Home / Browse projects / Nashik, Maharashtra / Samruddhi Business Park

Registered No litigation declared Commercial project

Samruddhi Business Park

By Anandraj Infrastructure LLP

RG-MH-14882 · RERA P51600033271 · Last updated on MahaRERA portal: 26 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 39 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 39 months from the original
3 of 11Construction stages donefurthest along: Staircases, 80%
4 of 16Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 59 documents Report an error

Samruddhi Business Park is a Commercial project by Anandraj Infrastructure LLP in Nashik, Maharashtra, registered with MahaRERA as P51600033271 on 15 Feb 2022. Possession is promised by 31 Mar 2027. The completion date has moved by 39 months from the original filing. 12 of the 16 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameSamruddhi Business Park
  • TypeCommercial
  • Location
    • Nasik Aurangabad Road
    • Kapaleshwar Nagar
    • Nashik
    • 422003
  • Pincode422003
  • RERA no.P51600033271
  • ReraGenie IDRG-MH-14882

Builder

  • NameAnandraj Infrastructure LLP
  • Entity typePartnership
  • PartnersUddhav Ananda Ahire, Abhay Ambalal Nahar, Vaishali Uddhav Ahire
  • Other registrations2 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredFeb 2022First promiseDec 2023Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Feb 2022
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Dec 2023)
  • Buildings1 building record
  • Documents filed59 files

Current status

75%12 of 16 units booked
99.5%Work done, per cost certificate

Figures as on 26 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Samruddhi Business ParkNA3301616

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 80%.

Samruddhi Business Park: 42% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)-
Podiums (if any)0%
Plinth100%
Stilt Floor-
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 26 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed10

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots10
Closed/Covered10

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area920 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on29 Sep 2025

Approvals and building plan

Sanctioning authorityTown Planning - Nashik Municipal Corporation
Permissible FSI1029.5
Proposed, not sanctioned1,030 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNashik
Estimated costRs 2.11 cr
Cost incurredRs 2.10 cr
Work done99.53%
BuildingWingEstimatedIncurred
Samruddhi Business ParkNARs 2.00 crRs 2.00 cr
-NARs 11.00 lakhRs 10.00 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSumit M. Kumath
EngineerBhushan Shintre
Chartered AccountantJain Chhajed & Associates
PartnerRole in project
Anandraj Infrastructure LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA22012619544Dec 2023 → Mar 2027

Reason as filed by the promoterDue to inadequate bookings from the customer, the construction activities are progressing at a slower pace than anticipated. Also, there might be change in the end-use of the bigger size units of 101 & 201 having carpet area 244.50 Sq. Mtr. & 242.52 Sq. Mtr. respectively. Consequently, additional time will be required to complete the project and find a suitable buyer of such large units.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Feb 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Feb 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Feb 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed59

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Business Park - Dec 2023.pdf26 May 2026
Withdrawal Update Form 1File: Form 1 - Business Park - June 2025.pdf26 May 2026
Withdrawal Update Form 1File: Form 1 - Business Park - Sep 2025.pdf26 May 2026
Withdrawal Update Form 1File: Form 1 - Business Park - Dec 2025.pdf26 May 2026
Withdrawal Update Form 2File: Form 2 - Business Park - June 2025.pdf26 May 2026
Withdrawal Update Form 2File: Form 2 - Business Park - June 2025.pdf26 May 2026
Withdrawal Update Form 2File: Form 2 - Business Park - Sep 2025.pdf26 May 2026
Withdrawal Update Form 2File: Form 2 - Business Park - Dec 2025.pdf26 May 2026
Withdrawal Update Form 3File: Form 3 Business Park June 2025.pdf26 May 2026
Withdrawal Update Form 3File: Form 3 Business Park June 2025.pdf26 May 2026
Withdrawal Update Form 3File: Form 3 - Business Park - Sept 2025.pdf26 May 2026
Withdrawal Update Form 3File: Form 3 - Business Park - Dec 2025.pdf26 May 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Business Park - Dec 2024 v1.pdf12 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Business Park - March 2025 v1.pdf12 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Samruddhi Business Park FY 2023-24.pdf12 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Business Park - Mar 2024.pdf10 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Business Park - June 2024.pdf10 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Business Park - Sept 2024.pdf10 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Business Park - Dec 2024.pdf10 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Business Park - Mar 2025.pdf10 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Business Park - Dec 2024.pdf10 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Business Park - March 2025.pdf10 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Business Park - Mar 2024.pdf10 May 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold - Booked Inventory - BP - Mar 24.pdf10 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Samruddhi Business Park - Mar 24.pdf10 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Business Park - Sept 2024.pdf25 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Business Park - Mar 2024.pdf13 Aug 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold - Booked Inventory - Business Park v1.pdf29 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Business Park - Mar 2023.pdf19 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Business Park - Sept 2023.pdf19 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Business Park - Dec 2023.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Business Park - Mar 2023.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Business Park - Sept 2023.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Business Park - Dec 2023.pdf19 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Samruddhi Business Park - Mar 22.pdf20 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Business Park - Sept 2023.pdf19 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Business Park - Dec 2023.pdf19 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - FY 2022-23.pdf19 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Business Park - Mar 23 v1.pdf3 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - Samruddhi Business Park FY 2021-22.pdf30 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Business Park - Mar 22.pdf20 Mar 2023
Layout approvalFile: Approved Building Plan 1-2.pdf11 Feb 2022
Building plan approvalFile: Approved Building Plan 1-2.pdf11 Feb 2022
Building plan approvalFile: Approved Building Plan 2-2.pdf11 Feb 2022
Copy of Layout Approval (in case of layout)File: Approved Building Plan 1-2.pdf11 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: Approved Building Plan 1-2.pdf11 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: Approved Building Plan 2-2.pdf11 Feb 2022
CERSAI detailsFile: CERSAI_Search_Report.pdf11 Feb 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate.pdf11 Feb 2022
Copy of the legal title reportFile: Legal title Report.pdf8 Feb 2022
Details of encumbrancesFile: Non Encumbrance Certificate.pdf8 Feb 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf8 Feb 2022
Declaration about Commencement CertificateFile: Commencement Certificate - Declaration.pdf8 Feb 2022
Declaration in FORM BFile: Form B.pdf8 Feb 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate.pdf8 Feb 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer's Certificate.pdf8 Feb 2022
Proforma of Allotment letterFile: Draft Letter of Allotment.pdf8 Feb 2022
Proforma of Allotment letterFile: Draft Agreement for Sale.pdf8 Feb 2022
PAN CardFile: PAN - Anandraj Infrastructure LLP.pdf12 Jan 2022

How this compares with Nashik

75%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one moved by 39 months
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Samruddhi Business Park on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kapaleshwar Nagar4,100+ in Nashik

Builder: Anandraj Infrastructure LLP

Anandraj Infrastructure LLP has 3 registrations on MahaRERA, including SAMRUDDHI PARK and Samruddhi Business Park. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if Samruddhi Business Park is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Samruddhi Business Park?

The registered promoter entity is Anandraj Infrastructure LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Samruddhi Business Park?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Samruddhi Business Park?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Samruddhi Business Park?

The professionals named in the filing: Architect: Sumit M. Kumath; Engineer: Bhushan Shintre; Chartered Accountant: Jain Chhajed & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Samruddhi Business Park?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Samruddhi Business Park. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Samruddhi Business Park to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.