SAMARTH TANISH
RG-MH-19753 · RERA P51800003379 · Last updated on MahaRERA portal: 10 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 14 complaints at MahaRERA
- Completion date moved by 36 months
- 3 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAMARTH TANISH is a Residential / Group Housing project by NITIN DATTARAM SAMANT in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003379 on 5 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 64 of the 133 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 14 complaints are on record with the regulator.
At a glance
Project
- NameSAMARTH TANISH
- TypeResidential / Group Housing
- Location
- J P ROAD NO.5
- GOREGAON EAST
- Borivali
- Mumbai Suburban
- 400063
- Pincode400063
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800003379
- ReraGenie IDRG-MH-19753
Builder
- NameNITIN DATTARAM SAMANT
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on5 Aug 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2023)
- Buildings1 building record
- Documents filed69 files
Current status
Figures as on 10 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SAMARTH TANISH | NA | 25 | 23 | 133 | 0 | 133 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 10 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 97%.
SAMARTH TANISH: 78% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 97% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 10 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed29
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SAMARTH TANISH | NA | Rs 51.30 cr | Rs 50.27 cr |
| - | NA | Rs 51.30 cr | Rs 50.27 cr |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SAMARTH ASSOCIATES |
| Engineer | SOAHM CONSULTANTS |
| Chartered Accountant | APRAJ AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| NITIN DATTARAM SAMANT | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDUE TO COVID 19 WE ARE NOT ABLE TO COMPLETE OUR PROJECT AND SHORTAGE OF MATERIAL PLEASE GRANT US EXTENSION FOR 12 MONTHS
Reason as filed by the promoterWith reference to delay in possession of the site Samarth Tanish, we would like to clarify on certain points as mentioned below. On 26/09/19 as per IOD Flats bearing 269 sq.ft were converted into 300 sq.ft area as the overall process consumed nearly one year. On 07/11/19 & 24/03/21 there were changes in Plan / CC endorsement and because of the re-endorsed plans there was delay in execution of the site progress. On 2021 as per DPCR 2034, number of Sale flats in A Wing were increased and therefore the procedure consumed 7 to 8 months of time. Above mentioned points have resulted in delayed posse
Reason as filed by the promoterWe reference to the above subject we Samarth Erectors and Developers would like mention the reasons for overall delay in completing the site. We had received LOI for constructing area of 225 sq.ft flats but later was revised to area I of 269 sq.ft flats. Vacating of site (tenants shifting work) was carried out for another three years span. Again due to change in rules we had to apply for revised LOI ie area of 269 sq.ft flats were converted to to 300 sqft. Corona pandemic hit so badly that the site work stopped completely for nearly two years. In Feb 2023, SRA issued letter to stop work and we
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 3019/2014 | CITY CIVIL COURT DINDOSHI | CHAMBER SUMMONS FOR VERIFICATION OF ORIGINAL ALLOTMENT LETTER |
Complaints filed with MahaRERA14
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000012653 | UMESH VASANTLAL SHAH | NITIN DATTARAM SAMANT | 06/01/2018 |
| CC006000000022913 | Trupti More | Nitin Dattaram Samant | 25/01/2018 |
| CC006000000209380 | Shri.Bhavanishankar Kalnad and Smt.Sujatha Kalnad | M/s.Samarth Erectors and Developers | 12/02/2022 |
| CC006000000209762 | AJAY K VAKIL AND PRITI AJAY VAKIL | SAMARTH ERECTORS AND DEVELOPERS | 21/01/2022 |
| CC006000000396468 | DIPAK MIRAJKAR | M/S. SAMARTH ERECTORS & DEVELOPERS | 01/07/2023 |
| CC006000000428795 | LAXMIKANT PRAKASH GAIKWAD | MR NITIN DATTARAM SAMANT | 16/01/2024 |
| CC12401219 | Mr Ajay Krishnakant Vakil | NITIN DATTARAM SAMANT | 24/12/2024 |
| CC12401220 | Mr Ajay Krishnakant Vakil | NITIN DATTARAM SAMANT | 24/12/2024 |
| CC12401222 | Mr Ajay Krishnakant Vakil | NITIN DATTARAM SAMANT | 24/12/2024 |
| CC12500363 | Datta prasad Sadwelkar | NITIN DATTARAM SAMANT | 03/02/2025 |
| CC12500372 | Datta Prasad Sadwelkar | NITIN DATTARAM SAMANT | 04/02/2025 |
| CC12500842 | DIPAK GANGARAM MIRAJKAR | NITIN DATTARAM SAMANT | 11/03/2025 |
| CC12602804 | KOMAL SANDEEP NAIK | Samarth Erectors and Developers (Developers) | 14/05/2026 |
| CC12603154 | Priya Anil | NITIN DATTARAM SAMANT | 27/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed69
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Architect Certificate.pdf | 10 Aug 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 10 Aug 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 10 Aug 2026 |
| Withdrawal Update Form 1File: Architect Certificate.pdf | 8 Aug 2026 |
| Withdrawal Update Form 2File: Engineer Form 2.pdf | 8 Aug 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 8 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 June 2025.pdf | 4 Feb 2026 |
| Withdrawal Update Form 2File: Engineer Form 2.pdf | 4 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 (5).pdf | 4 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 June 2025.pdf | 29 Dec 2025 |
| Withdrawal Update Form 2File: Form 2 (6).pdf | 29 Dec 2025 |
| Withdrawal Update Form 3File: Form 3 (4).pdf | 29 Dec 2025 |
| Withdrawal Update Form 1File: Form 1 June 2025.pdf | 24 Dec 2025 |
| Withdrawal Update Form 2File: Form 2 June 2025.pdf | 24 Dec 2025 |
| Withdrawal Update Form 3File: Form 3 June 25.pdf | 24 Dec 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 26 Apr 2025 |
| Certificates of CA (Form 3)File: form 3.pdf | 26 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 26 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Revised Inventory.pdf | 11 Mar 2025 |
| Declaration in FORM BFile: Form B (4).pdf | 20 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Form 1.pdf | 20 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Form 2.pdf | 20 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: Form -3-31-3-2023.pdf | 25 Jan 2025 |
| Certificates of CA (Form 3)File: Form-3-31-3-2024.pdf | 25 Jan 2025 |
| Certificates of CA (Form 3)File: Form -3-30-6-2024.pdf | 25 Jan 2025 |
| Certificates of CA (Form 3)File: Form-3-30-09-2024.pdf | 25 Jan 2025 |
| Certificates of CA (Form 3)File: Form-3-31-12-2024.pdf | 25 Jan 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Navpada Undated CC.pdf | 25 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Inventary.pdf | 25 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer form 2A 2023 24.pdf | 15 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 14 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Form 2.pdf | 14 Jan 2025 |
| Declaration in FORM BFile: Form B.pdf | 20 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 19 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Form 2.pdf | 19 Dec 2023 |
| Declaration about Commencement CertificateFile: CC Declaration.pdf | 9 Dec 2023 |
| CERSAI detailsFile: Cersai declaration.pdf | 9 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Inventary.pdf | 9 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CA form 5 22-23.pdf | 9 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2019-2020.pdf | 6 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2020-2021.pdf | 6 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2021-2022.pdf | 6 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2022-2023.pdf | 6 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Samarth 18-19.pdf | 15 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Samarth 18-19.pdf | 15 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Samarth 19-20.pdf | 15 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Samarth FY20-21.pdf | 15 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Samarth 21-22.pdf | 15 May 2023 |
| Certificates of CA (Form 3)File: Form 31-3-18_compressed.pdf | 9 May 2023 |
| Certificates of CA (Form 3)File: Form 31-3-19_compressed.pdf | 9 May 2023 |
| Certificates of CA (Form 3)File: Form 31-3-20_compressed.pdf | 9 May 2023 |
| Certificates of CA (Form 3)File: Form 31-3-21_compressed.pdf | 9 May 2023 |
| Certificates of CA (Form 3)File: Form 31-3-22_compressed.pdf | 9 May 2023 |
| PAN CardFile: NDSNew Pan Card (1).pdf | 6 Oct 2022 |
| Layout approvalFile: NAVPADA LAY OUT.pdf | 28 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: NAVPADA LAY OUT.pdf | 28 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: NAVPADA ARCH CERT.PDF | 28 Jul 2017 |
| Certificates of CA (Form 3)File: NAVPADA FORM 3 CA.PDF | 28 Jul 2017 |
| Building plan approvalFile: NAVPADA IOD 2014.PDF | 27 Jul 2017 |
| Building plan approvalFile: NAVPADA IOD.PDF | 27 Jul 2017 |
| Copy of the legal title reportFile: NAVPADA TITLE.PDF | 27 Jul 2017 |
| Details of encumbrancesFile: NAVPADA TITLE.PDF | 27 Jul 2017 |
| Building Plan Approval (IOD)File: NAVPADA IOD 2014.PDF | 27 Jul 2017 |
| Building Plan Approval (IOD)File: NAVPADA IOD.PDF | 27 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: NAVPADA CC.PDF | 27 Jul 2017 |
| Declaration in FORM BFile: NAVPADA FORM B.PDF | 27 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: NAVPADA FORM 2.PDF | 27 Jul 2017 |
| Proforma of Allotment letterFile: NAVPADA AGREEMENT.pdf | 27 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 69 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SAMARTH TANISH on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near GOREGAON EAST6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 353 registered projects within 2 km.
Elysian Tower C, D, E
Oberoi Realty Limited
Elysian Tower B
Oberoi Realty Limited
Elysian Tower A
Oberoi Realty Limited
Sheetal Sangam
DGS Township Pvt Ltd
SEJAL SQUARE
ALCHEMI DEVELOPERS PRIVATE LIMITED
Mehta Marquina 1978
Shreeram Builders
See every Mumbai Suburban project, with the district possession charts
Builder: NITIN DATTARAM SAMANT
NITIN DATTARAM SAMANT has 1 registration on MahaRERA, including SAMARTH TANISH. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if SAMARTH TANISH is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAMARTH TANISH?
The registered promoter entity is NITIN DATTARAM SAMANT, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAMARTH TANISH?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SAMARTH TANISH?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SAMARTH TANISH?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAMARTH TANISH?
The professionals named in the filing: Architect: SAMARTH ASSOCIATES; Engineer: SOAHM CONSULTANTS; Chartered Accountant: APRAJ AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAMARTH TANISH?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback