ in Ahmednagar

Builder: SAMRUDDHI CONSTRUCTION

SAMRUDDHI CONSTRUCTION has 4 registrations on MahaRERA, including SAI NIRMAL APPARTMENT and SAMRUDDHI NAGAR. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ahmednagar district page.

Frequently asked questions

What does it mean that SAMRUDDHI NAGAR shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SAMRUDDHI NAGAR is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAMRUDDHI NAGAR?

The registered promoter entity is SAMRUDDHI CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAMRUDDHI NAGAR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAMRUDDHI NAGAR?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAMRUDDHI NAGAR?

The professionals named in the filing: Architect: CHANDRAKANT TAGAD; Architect: KALYAN NAMDEV SONAWANE; Engineer: SATISH SHINDE; Chartered Accountant: p m bhandari and co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAMRUDDHI NAGAR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAMRUDDHI NAGAR. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAMRUDDHI NAGAR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.