SAI AURA

By DHARMENDRA TULSHIBHAI MANANI

RG-MH-94133 · RERA P52000047859 · Last updated on MahaRERA portal: 22 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
32 of 44Construction stages doneacross 4 buildings; furthest along: Sanitary Fittings within the flats /..., 50%
45 of 110Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 82 documents Report an error

SAI AURA is a Others project by DHARMENDRA TULSHIBHAI MANANI in Raigarh, Maharashtra, registered with MahaRERA as P52000047859 on 28 Nov 2022. Possession is promised by 31 Dec 2027. 65 of the 110 units on this registration are recorded sold or booked, and 32 of 44 construction stages are filed complete.

At a glance

Project

  • NameSAI AURA
  • TypeOthers
  • Location
    • Plot No 16/1
    • Near Old Thane Road
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000047859
  • ReraGenie IDRG-MH-94133

Builder

  • NameDHARMENDRA TULSHIBHAI MANANI
  • Entity typeIndividual
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredNov 2022PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Nov 2022
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings4 building records
  • Documents filed82 files

Current status

59%65 of 110 units booked
74.2%Work done, per cost certificate

Figures as on 22 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA7722628
B WINGNA7724024
C WINGNA7728028
D WINGNA7730030

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 22 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

32 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 50%.

A WING82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
B WING82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
C WING79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
D WING82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 22 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed97

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots97
Closed/Covered85
Open Space12
BuildingClosed/CoveredOpen SpaceTotal
A WING22325
B WING21324
C WING21324
D WING21324

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,126 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Oct 2025

Approvals and building plan

Sanctioning authorityPANVEL MUNICIPAL CORPORATION
Permissible FSI5428.42
Proposed, not sanctioned5,428 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGR FLR,SHOP NO 4,5 & 6,NEEL ASHIMA,PLOT NO.14,SECTOR 2A,URAN PANVEL ROAD,KARANJADE,PANVEL 410206
Estimated costRs 28.80 cr
Cost incurredRs 21.36 cr
Work done74.17%
BuildingWingEstimatedIncurred
A WINGNARs 6.78 crRs 5.34 cr
B WINGNARs 6.78 crRs 5.34 cr
C WINGNARs 6.78 crRs 5.34 cr
D WINGNARs 6.78 crRs 5.34 cr
-NARs 1.69 cr-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNAGARKAR & ASSOCIATES
EngineerAGHARKAR CONSULTING ENGINEERS PVT LTD
Chartered AccountantKANKOTIYA & CO

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Oct 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Oct 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Oct 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed82

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 82 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 31032026 sai aura.pdf22 Jun 2026
Withdrawal Update Form 1File: Form 1 31032026 sai aura.pdf22 Jun 2026
Withdrawal Update Form 2File: Form 2 sai aura 05042026.pdf22 Jun 2026
Withdrawal Update Form 2File: Form 2 sai aura 05042026.pdf22 Jun 2026
Withdrawal Update Form 3File: Sai Aura Form 3 31122025.pdf22 Jun 2026
Withdrawal Update Form 3File: Sai Aura Form 3 31122025.pdf22 Jun 2026
Withdrawal Update Form 1File: Form 1 112026.pdf20 Jan 2026
Withdrawal Update Form 2File: form 2 saiaura 05012026.pdf20 Jan 2026
Withdrawal Update Form 3File: Sai Aura Form 3 31122025.pdf20 Jan 2026
Withdrawal Update Form 1File: Form 1 30092025.pdf11 Nov 2025
Withdrawal Update Form 1File: Form 1 30-06-2025 (1).pdf11 Nov 2025
Withdrawal Update Form 1File: Form 1 30092025.pdf11 Nov 2025
Withdrawal Update Form 2File: Form 2 30092025.pdf11 Nov 2025
Withdrawal Update Form 2File: Form230-06-2025.pdf11 Nov 2025
Withdrawal Update Form 2File: Form 2 30092025.pdf11 Nov 2025
Withdrawal Update Form 3File: Sai Aura 30092025.pdf11 Nov 2025
Withdrawal Update Form 3File: Form3 30062025(1).pdf11 Nov 2025
Withdrawal Update Form 3File: Sai Aura 30092025.pdf11 Nov 2025
Form 1File: Form 1 30062024.pdf10 Oct 2025
Form 2File: Form 2 30062024.pdf10 Oct 2025
Form 3File: Sai Aura Form 3 30062024.pdf10 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked - SAI AURA - 30062024.pdf10 Oct 2025
Form 1File: Form1.pdf10 Oct 2025
Form 2File: Form2.pdf10 Oct 2025
Form 3File: Form 3.pdf10 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked.pdf10 Oct 2025
Form 1File: Form 1 31032024.pdf10 Oct 2025
Form 2File: Form 2 31032024.pdf10 Oct 2025
Form 3File: Form 3 - 31032024.pdf10 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked 31032024.pdf10 Oct 2025
Form 1File: Form 1 31032025.pdf10 Oct 2025
Form 2File: Form 2 31032025.pdf10 Oct 2025
Form 3File: Form 3 31032025.pdf10 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold 31032025.pdf10 Oct 2025
Form 1File: Sai Aura Form 1 31122024.pdf10 Oct 2025
Form 2File: Sai Aura Form 2 31122024.pdf10 Oct 2025
Form 3File: Form 3 3112024.pdf10 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold And booked inventory.pdf10 Oct 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31032025.pdf18 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31032025.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31032025.pdf18 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold 31032025.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sai Aura Form 1 31122024.pdf10 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 3112024.pdf10 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sai Aura Form 2 31122024.pdf10 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold And booked inventory.pdf10 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31032024.pdf28 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31032024.pdf28 May 2024
Disclosure of sold/ booked inventoryFile: Sold Booked 31032024.pdf28 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - 31032024.pdf28 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1.pdf8 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2.pdf8 Feb 2024
Disclosure of sold/ booked inventoryFile: Sold Booked.pdf8 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf8 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 21102022Bank Declaration.pdf11 Nov 2022
Deviation Report with respect to model copy of AgreementFile: 21102022 DRAFT AGREEMENY.pdf21 Oct 2022
Deviation Report with respect to model copy of AgreementFile: 21102022 Deviation AFS.pdf21 Oct 2022
Proforma of Allotment letterFile: Allotment Letter.pdf11 Oct 2022
Proforma of Agreement for saleFile: Allotment Letter.pdf11 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf7 Oct 2022
Details of encumbrances concerned to FinanceFile: Financial Encumbrances.pdf6 Oct 2022
Details of encumbrances concerned to LegalFile: Legal Encumbrances.pdf6 Oct 2022
Declaration about Commencement CertificateFile: Declaration CC.pdf6 Oct 2022
Declaration in FORM BFile: Form B.pdf6 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf6 Oct 2022
CERSAI detailsFile: CRESAI.pdf6 Oct 2022
Deviation Report with respect to Allotment letterFile: Deviation Allotment.pdf6 Oct 2022
Layout approvalFile: Layout 1.pdf5 Oct 2022
Layout approvalFile: Layout 2.pdf5 Oct 2022
Layout approvalFile: Layout 3.pdf5 Oct 2022
Layout approvalFile: Layout 4.pdf5 Oct 2022
Layout approvalFile: Layout 5.pdf5 Oct 2022
Building plan approvalFile: CC FOR RERA.pdf5 Oct 2022
PAN CardFile: PAN CARD.pdf5 Oct 2022
Copy of the legal title reportFile: Title Report RERA.pdf5 Oct 2022
Copy of Layout Approval (in case of layout)File: Layout 1.pdf5 Oct 2022
Copy of Layout Approval (in case of layout)File: Layout 2.pdf5 Oct 2022
Copy of Layout Approval (in case of layout)File: Layout 3.pdf5 Oct 2022
Copy of Layout Approval (in case of layout)File: Layout 4.pdf5 Oct 2022
Copy of Layout Approval (in case of layout)File: Layout 5.pdf5 Oct 2022

How this compares with Raigarh

59%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAI AURA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near Old Thane Road5,900+ in Raigarh

2 kmSAI AURACompleted 172Lapsed / revoked 58Other 151Dot size: filed unitsN

Filed coordinates, straight-line distance. 381 registered projects within 2 km.

Builder: DHARMENDRA TULSHIBHAI MANANI

DHARMENDRA TULSHIBHAI MANANI has 3 registrations on MahaRERA, including PRIYA RESIDENCY and SAI KIRAN. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if SAI AURA is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAI AURA?

The registered promoter entity is DHARMENDRA TULSHIBHAI MANANI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAI AURA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAI AURA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAI AURA?

The professionals named in the filing: Architect: NAGARKAR & ASSOCIATES; Engineer: AGHARKAR CONSULTING ENGINEERS PVT LTD; Chartered Accountant: KANKOTIYA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI AURA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI AURA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI AURA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.