Home / Browse projects / Raigarh, Maharashtra / SAI SYMPHONY

Completed Litigation declared Residential / Group Housing project

SAI SYMPHONY

By Paradise Infracon Private Limited

RG-MH-49021 · RERA P52000017044 · Last updated on MahaRERA portal: 1 May 2025

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 1 complaint at MahaRERA
  • Completion date moved by 15 months
  • 2 extensions taken

Clear

  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Mar 2025Possession promisedregistration recorded completed
2 of 11Construction stages donefurthest along: Basement (if any), 90%
1Complaints at MahaRERAon this registration
Jump to the 130 documents Report an error

SAI SYMPHONY is a Residential / Group Housing project by Paradise Infracon Private Limited in Raigarh, Maharashtra, registered with MahaRERA as P52000017044 on 4 Jul 2018. The registration is recorded completed; possession was promised by 31 Mar 2025. The completion date has moved by 15 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSAI SYMPHONY
  • TypeResidential / Group Housing
  • Location
    • Ganesh Temple Road
    • Sector 35 F Kharghar Navi Mumbai
    • Owe
    • Panvel
    • Raigarh
    • 410210
  • Pincode410210
  • RERA no.P52000017044
  • ReraGenie IDRG-MH-49021

Builder

  • NameParadise Infracon Private Limited
  • Entity typeCompany
  • CINU45201MH2006PTC165752
  • ChairpersonMadhu Bhagwandas Bathija
  • Managing DirectorManish Madhu Bathija
  • DirectorAmit Madhu Bathija
  • Other registrations2 more →
  • Completed1 of 3
  • Declared earlier projects37 →

Key dates

this monthRegisteredJul 2018First promiseDec 2023Revised toMar 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on4 Jul 2018
  • Promised completion31 Mar 2025
  • Revised completionRevised to 31 Mar 2025 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed130 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAI SYMPHONYNA290000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 90%.

SAI SYMPHONY: 80% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)90%
Podiums (if any)80%
Plinth90%
Stilt Floor90%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises87%
Sanitary Fittings within the flats / premises66%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.71%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.25%

Progress on shared amenities15

As on 1 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed270

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots270
Closed/Covered214
Open Space56

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,100 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityCIDCO
Permissible FSI7640.38
Proposed, not sanctioned7,640 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSector 17 VASHI NAVI MUMBAI

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
Paradise Infracon Private Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000017766Dec 2023 → Dec 2024

Reason as filed by the promoterDespite all efforts done by Promoter the work has got delayed due to Pandemic COVID 19 first and financial difficulties later. The Promoter has availed construction finance for faster completion of the project from Indiabulls Housing Finance Limited but due to the restrictions imposed by Reserve bank of India on NBFCs the Indiabulls could not do the required disbursement of loan amount, hence Promoter negotiated a deal with IndusInd bank Limited to take over the loan granted by the Indiabulls. Finally, IndusInd bank has taken over the loan on 29.03.2022. Thereafter Construction work is going o

EXT52000025638Dec 2023 → Mar 2025

Reason as filed by the promoterThe work got delayed firstly aftermath of Pandemic COVID and afterwords due to labours shortage. Since the Contractor was sufferring from Cancer and unable to provide skilled labour required for completion of work in time the Promoter appointed new labours contractor and completed the 100 % construction work mentioned in the Table A of the Form 1 with Photograph of the building uploaded below. However the task/activity mentioned in the Table B of the Form 1 certified by Architect. The balance work is continue at site in speed. The promoter will complete the balance work and obtain OC before 31

Litigation declared1

CaseCourtStatus
502/2006Panvel Civil Courtpending

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000490391Charanpreet Singh SehgalM/S Paradise Infracon pvt Ltd07/05/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jun 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jun 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 May 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 1 Apr 2025

Documents filed130

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 130 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Building plan approvalFile: OC Plans 1.pdf1 May 2025
Building plan approvalFile: OC Plans 2.pdf1 May 2025
Building plan approvalFile: OC Plans 3.pdf1 May 2025
Building plan approvalFile: OC Plans 4.pdf1 May 2025
Building plan approvalFile: OC Plans 5.pdf1 May 2025
Building plan approvalFile: OC Plans 6.pdf1 May 2025
Building plan approvalFile: OC Plans 7.pdf1 May 2025
Building plan approvalFile: OC Plans 8.pdf1 May 2025
Building Plan Approval (IOD)File: OC Plans 1.pdf1 May 2025
Building Plan Approval (IOD)File: OC Plans 2.pdf1 May 2025
Building Plan Approval (IOD)File: OC Plans 3.pdf1 May 2025
Building Plan Approval (IOD)File: OC Plans 4.pdf1 May 2025
Building Plan Approval (IOD)File: OC Plans 5.pdf1 May 2025
Building Plan Approval (IOD)File: OC Plans 6.pdf1 May 2025
Building Plan Approval (IOD)File: OC Plans 7.pdf1 May 2025
Building Plan Approval (IOD)File: OC Plans 8.pdf1 May 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf1 Apr 2025
Other - LegalFile: CP order.pdf5 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf17 Jan 2025
Certificates of CA (Form 3)File: Form 3.pdf17 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf17 Jan 2025
Declaration in FORM BFile: Form B.pdf19 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf19 Dec 2024
Certificates of CA (Form 3)File: Form 3.pdf19 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf19 Dec 2024
Disclosure of sold/ booked inventoryFile: Sai Symphony Inventory.pdf19 Dec 2024
Declaration about Commencement CertificateFile: Declaration for Commencement Certificate.pdf19 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf17 Dec 2024
Certificates of CA (Form 3)File: Form 3.pdf17 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf17 Dec 2024
Details of encumbrancesFile: Sai Symphony.pdf7 Dec 2024
Building plan approvalFile: Sai Symphony 27 Floors-Sheet 1.pdf27 Nov 2024
Building plan approvalFile: Sai Symphony 27 Floors-Sheet 2.pdf27 Nov 2024
Building plan approvalFile: Sai Symphony 27 Floors-Sheet 3.pdf27 Nov 2024
Building plan approvalFile: Sai Symphony 27 Floors-Sheet 4.pdf27 Nov 2024
Building plan approvalFile: Sai Symphony 27 Floors-Sheet 5.pdf27 Nov 2024
Building plan approvalFile: Sai Symphony 27 Floors-Sheet 6.pdf27 Nov 2024
Building plan approvalFile: Sai Symphony 27 Floors-Sheet 7.pdf27 Nov 2024
Building plan approvalFile: Sai Symphony 27 Floors-Sheet 8.pdf27 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: CC Validated 27 Floors.pdf27 Nov 2024
Building Plan Approval (IOD)File: Sai Symphony 27 Floors-Sheet 1.pdf27 Nov 2024
Building Plan Approval (IOD)File: Sai Symphony 27 Floors-Sheet 8.pdf27 Nov 2024
Building Plan Approval (IOD)File: Sai Symphony 27 Floors-Sheet 7.pdf27 Nov 2024
Building Plan Approval (IOD)File: Sai Symphony 27 Floors-Sheet 6.pdf27 Nov 2024
Building Plan Approval (IOD)File: Sai Symphony 27 Floors-Sheet 5.pdf27 Nov 2024
Building Plan Approval (IOD)File: Sai Symphony 27 Floors-Sheet 4.pdf27 Nov 2024
Building Plan Approval (IOD)File: Sai Symphony 27 Floors-Sheet 3.pdf27 Nov 2024
Building Plan Approval (IOD)File: Sai Symphony 27 Floors-Sheet 2.pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Sai Symphony 30092024.pdf27 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf19 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf14 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf14 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Form 3.pdf14 Aug 2024
Certificates of CA (Form 3)File: Form 3.pdf9 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Signed.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Signed.pdf10 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Sai Symphony (2023-2024).pdf10 May 2024
Certificates of CA (Form 3)File: Form 3 Signed.pdf10 May 2024
Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory.pdf20 Mar 2024
Declaration about Commencement CertificateFile: Declaration for Commencement Certificate.pdf14 Oct 2023
Declaration in FORM BFile: Form B.pdf14 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf14 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf14 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A (2022-2023).pdf14 Oct 2023
Disclosure of sold/ booked inventoryFile: Inventory.pdf14 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: (Form 5) (FY 2021-22).pdf14 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf14 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Sai Symphony (2020-2021).pdf30 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Sai Symphony (2021-2022).pdf30 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Sai Symphony Apr 20-Mar 21.pdf2 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Sai Symphony Apr 21-Mar 22.pdf2 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Sai symphony FY 20-21.pdf1 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Sai symphony 21-22.pdf1 May 2023
Details of encumbrancesFile: Encumbrance Certificate.pdf11 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: CCNEW.pdf18 Feb 2022
Building plan approvalFile: 1.pdf5 Jan 2022
Building plan approvalFile: 1.pdf5 Jan 2022
Building plan approvalFile: 2.pdf5 Jan 2022
Building plan approvalFile: 3.pdf5 Jan 2022
Building plan approvalFile: 4.pdf5 Jan 2022

Promoter's earlier projects11

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

10 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Sai RiverdaleSector 7 Taloja244CompletedOct 2017Jul 2017
Sai WonderSector 35 F Kharghar95CompletedJul 2017May 2017
Sai SolitaireSector 35 H83CompletedJul 2017Jun 2016
Sai GangaSector 5 Ulwe62CompletedMay 2017Apr 2017
Sai SahilSector 5 Ulwe50CompletedMay 2017Apr 2017
Sai FortuneSector 8 Ulwe99CompletedDec 2016Nov 2016
Sai CrystalSector 35 D Kharghar166CompletedOct 2016Sep 2016
Sai SpringSector 35G Kharghar148CompletedAug 2016Jul 2016
Sai HarmonySector 21 Ulwe115CompletedJul 2016Late, Sep 2016
Sai MokshSector 15 Kharghar Navi Mumbai73CompletedDec 2015Jun 2015
Sai SapphireSector 20 Ulwe162CompletedJul 2015Jul 2015

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 15 months
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAI SYMPHONY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Sector 35 F Kharghar Navi Mumbai5,900+ in Raigarh

Builder: Paradise Infracon Private Limited

Paradise Infracon Private Limited has 3 registrations on MahaRERA, including SAI SYMPHONY and SAI PRERNA. Its filings disclose 37 earlier MahaRERA projects: declares 18 of 20 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if SAI SYMPHONY is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAI SYMPHONY?

The registered promoter entity is Paradise Infracon Private Limited, a company as per the filing. Its CIN U45201MH2006PTC165752 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAI SYMPHONY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SAI SYMPHONY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SAI SYMPHONY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in SAI SYMPHONY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI SYMPHONY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI SYMPHONY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.