Home / Browse projects / Pune, Maharashtra / SAI PARADISE
SAI PARADISE
RG-MH-33816 · RERA P52100034909 · Last updated on MahaRERA portal: 20 Jan 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAI PARADISE is a Others project by SHREE SAI SEVA DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100034909 on 28 Apr 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date. 82 of the 94 units on this registration are recorded sold or booked, and 18 of 22 construction stages are filed complete.
At a glance
Project
- NameSAI PARADISE
- TypeOthers
- Location
- SURVEY NO 124 HISSA NO 2
- DEHUGAON
- DEHU
- Haveli
- Pune
- 412109
- Pincode412109
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100034909
- ReraGenie IDRG-MH-33816
Builder
- NameSHREE SAI SEVA DEVELOPERS
- Entity typePartnership
- PartnersSAGAR NIVRUTTI BHASE, YOGESH HANUMANT KALOKHE
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on28 Apr 2022
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings2 building records
- Documents filed96 files
Current status
Figures as on 20 Jan 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SAI PARADISE BLG A and B | NA | 14 | 14 | 84 | 4 | 88 |
| SAI PARADISE BLG C | NA | 3 | 3 | 6 | 0 | 6 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 20 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.
SAI PARADISE BLG A and B82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
SAI PARADISE BLG C82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 20 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed116
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| SAI PARADISE BLG A and B | 18 | 91 | 109 |
| SAI PARADISE BLG C | 0 | 7 | 7 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SAI PARADISE BLG A and B | NA | Rs 8.80 cr | Rs 8.80 cr |
| SAI PARADISE BLG C | NA | Rs 1.16 cr | Rs 1.16 cr |
| - | NA | Rs 70.00 lakh | - |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VISION ARCHITECT AR SWAPNIL PARASHAR |
| Engineer | ANSHUMAN BHIDE |
| Engineer | PANKAJ SAHEBRAO KARANDE |
| Chartered Accountant | M S KUMBHAR AND ASSOCIATES |
| Chartered Accountant | SHRIKANT THORAT |
| Chartered Accountant | PGMJ & ASSOCIATES |
| Chartered Accountant | NITISH VAIDYA & ASSOCIATES |
| Chartered Accountant | Nilesh Mangilal Nahata |
| Partner | Role in project |
|---|---|
| SHREE SAI SEVA DEVELOPERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Feb 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Apr 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 8 Apr 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed96
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1.pdf | 20 Jan 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 20 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 final.pdf | 20 Jan 2026 |
| Form 5 (FY 2023-2024)File: Form 5 FY 23-24 Final.pdf | 24 Dec 2025 |
| Form 5 (FY 2024-2025)File: Form 5 FY 24-25 Final.pdf | 24 Dec 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 18 Nov 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 18 Nov 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 18 Nov 2025 |
| Withdrawal Update Form 1File: fORM 1.pdf | 17 Oct 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 17 Oct 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 17 Oct 2025 |
| Form 1File: Form 1 Final.pdf | 3 Oct 2025 |
| Form 2File: Form 2.pdf | 3 Oct 2025 |
| Form 3File: Form 3 Final.pdf | 3 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Circular.pdf | 3 Oct 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Final.pdf | 20 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final_compressed.pdf | 20 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final.pdf | 20 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 20 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Circular.pdf | 20 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 18 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final_compressed.pdf | 18 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 18 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Circular Final.pdf | 18 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 20 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Signed -Upload.pdf | 20 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Final.pdf | 20 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Circular.pdf | 20 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 28 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 28 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Circular.pdf | 28 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf | 28 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf | 28 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf | 28 Jun 2024 |
| Declaration about Commencement CertificateFile: Declaration Of Commencement Certificate.pdf | 17 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form1 -Q1-2022-23.pdf | 29 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form1 -Q2-2022-23.pdf | 29 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form1 -Q3-2022-23.pdf | 29 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form1-Q4-2022-23.pdf | 29 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form1-Q1-2023-24.pdf | 29 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form1 -Q2-2023-24.pdf | 29 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form 1.pdf | 29 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Final.pdf | 29 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Final Form 2 uploaded.pdf | 29 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Final Form 2 Q2 Uploaded.pdf | 29 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Final Form 2 uploaded.pdf | 29 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q4 22-23.pdf | 29 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q1 23-24.pdf | 29 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 29 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 29 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 29 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Final Form 2A.pdf | 29 May 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Circular 29 Q1.pdf | 29 May 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Circular 29 Q2.pdf | 29 May 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Circular 29 Q3.pdf | 29 May 2024 |
| Disclosure of sold/ booked inventoryFile: Final Sold Circular.pdf | 29 May 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Circular 29 Q1.pdf | 29 May 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Circular 29 Q2.pdf | 29 May 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Circular 29 Q3.pdf | 29 May 2024 |
| Disclosure of sold/ booked inventoryFile: Final Sold Circular.pdf | 29 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 FinalQ1 Uploaded_compressed.pdf | 29 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final.pdf | 29 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3.pdf | 29 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3_compressed.pdf | 29 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3_compressed.pdf | 29 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3_compressed (1).pdf | 29 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3_compressed.pdf | 29 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3_compressed (1).pdf | 29 May 2024 |
| Layout approvalFile: plan1_11zon.pdf | 24 Apr 2023 |
| Layout approvalFile: plan2_11zon.pdf | 24 Apr 2023 |
| Copy of Layout Approval (in case of layout)File: plan1_11zon.pdf | 24 Apr 2023 |
| Copy of Layout Approval (in case of layout)File: plan2_11zon.pdf | 24 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 34-Engineer cost certificate for Rera.pdf | 24 Apr 2023 |
| Copy of the legal title reportFile: 37- Search report for Rera legal title report_11zon.pdf | 27 Feb 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: 29-new sanction letter 30-01-2023_compressed.pdf | 27 Feb 2023 |
| Proforma of Agreement for saleFile: LATEST AGREEMENT DRAFT COPY 22 02.pdf | 27 Feb 2023 |
| Details of encumbrancesFile: ENCU CERT.pdf | 19 Apr 2022 |
| Declaration about Commencement CertificateFile: DECL.pdf | 19 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: SOLD AND UNSOLD.pdf | 19 Apr 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT 02.pdf | 19 Apr 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 96 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SAI PARADISE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near DEHUGAON13,700+ in Pune
Filed coordinates, straight-line distance. 31 registered projects within 2 km.
Gathagram Sector 2
HARIT LANDMARKS LLP
ANANDI VIHAR
SANSKRUTI DEVELOPERS
GATHAGRAM SECTOR-3 PHASE-1
HARIT LANDMARKS LLP
KESHAV KUNJ
M/S SANSKRUTI DEVELOPERS AND BUILDERS
VRUNDAVAN PARK
BG ASSOCIATES
Rivereast Residency
KRUSHNA PARADISE DEVELOPERS
Builder: SHREE SAI SEVA DEVELOPERS
SHREE SAI SEVA DEVELOPERS has 1 registration on MahaRERA, including SAI PARADISE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that SAI PARADISE shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SAI PARADISE is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAI PARADISE?
The registered promoter entity is SHREE SAI SEVA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAI PARADISE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SAI PARADISE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAI PARADISE?
The professionals named in the filing: Architect: VISION ARCHITECT AR SWAPNIL PARASHAR; Engineer: ANSHUMAN BHIDE; Engineer: PANKAJ SAHEBRAO KARANDE; Chartered Accountant: M S KUMBHAR AND ASSOCIATES; Chartered Accountant: SHRIKANT THORAT; Chartered Accountant: PGMJ & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAI PARADISE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback