Home / Browse projects / Mumbai Suburban, Maharashtra / Sai Divine B And C

Registered No litigation declared Residential / Group Housing project

Sai Divine B And C

By SHREEJI DEVELOPERS

RG-MH-07292 · RERA P51800055152 · Last updated on MahaRERA portal: 6 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 4 months
  • 1 extension taken
  • Rs 60.00 crore secured on the land, in favour of Capri Global Housing Finance Limited

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 4 months from the original
4 of 22Construction stages doneacross 2 buildings; furthest along: Stilt Floor, 95%
80 of 102Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 62 documents Report an error

Sai Divine B And C is a Residential / Group Housing project by SHREEJI DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800055152 on 4 Mar 2024. Possession is promised by 31 Dec 2027. The completion date has moved by 4 months from the original filing. 22 of the 102 units on this registration are recorded sold or booked, and 4 of 22 construction stages are filed complete.

At a glance

Project

  • NameSai Divine B And C
  • TypeResidential / Group Housing
  • Location
    • SECTOR 1
    • KANDIVALI WEST
    • Kandivali
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • RERA no.P51800055152
  • ReraGenie IDRG-MH-07292

Builder

  • NameSHREEJI DEVELOPERS
  • Entity typePartnership
  • PartnersNIMESH UTTAMBHAI DESAI, BHUSHAN KHANDERAO PATIL
  • Other registrations26 more →
  • Completed11 of 27
  • No longer live4 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects7 →

Key dates

this monthRegisteredMar 2024First promiseAug 2027Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Mar 2024
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Aug 2027)
  • Buildings2 building records
  • Documents filed62 files

Current status

22%22 of 102 units booked
24.2%Work done, per cost certificate

Figures as on 6 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B WingNA161667875
C WingNA15927027

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 6 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Stilt Floor, at 95%.

B Wing28%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor95%
Slabs of Super Structure14%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C Wing28%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor95%
Slabs of Super Structure14%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed136

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots136
Closed/Covered136
BuildingClosed/CoveredTotal
B Wing9393
C Wing4343

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,304 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofCapri Global Housing Finance Limited
Secured amountRs 60.00 crore
CERSAI search filedYes
Declared on4 May 2026
LandownerVillageDistrict
Kalakunj CHSLKandivaliMumbai Suburban

Approvals and building plan

Sanctioning authorityMAHADA
Permissible FSI6244.96
Proposed, not sanctioned6,245 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 3/4, ARBOUR 180/A, MARVE ROAD, ORLEM, MALAD WEST, MUMBAI 400064
Estimated costRs 39.81 cr
Cost incurredRs 9.63 cr
Work done24.2%
BuildingWingEstimatedIncurred
B WingNARs 15.92 crRs 4.82 cr
C WingNARs 15.92 crRs 4.82 cr
-NARs 7.96 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCharudatta Samant
ArchitectM S TRUE SCALE STUDIO
EngineerKRISHNA PANDEY
Chartered AccountantNEHALI DHAVAL DOSHI
Chartered AccountantJIMIT BIPIN SHAH
PartnerRole in project
SHREEJI DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA22042620691Aug 2027 → Dec 2027

Reason as filed by the promoterDelays in v. Further Second Approval Pursuant to the above, our matter was relisted before the MoEF Authority for a second approval on 24th January 2025. However, due to continued restrictions and procedural uncertainties, the Authority has since ceased taking up such matters, and no further hearings have occurred to date. This has left our project in a state of regulatory limbo, unable to proceed as per the original sanctioned plans. Till date no hearing has taken place vi. Amendment of Plans to Reduce Constructable Area below 20,000 sq. mtrs.: In view of these persistent difficulties, we hav

Litigation declared1

CaseCourtStatus
53 OF 2023/2023CO OPERATIVE COURT MUMBAIARGUMENTS

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Dec 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Apr 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Dec 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed62

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Signed Sai Divine B C Wing.pdf6 Aug 2026
Withdrawal Update Form 2File: Signed Engineer Certificate Shreeji Divine B C KP Jun 26.pdf6 Aug 2026
Withdrawal Update Form 3File: Signed CA Certificate SAI DIVINE B C june26.pdf6 Aug 2026
Form 2A (FY 2025-2026)File: Divine B C Form 2A FY 25 26.pdf15 Jul 2026
Withdrawal Update Form 1File: Architect Sai.pdf21 Apr 2026
Withdrawal Update Form 1File: Architect Sai.pdf21 Apr 2026
Withdrawal Update Form 1File: architecture.pdf21 Apr 2026
Withdrawal Update Form 2File: Engineer.pdf21 Apr 2026
Withdrawal Update Form 2File: Engineer.pdf21 Apr 2026
Withdrawal Update Form 2File: engineer.pdf21 Apr 2026
Withdrawal Update Form 3File: SIGNED CA.pdf21 Apr 2026
Withdrawal Update Form 3File: SIGNED CA.pdf21 Apr 2026
Withdrawal Update Form 3File: CA Certificate.pdf21 Apr 2026
Form 2A (FY 2024-2025)File: form 2A 24-25.pdf21 Apr 2026
Layout approvalFile: Plans Highlighted (1).pdf6 Apr 2026
Layout approvalFile: Plans Highlighted (1).pdf13 Mar 2026
Layout approvalFile: Plans in gray (1).pdf9 Feb 2026
Layout approvalFile: Amended IOA plan sai divine grayscale.pdf26 Dec 2025
Form 5 (FY 2024-2025)File: FORM 5 24-25.pdf18 Dec 2025
Withdrawal Update Form 1File: form 1.pdf17 Dec 2025
Withdrawal Update Form 2File: form 2.pdf17 Dec 2025
Withdrawal Update Form 3File: form 3.pdf17 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf15 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sai divine B C-Engineer.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf14 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 23-24.pdf11 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf23 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 (3).pdf20 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A 23-24.pdf6 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf24 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf24 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf10 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf15 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf15 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf11 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf25 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf24 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf24 Apr 2024
Declaration about Commencement CertificateFile: CC decleration Sai Divine B and C wing.pdf17 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A DOI.pdf3 Feb 2024
Details of encumbrances concerned to FinanceFile: Encumbrance self declaration B and C.pdf24 Jan 2024
Details of encumbrances concerned to LegalFile: Encumbrance self declaration B and C.pdf24 Jan 2024
Details of encumbrances concerned to FinanceFile: No encumberance.pdf20 Jan 2024
Details of encumbrances concerned to LegalFile: No encumberance.pdf20 Jan 2024
Details of encumbrances concerned to FinanceFile: No Encumbrance Self-Declaration sai Divine B C Wing.pdf27 Dec 2023
Details of encumbrances concerned to LegalFile: No Encumbrance Self-Declaration sai Divine B C Wing.pdf27 Dec 2023
CERSAI detailsFile: Cersai Declaration Sai Divine B C Wing.pdf27 Dec 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Details Letter Rara Sai Divine B C Wing 20-Dec-2023 11-35-19.pdf26 Dec 2023
PAN CardFile: 1 PAN Card.pdf21 Dec 2023
Deviation Report with respect to Allotment letterFile: Deviation report on allotment Sai Divine B and C Wing.pdf14 Dec 2023
Deviation Report with respect to model copy of AgreementFile: Deviation report on Agreement for sale Sai Divine B and C Wing.pdf14 Dec 2023
Layout approvalFile: IOA plan.pdf13 Dec 2023
Building plan approvalFile: IOA.pdf13 Dec 2023
Copy of the legal title reportFile: Title Report Kala Kunj.pdf13 Dec 2023
Copy of Layout Approval (in case of layout)File: IOA plan.pdf13 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: IOA.pdf13 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: Kalakunj Plinth CC.pdf13 Dec 2023
Declaration in FORM BFile: Form B promoter.pdf13 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed CA Certificate Sai Divine.pdf13 Dec 2023
Proforma of Agreement for saleFile: Draft Agreement for Sale - Kalakunj revised.pdf13 Dec 2023
Proforma of Allotment letterFile: Draft Allotment Letter - Sai Divine.pdf13 Dec 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SHREEJI PLAZA A WINGCTS 1 PT 2 PT OF VILLAGE VALNAI TALUKA BORIVALI ORLEM MALAD WEST170CompletedJun 2023Jun 2023

How this compares with Mumbai Suburban

22%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 4 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sai Divine B And C on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KANDIVALI WEST6,700+ in Mumbai Suburban

Builder: SHREEJI DEVELOPERS

SHREEJI DEVELOPERS has 27 registrations on MahaRERA, including SAHAJANAND INTEGRITY and SHREEJI DREAMS. Its filings disclose 7 earlier MahaRERA projects: declares 6 of 7 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Sai Divine B And C is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sai Divine B And C?

The registered promoter entity is SHREEJI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sai Divine B And C?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sai Divine B And C?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sai Divine B And C?

The professionals named in the filing: Architect: Charudatta Samant; Architect: M S TRUE SCALE STUDIO; Engineer: KRISHNA PANDEY; Chartered Accountant: NEHALI DHAVAL DOSHI; Chartered Accountant: JIMIT BIPIN SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sai Divine B And C?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sai Divine B And C. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sai Divine B And C to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.