Home / Browse projects / Pune, Maharashtra / Sai SparshA3,A4

Registration lapsed No litigation declared Others project

Sai SparshA3,A4

By Jalan Associates

RG-MH-11993 · RERA P52100003340 · Last updated on MahaRERA portal: 10 Nov 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 28 months past the filed date
  • Completion date moved by 54 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
10 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 65%
0Complaints at MahaRERAon this registration
Jump to the 47 documents Report an error

Sai SparshA3,A4 is a Others project by Jalan Associates in Pune, Maharashtra, registered with MahaRERA as P52100003340 on 5 Aug 2017. Possession was promised by 30 Jun 2024 and is now 28 months past that date. The completion date has moved by 54 months from the original filing.

At a glance

Project

  • NameSai SparshA3,A4
  • TypeOthers
  • Location
    • Pune Satara Highway
    • Kapurhol
    • Bhor
    • Pune
    • 412205
  • Pincode412205
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100003340
  • ReraGenie IDRG-MH-11993

Builder

  • NameJalan Associates
  • Entity typePartnership
  • PartnersDwarkaprasad Narayan Jalan, Sanjay Narayan Jalan
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

28 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Aug 2017
  • Promised completion30 Jun 2024
  • Revised completionRevised to 30 Jun 2024 (originally 31 Dec 2019)
  • Buildings2 building records
  • Documents filed47 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A3NA60000
A4NA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 10 Nov 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 65%.

A361%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.45%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A460%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Nov 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed6

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots6
Closed/Covered6
BuildingClosed/CoveredTotal
A333
A433

Land and ownership7

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,376 sq m
Land owned byThe promoter, with other names on the file
Named landowners7
LandownerVillageDistrict
Asha Dattatray GohadPune (M Corp.)Pune
Leena Asutosh GadgilPune (M Corp.)Pune
Kapil Dattatraya GohadPune (M Corp.)Pune
Pralhad Narayan GohadPune (M Corp.)Pune
Madhav Narayan GohadPune (M Corp.)Pune
Vidya Umesh GohadkapurholPune
Sanjay Narayan GohadkapurholPune

Approvals and building plan

Permissible FSI1683.06
Proposed, not sanctioned1,683 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNavi Peth Pune

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCON
EngineerDelcons Structural Consultants
PartnerRole in project
Jalan Associates-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100008618Dec 2019 → Dec 2021

Reason as filed by the promoterPrevious sanction for the Project was for 3 floors which are completed. New sanctioned plan was received on 21/10/2020 from PMRDA for the 4th floor of the building (Delayed due to Covid-19 pandemic and subsequent lockdown). Attaching Resolution of the Association of Allottees along with new Commencement Certificate received from PMRDA.

EXT52100012503Dec 2019 → Jun 2024

Reason as filed by the promoterWe M/s Jalan Associates having project named as Sai Sparsh A3, A4. Project Registration No. P52100003340 situated at Gat No. 9/1 at Kapurhol, Taluka Bhor, District Pune 412205 do hereby apply for extension of the project which has expired on 30/06/2022 for further 2 years i.e upto 30/06/2024. Explanatory note regarding the state of development works in the project and reason for not completing the development works in the project within the period declared in the declaration submitted in Form ‘B’ at the time of making application for the registration of the project ; 1. Revised Commencement Ce

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Jan 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Jan 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Jan 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed47

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Sai Sparsh A3,A4 FY 2018-19.pdf10 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Sai Sparsh A3,A4 FY 2019-20.pdf10 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Sai Sparsh A3,A4 FY 2020-21.pdf10 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Sai Sparsh A3,A4 FY 2021-22.pdf10 Nov 2022
Declaration about Commencement CertificateFile: Declaration 2022.pdf24 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance 2019-20.pdf24 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance 2020-21.pdf24 Sep 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold 2022.pdf24 Sep 2022
Disclosure of sold/ booked inventoryFile: SOLD - BOOKED - SAI SPARSH - A3,A4.pdf29 May 2021
Layout approvalFile: Layout.pdf2 Jan 2021
Building plan approvalFile: Plan 1.pdf2 Jan 2021
Building plan approvalFile: Plan 2.pdf2 Jan 2021
Building plan approvalFile: Plan 3.pdf2 Jan 2021
Copy of Layout Approval (in case of layout)File: Layout.pdf2 Jan 2021
Building Plan Approval (IOD)File: Plan 1.pdf2 Jan 2021
Building Plan Approval (IOD)File: Plan 2.pdf2 Jan 2021
Building Plan Approval (IOD)File: Plan 3.pdf2 Jan 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf2 Jan 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sai Sparsh-A3, A4_Arch Cert.pdf8 Jun 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sai Sparsh_A3,A4_Engg Cert.pdf8 Jun 2019
Certificates of CA (Form 5)File: Certificates of CA (Form 5)- A3,A4.pdf8 Jun 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sai Sparsh A3 A4 Arch Certificate 05012018 ARCON.pdf31 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sai Sparsh A3 A4 05012018 Engg Certificate.pdf31 Mar 2018
Certificates of CA (Form 3)File: Sai Sparsh A3 A4.pdf31 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: NA order and Commencement Certificate - Sai Sparsh.pdf30 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE A3A4.pdf30 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: a3,a4 engg certificate- sai sparsh.pdf30 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate -A3,A4_SAI SPARSH.pdf30 Jul 2017
Certificates of CA (Form 3)File: Sai Sparsh-A3,A4-Compressed.pdf30 Jul 2017
Layout approvalFile: Master Plan IOD 2.pdf29 Jul 2017
Building plan approvalFile: Master Plan (IOD)-2.pdf29 Jul 2017
Details of encumbrancesFile: INDEX II_1696_2015_MORTGAGE DEED_KAPURHOL_SAI SPARSH PHASE 1.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Master Plan IOD 2.pdf29 Jul 2017
Building Plan Approval (IOD)File: Master Plan (IOD)-2.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE A3A4.pdf29 Jul 2017
Layout approvalFile: 1 of 2_SAI SPARSH_KAPURHOLcompressed.pdf28 Jul 2017
Layout approvalFile: 2 of 2_SAI SPARSH_KAPURHOLcompressed.pdf28 Jul 2017
Building plan approvalFile: 1 of 2_SAI SPARSH_KAPURHOL--compressed.pdf28 Jul 2017
Building plan approvalFile: 2 of 2_SAI SPARSH_KAPURHOL--compressed.pdf28 Jul 2017
Copy of the legal title reportFile: Legal Title Report.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: 1 of 2_SAI SPARSH_KAPURHOLcompressed.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: 2 of 2_SAI SPARSH_KAPURHOLcompressed.pdf28 Jul 2017
Building Plan Approval (IOD)File: 1 of 2_SAI SPARSH_KAPURHOL--compressed.pdf28 Jul 2017
Building Plan Approval (IOD)File: 2 of 2_SAI SPARSH_KAPURHOL--compressed.pdf28 Jul 2017
Declaration in FORM BFile: FORM B-A3, A4 PROMOTER--compressed.pdf28 Jul 2017
Proforma of Allotment letterFile: Agreement_SAI SPARSH.pdf28 Jul 2017
Proforma of Allotment letterFile: Allotment_SAI SPARSH.pdf28 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 54 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sai SparshA3,A4 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kapurhol13,700+ in Pune

2 kmSai SparshA3,A4Completed 2Lapsed / revoked 1Other 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 4 registered projects within 2 km.

Builder: Jalan Associates

Jalan Associates has 2 registrations on MahaRERA, including Sai Sparsh-A1, A2 and Sai SparshA3,A4. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Sai SparshA3,A4 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Sai SparshA3,A4 is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sai SparshA3,A4?

The registered promoter entity is Jalan Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sai SparshA3,A4?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sai SparshA3,A4?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sai SparshA3,A4?

The professionals named in the filing: Architect: ARCON; Engineer: Delcons Structural Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sai SparshA3,A4?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sai SparshA3,A4. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sai SparshA3,A4 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.