Home / Browse projects / Raigarh, Maharashtra / SAI GREENS

Registration lapsed No litigation declared Residential / Group Housing project

SAI GREENS

By REKHA SUBHASH JAGDALE

RG-MH-25078 · RERA P52000003773 · Last updated on MahaRERA portal: 1 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 137 months past the filed date
  • 3 complaints at MahaRERA
  • 3 extensions taken

Clear

  • No litigation declared
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
May 2015Possession promised137 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
5 of 24Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 78 documents Report an error

SAI GREENS is a Residential / Group Housing project by REKHA SUBHASH JAGDALE in Raigarh, Maharashtra, registered with MahaRERA as P52000003773 on 6 Aug 2017. Possession was promised by 31 May 2015 and is now 137 months past that date. 19 of the 24 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameSAI GREENS
  • TypeResidential / Group Housing
  • Location
    • Kudawe Road
    • Bramhan Ali
    • Palaspe
    • Panvel
    • Raigarh
    • 410221
  • Pincode410221
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000003773
  • ReraGenie IDRG-MH-25078

Builder

  • NameREKHA SUBHASH JAGDALE
  • Entity typeIndividual
  • GSTIN27AAIPJ1460B1Z6
  • Other registrations2 more →
  • No longer live3 lapsed, de-registered or revoked

Key dates

Registered
6 Aug 2017
Promised
30 Sep 2019
Revised
31 May 2015

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on6 Aug 2017
  • Promised completion31 May 2015
  • Revised completionRevised to 31 May 2015 (originally 30 Sep 2019)
  • Buildings1 building record
  • Documents filed78 files

Current status

79%19 of 24 units booked
100.0%Work done, per cost certificate

Figures as on 1 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Laxmi Vishnu ViharNA5424024

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Laxmi Vishnu Vihar: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 1 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed14

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots14
Closed/Covered14

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area753 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Mar 2026

Approvals and building plan

Sanctioning authorityNAINA CIDCO
Permissible FSI1466.97
Proposed, not sanctioned714 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAUM SAI CHS SHOP 7 to 11 sec 7 KHARGHAR
Estimated costRs 2.95 cr
Cost incurredRs 2.95 cr
Work done100.0%
BuildingWingEstimatedIncurred
Laxmi Vishnu ViharNARs 2.55 crRs 2.55 cr
-NARs 40.49 lakhRs 40.49 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNavnath L Gole
EngineerRam Marathe
Chartered AccountantAshok T Upadhye
PartnerRole in project
REKHA SUBHASH JAGDALE-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000017879Sep 2019 → Dec 2025

Reason as filed by the promoterThe work is nearing completion as per the approved Development permission Ref No. CIDCO/NAINA/PANVEL/Palaspe/BP-44/CC/2017/73 dated 03.02.2017. This permission was issued based on Interim Draft Development Plan and Draft Development Control & Promotion Rules & Regulations dated 07.11.2016. And as per that draft interim DP Rules we had been deprived off our legitimate eligible FSI of approx. 250 sq. mtr. as the area used for Staircase, Lobbies etc. was not excluded from the usable area and hence there was reduction in the usable area approved by NAINA at that time. But however subsequently the

EXT52000009672Sep 2019 → Dec 2022

Reason as filed by the promoterThe construction work is substantially suffered and delayed due to COVID 19 Lockdown, non-availability of Labor & Staff, Construction Material etc. Hence the extension is required to complete the balance work as per existing approved plan and give possession to the existing flat buyers AND also to do the proposed additional construction as per proposed revised plan after getting the approval of the concerned authorities. Further the marketing/sale of Balance flat/inventory is also to be done which is becoming difficult day by day due to COVID 19 lockdown and slow down in the real estate market

EXT52000005630Sep 2019 → Sep 2020

Reason as filed by the promoterThe work is behind the schedule due to technical issues regarding the road connectivity to the project. The connecting road to the project plot was encroached by the attached neighboring plot owners by construction of unauthorized structures, illegal extention of their compound wall etc. We had to take this matter of encroachment to CIDCO/NAINA, & Palaspe Grampanchayat. After follow-up with CIDCO/NAINA & Palaspe Grampanchayat now said encroachment is removed and the road connectivity to the project is restored. After this removal of road encroachment now work at the site is in full progress. T

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC006000000209690बिल्डर कडून फसवणूकRekha Subhash Jagdale02/03/2022
CC006000000396909Jitendra Dattaram MugurdekarRekha Jagdale07/09/2023
CC12503668Jitendra Dattaram MugurdekarREKHA SUBHASH JAGDALE15/10/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Oct 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed78

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Architect Cert Sai Greens Palaspe 31 March 2025.pdf1 May 2026
Withdrawal Update Form 1File: Form 1 Architect Cert Sai Greens Palaspe 31 March 2025.pdf1 May 2026
Withdrawal Update Form 1File: Form 1 Sai Greens 30 June 2025 compressed.pdf1 May 2026
Withdrawal Update Form 1File: Form 1 Sai Greens 30 Sept 2025 compressed.pdf1 May 2026
Withdrawal Update Form 1File: Form 1 Sai Greens 31 Dec 2025 compressed.pdf1 May 2026
Withdrawal Update Form 2File: Form 2 Sai Greens 31 March 2025 compressed.pdf1 May 2026
Withdrawal Update Form 2File: Form 2 Sai Greens 31 March 2025 compressed.pdf1 May 2026
Withdrawal Update Form 2File: Form 2 Sai Greens 30 June 2025 compressed.pdf1 May 2026
Withdrawal Update Form 2File: Form 2 Sai Greens 30 Sept 2025 compressed.pdf1 May 2026
Withdrawal Update Form 2File: Form 2 Sai Greens 31 Dec 2025 compressed.pdf1 May 2026
Withdrawal Update Form 3File: Form 3 Sai Greens 31 March 2025 compressed.pdf1 May 2026
Withdrawal Update Form 3File: Form 3 Sai Greens 31 March 2025 compressed.pdf1 May 2026
Withdrawal Update Form 3File: Form 3 Sai Greens 30 June 2025 compressed.pdf1 May 2026
Withdrawal Update Form 3File: Form 3 Sai Greens 30 June 2025 compressed.pdf1 May 2026
Withdrawal Update Form 3File: Form 3 Sai Greens 31 Dec 2025 compressed.pdf1 May 2026
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Cert 31 March 2025.pdf27 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engr Cert Sai Greens 31 March 2025 Compressed.pdf27 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arct Cert Sai Greens LVV 31 Dec 2024.pdf21 Feb 2025
Certificates of CA (Form 3)File: Form 3 Sai Greens 31 Dec 2024 Compressed.pdf21 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engr Cert Sai Greens LVV 31 Dec 2024.pdf21 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Sai Greens 31 March 2024.pdf21 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A June 24 Format Declaration Sai Greens.pdf11 Nov 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: UBI Letter RERA Accounts Opening Sai Greens.pdf11 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Archt Cert Sai Greens 31 March 24.pdf13 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engr Cert as on 31 March 24 Compressed.pdf13 Aug 2024
Certificates of CA (Form 3)File: Form 3 Sai Greens March 2024-compressed.pdf13 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Sai Greens March 2024.pdf13 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Sai Greens March 2024.pdf13 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate 31 Jan 2024.pdf3 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate 31 Jan 2024.pdf3 Mar 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory disclosure 31 Jan 2024 Sai Greens.pdf3 Mar 2024
Certificates of CA (Form 3)File: Form 3 CA Cert 31 Jan 2024 Sai Greens compressed.pdf3 Mar 2024
Declaration in FORM BFile: Form B Notorized Declaration Compresssed.pdf2 Dec 2023
Certificates of CA (Form 3)File: Form 3 Revised CA Cert 31 March 2023 Sai Greens.pdf1 Dec 2023
Certificates of CA (Form 3)File: Form 3 Revised CA Cert 14 Sept 2023 Sai Greens.pdf1 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 CA Certificate 31 March 2023.pdf1 Dec 2023
Layout approvalFile: Amendment Approved CC Drawings Compressed 1 Sept 2023.pdf30 Oct 2023
Details of encumbrances concerned to FinanceFile: Legal Declaration Sai Greens.pdf30 Oct 2023
Details of encumbrances concerned to LegalFile: Legal Declaration Sai Greens.pdf30 Oct 2023
Copy of Layout Approval (in case of layout)File: Amendment Approved CC Drawings Compressed 1 Sept 2023.pdf30 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: Amendment Permission CC dt 1st Sept 2023 Compressed.pdf30 Oct 2023
Declaration about Commencement CertificateFile: Format D Declaration Sai Greens.pdf30 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architects Certificate 31 March 2023.pdf30 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architects Certificate 14 Sept 2023.pdf30 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Cert 31 March 2023.pdf30 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Cert 14 Sept 2023.pdf30 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Sai Greens 2020.pdf30 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Sai Greens 2021.pdf30 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Sai Greens 2022.pdf30 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Sai Greens 2023.pdf30 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold Inventory List.pdf30 Oct 2023
Certificates of CA (Form 3)File: Form 3 CA Cert 14 Sept 2023 Sai Greens Compressed.pdf30 Oct 2023
Certificates of CA (Form 3)File: Form 3 CA Cert 31 March 2023 Sai Greens compressed.pdf30 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 CA Certificate FY Ended on 31 March 22.pdf5 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Sai Greens Form 5 CA Cert 2020.pdf8 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Sai Greens Form 5 CA Cert 2021.pdf8 Aug 2022
Certificates of CA (Form 3)File: LVV Form 3 Revised March 2017.pdf3 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: LVV Form 5 CA Certificate March 2018.pdf3 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: LVV Form 5 CA Certificate March 2019.pdf3 Dec 2019
Layout approvalFile: NAINA Approved Drawing 1.PDF27 Jul 2017
Building plan approvalFile: NAINA Approved Drawing 2.PDF27 Jul 2017
Building plan approvalFile: NAINA Approved Drawing 3.pdf27 Jul 2017
Building plan approvalFile: NAINA Approved Drawing 1.PDF27 Jul 2017
PAN CardFile: Rekha Jagdale PAN Card.pdf27 Jul 2017
Copy of the legal title reportFile: Title Certificate.pdf27 Jul 2017
Details of encumbrancesFile: letter of emcumbrances.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: NAINA Approved Drawing 1.PDF27 Jul 2017
Building Plan Approval (IOD)File: NAINA Approved Drawing 1.PDF27 Jul 2017
Building Plan Approval (IOD)File: NAINA Approved Drawing 2.PDF27 Jul 2017
Building Plan Approval (IOD)File: NAINA Approved Drawing 3.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Cidco CC compressed.pdf27 Jul 2017
Declaration in FORM BFile: LVV Declaration Form B.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: LVV_Architect Certificate.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: LVV_Engineer Certificate.pdf27 Jul 2017
Certificates of CA (Form 3)File: CA form3.pdf27 Jul 2017
Proforma of Allotment letterFile: LVV RERA Agreement for Sale.pdf27 Jul 2017
Proforma of Allotment letterFile: LVV RERA Allotment Letter format.pdf27 Jul 2017
OtherFile: Scan.pdf27 Jul 2017

How this compares with Raigarh

79%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAI GREENS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bramhan Ali5,900+ in Raigarh

2 kmSAI GREENSCompleted 3Lapsed / revoked 3Other 14Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: REKHA SUBHASH JAGDALE

REKHA SUBHASH JAGDALE has 3 registrations on MahaRERA, including SAI GREENS and SAI GARDENS. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that SAI GREENS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SAI GREENS is delayed beyond 31 May 2015?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAI GREENS?

The registered promoter entity is REKHA SUBHASH JAGDALE, an individual as per the filing. Its GSTIN 27AAIPJ1460B1Z6 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAI GREENS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SAI GREENS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SAI GREENS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAI GREENS?

The professionals named in the filing: Architect: Navnath L Gole; Engineer: Ram Marathe; Chartered Accountant: Ashok T Upadhye. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI GREENS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI GREENS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI GREENS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.