Red flags

  • Possession 2 months past the filed date
  • Completion date moved by 20 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Aug 2026Possession promised2 months past this date
8 of 11Construction stages donefurthest along: Installation of Lifts, 98%
13 of 18Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 88 documents Report an error

SAI DEEP RESIDENCY is a Others project by PAVAN MAHATMA DEVALKAR in Raigarh, Maharashtra, registered with MahaRERA as P52000034601 on 11 Apr 2022. Possession was promised by 31 Aug 2026 and is now 2 months past that date. The completion date has moved by 20 months from the original filing. 5 of the 18 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameSAI DEEP RESIDENCY
  • TypeOthers
  • Location
    • SECTOR - 5
    • PUSHPAK NAGAR
    • NAVI MUMBAI
    • Navi Mumbai Panvel Rigardh (CT)
    • Panvel
    • Raigarh
    • 410221
  • Pincode410221
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000034601
  • ReraGenie IDRG-MH-39912

Builder

  • NamePAVAN MAHATMA DEVALKAR
  • Entity typeIndividual
  • GSTIN27AHBPD9130C2ZV
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Other registrations4 more →
  • Past their filed date1
  • Declared earlier projects4 →

Key dates

2 months past promisethis monthRegisteredApr 2022First promiseDec 2024Revised toAug 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Apr 2022
  • Promised completion31 Aug 2026
  • Revised completionRevised to 31 Aug 2026 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed88 files

Current status

28%5 of 18 units booked
100.0%Work done, per cost certificate

Figures as on 17 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAI DEEP RESIDENCYNA5515318

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 98%.

SAI DEEP RESIDENCY: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%

Progress on shared amenities15

As on 17 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed6

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots6
Open Space6

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area300 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on2 Jun 2026
LandownerVillageDistrict
BHUSHAN KOLIUlaweRaigarh

Approvals and building plan

Sanctioning authoritycidco
Permissible FSI749.9
Proposed, not sanctioned750 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKHARGHAR BRANCH
Estimated costRs 1.54 cr
Cost incurredRs 1.54 cr
Work done100.0%
BuildingWingEstimatedIncurred
SAI DEEP RESIDENCYNARs 1.44 crRs 1.44 cr
-NARs 9.60 lakhRs 9.60 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAJESH RC
EngineerRAM V MARATHE
Chartered AccountantKEYUR BHAYANI
Chartered AccountantSHRADDHA KALPESH GURAV
PartnerRole in project
ANMOL BUILDERS AND DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA19112518373Dec 2024 → Aug 2026

Reason as filed by the promoterearlier due to some personal reason it was delayed but now the project is almost completed and we are applied for oc hence till the oc will received we are applied for extension so i request you to please approved the extension

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Jan 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Jan 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Jan 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed88

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect_certificate_85_dec_25.pdf17 Jun 2026
Withdrawal Update Form 1File: Architect_certificate_85.pdf17 Jun 2026
Withdrawal Update Form 2File: 85_engineering_certificate_dec_25.pdf17 Jun 2026
Withdrawal Update Form 2File: sai_deep_85_engineering_certificate.pdf17 Jun 2026
Withdrawal Update Form 3File: form 3 dec25.pdf17 Jun 2026
Withdrawal Update Form 3File: FORM 3 MARCH 26.pdf17 Jun 2026
Form 1File: Architect_certificate_85_march_25.pdf13 Jun 2026
Form 2File: Engineering_certificate_85_march_25.pdf13 Jun 2026
Form 3File: FORM 3 CA CERTIFICATE.pdf13 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure_of_sold_inventory_March_25.pdf13 Jun 2026
Withdrawal Update Form 1File: Architect_certificate_85_oct_25.pdf13 Jun 2026
Withdrawal Update Form 1File: Architect_certificate_85_sept_25.pdf13 Jun 2026
Withdrawal Update Form 2File: 85_engineering_certificate_sept_25.pdf13 Jun 2026
Withdrawal Update Form 2File: 85_engineering_certificate_sept_25.pdf13 Jun 2026
Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE.pdf13 Jun 2026
Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE.pdf13 Jun 2026
Form 1File: AR_MARCH_24.pdf11 Apr 2026
Form 2File: E_C_March_24.pdf11 Apr 2026
Form 3File: MAR 2024 FORM 3.pdf11 Apr 2026
Disclosure of Sold and Booked InventoryFile: 85_DC_MARCH_24.pdf11 Apr 2026
Form 1File: AR_DEC_23.pdf11 Apr 2026
Form 2File: E_C_Dec_23.pdf11 Apr 2026
Form 3File: DEC 2023 FORM 3.pdf11 Apr 2026
Disclosure of Sold and Booked InventoryFile: 85_DC_DEC_23.pdf11 Apr 2026
Form 1File: AR_SEPT_23.pdf11 Apr 2026
Form 2File: E_C_SEPT_23.pdf11 Apr 2026
Form 3File: SEPT 2023 FORM 3.pdf11 Apr 2026
Disclosure of Sold and Booked InventoryFile: 85_DC_SEPT_23.pdf11 Apr 2026
Form 1File: AR_JUNE_23.pdf11 Apr 2026
Form 2File: E_C_June_23.pdf11 Apr 2026
Form 3File: JUNE 2023 FORM 3.pdf11 Apr 2026
Disclosure of Sold and Booked InventoryFile: 85_DC_JUNE_23.pdf11 Apr 2026
Form 1File: AR_DEC_22.pdf11 Apr 2026
Form 2File: E_C_DEC_22.pdf11 Apr 2026
Form 3File: DEC 2022 from 3.pdf11 Apr 2026
Disclosure of Sold and Booked InventoryFile: 85_DC_DEC_22.pdf11 Apr 2026
Form 1File: AR_JUNE_22.pdf11 Apr 2026
Form 2File: E_C_June_22.pdf11 Apr 2026
Form 3File: JUNE 2022 form 3.pdf11 Apr 2026
Disclosure of Sold and Booked InventoryFile: 85_DC_JUNE_22.pdf11 Apr 2026
Form 1File: AR_SEPT_22.pdf11 Apr 2026
Form 2File: E_C_SEPT_22.pdf11 Apr 2026
Form 3File: SEPT 2022.pdf11 Apr 2026
Disclosure of Sold and Booked InventoryFile: 85_DC_SEPT_22.pdf11 Apr 2026
Form 1File: AR_MARCH_23.pdf11 Apr 2026
Form 2File: E_C_March_23.pdf11 Apr 2026
Form 3File: MAR 2023.pdf11 Apr 2026
Disclosure of Sold and Booked InventoryFile: 85_DC_MARCH_23.pdf11 Apr 2026
Form 1File: Architect_certificate_85_dec_24.pdf24 Dec 2025
Form 2File: Engineering_certificate_84_dec_24.pdf24 Dec 2025
Form 3File: FORM 3 CA CERTIFICATE.pdf24 Dec 2025
Disclosure of Sold and Booked InventoryFile: Disclosure_of_sold_inventory_December_24.pdf24 Dec 2025
Form 1File: Form_-_1__4th_issue____30-06-24___1_.pdf14 Oct 2025
Form 2File: ENGG CERTIFICATE 1 JUNE.pdf14 Oct 2025
Form 3File: july 2024.pdf14 Oct 2025
Disclosure of Sold and Booked InventoryFile: july 2024.pdf14 Oct 2025
Form 1File: architec cetificate.pdf14 Oct 2025
Form 2File: Engeering certificate.pdf14 Oct 2025
Form 3File: oct 2024.pdf14 Oct 2025
Disclosure of Sold and Booked InventoryFile: oct 2024.pdf14 Oct 2025
Form 5 (FY 2023-2024)File: FORM 5.pdf14 Oct 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf3 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form_-_1__4th_issue____30-06-24___1_.pdf17 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architec cetificate.pdf17 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: july 2024.pdf17 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: oct 2024.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE 1 JUNE.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engeering certificate.pdf17 Oct 2024
Declaration in FORM BFile: FORM B NEW_compressed.pdf1 Apr 2022
CERSAI detailsFile: CERSAI_Search_Report_200232512408_For_Asset_Based_Search_15_03_2022_17_35_11_711.pdf16 Mar 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf16 Mar 2022
Layout approvalFile: APPROVED PLAN_compressed (3).pdf15 Jan 2022
Copy of Layout Approval (in case of layout)File: APPROVED PLAN_compressed (3).pdf15 Jan 2022
Building plan approvalFile: COMPRESSED APPROVAL PLAN.pdf10 Jan 2022
PAN CardFile: PAVAN PANCARD.pdf10 Jan 2022
Building Plan Approval / NA Order for plotted developmentFile: COMPRESSED APPROVAL PLAN.pdf10 Jan 2022
Layout approvalFile: Agreement Plans.pdf8 Jan 2022
Copy of the legal title reportFile: COMRESS LEGAL TITLE REPORT NEW.pdf8 Jan 2022
Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE.pdf8 Jan 2022
Copy of Layout Approval (in case of layout)File: Agreement Plans.pdf8 Jan 2022

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date2 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
DHOONDIRAJ HOTELS PVT LTDP52000049628PANVEL, Raigarh50Feb 2023OngoingDec 2026Not due yet
DATTAKRUPA COMPLEXP52000048168PANVEL, Raigarh44Dec 2022OngoingDec 2026Not due yet
SHREE APARTMENTP52000029819AT PUSHPAK ULWE, Raigarh25Jul 2021OngoingNov 2023Not delivered

How this compares with Raigarh

28%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 20 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAI DEEP RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUSHPAK NAGAR, NAVI MUMBAI5,900+ in Raigarh

2 kmSAI DEEP RESIDENCYCompleted 11Lapsed / revoked 12Other 109Dot size: filed unitsN

Filed coordinates, straight-line distance. 132 registered projects within 2 km.

Builder: PAVAN MAHATMA DEVALKAR

PAVAN MAHATMA DEVALKAR has 5 registrations on MahaRERA, including SHREE APARTMENT and SAI DEEP RESIDENCY. Its filings disclose 4 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if SAI DEEP RESIDENCY is delayed beyond 31 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAI DEEP RESIDENCY?

The registered promoter entity is PAVAN MAHATMA DEVALKAR, an individual as per the filing. Its GSTIN 27AHBPD9130C2ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAI DEEP RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAI DEEP RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAI DEEP RESIDENCY?

The professionals named in the filing: Architect: RAJESH RC; Engineer: RAM V MARATHE; Chartered Accountant: KEYUR BHAYANI; Chartered Accountant: SHRADDHA KALPESH GURAV. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI DEEP RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI DEEP RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI DEEP RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.