Home / Browse projects / Nagpur, Maharashtra / Sahara City Homes Phase 1 Nagpur
Sahara City Homes Phase 1 Nagpur
RG-MH-07706 · RERA P50500013486 · Last updated on MahaRERA portal: 27 Sep 2017
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 29 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Sahara City Homes Phase 1 Nagpur is a Residential / Group Housing project by SAHARA PRIME CITY LTD in Nagpur, Maharashtra, registered with MahaRERA as P50500013486 on 7 Oct 2017. Possession is promised by 30 Oct 2026. 29 complaints are on record with the regulator.
At a glance
Project
- NameSahara City Homes Phase 1 Nagpur
- TypeResidential / Group Housing
- Location
- Gawasi Manapur
- Nagpur (Rural)
- Nagpur
- 441108
- Pincode441108
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500013486
- ReraGenie IDRG-MH-07706
Builder
- NameSAHARA PRIME CITY LTD
- Entity typeCompany
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on7 Oct 2017
- Promised completion30 Oct 2026
- Revised completionNone
- Buildings176 building records
- Documents filed27 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Block A1 | NA | 11 | 0 | 0 | 0 | 0 |
| Block A2 | NA | 11 | 0 | 0 | 0 | 0 |
| Block A3 | NA | 11 | 0 | 0 | 0 | 0 |
| Block B1 | NA | 11 | 0 | 0 | 0 | 0 |
| Block B2 | NA | 11 | 0 | 0 | 0 | 0 |
| Block B3 | NA | 11 | 0 | 0 | 0 | 0 |
| Block B4 | NA | 11 | 0 | 0 | 0 | 0 |
| Block B5 | NA | 11 | 0 | 0 | 0 | 0 |
| Block B6 | NA | 11 | 0 | 0 | 0 | 0 |
| Block B6A | NA | 11 | 0 | 0 | 0 | 0 |
| Block B7 | NA | 11 | 0 | 0 | 0 | 0 |
| Block B8 | NA | 11 | 0 | 0 | 0 | 0 |
| Block B9 | NA | 11 | 0 | 0 | 0 | 0 |
| Block C1 | NA | 11 | 0 | 0 | 0 | 0 |
| Block C2 | NA | 11 | 0 | 0 | 0 | 0 |
| Block C3 | NA | 11 | 0 | 0 | 0 | 0 |
| Block C4 | NA | 11 | 0 | 0 | 0 | 0 |
| Block C5 | NA | 11 | 0 | 0 | 0 | 0 |
| Blocks C6 | NA | 11 | 0 | 0 | 0 | 0 |
| Block C7 | NA | 11 | 0 | 0 | 0 | 0 |
| Block C8 | NA | 11 | 0 | 0 | 0 | 0 |
| Block C9 | NA | 11 | 0 | 0 | 0 | 0 |
| Block C12A | NA | 11 | 0 | 0 | 0 | 0 |
| Block C14 | NA | 11 | 0 | 0 | 0 | 0 |
| Block D11 | NA | 7 | 0 | 0 | 0 | 0 |
| Block D12 | NA | 7 | 0 | 0 | 0 | 0 |
| Block D12A | NA | 7 | 0 | 0 | 0 | 0 |
| Block B3A | NA | 11 | 0 | 0 | 0 | 0 |
| Block C6A | NA | 11 | 0 | 0 | 0 | 0 |
| R289 | NA | 2 | 0 | 0 | 0 | 0 |
| R290 | NA | 2 | 0 | 0 | 0 | 0 |
| R291 | NA | 2 | 0 | 0 | 0 | 0 |
| R292 | NA | 2 | 0 | 0 | 0 | 0 |
| R293 | NA | 2 | 0 | 0 | 0 | 0 |
| R294 | NA | 2 | 0 | 0 | 0 | 0 |
| R295 | NA | 2 | 0 | 0 | 0 | 0 |
| R296 | NA | 2 | 0 | 0 | 0 | 0 |
| R297 | NA | 2 | 0 | 0 | 0 | 0 |
| R298 | NA | 2 | 0 | 0 | 0 | 0 |
| R299 | NA | 2 | 0 | 0 | 0 | 0 |
| R300 | NA | 2 | 0 | 0 | 0 | 0 |
| R301 | NA | 2 | 0 | 0 | 0 | 0 |
| R302 | NA | 2 | 0 | 0 | 0 | 0 |
| R303 | NA | 2 | 0 | 0 | 0 | 0 |
| R304 | NA | 2 | 0 | 0 | 0 | 0 |
| R305 | NA | 2 | 0 | 0 | 0 | 0 |
| R306 | NA | 2 | 0 | 0 | 0 | 0 |
| R307 | NA | 2 | 0 | 0 | 0 | 0 |
| R308 | NA | 2 | 0 | 0 | 0 | 0 |
| R309 | NA | 2 | 0 | 0 | 0 | 0 |
| R310 | NA | 2 | 0 | 0 | 0 | 0 |
| R311 | NA | 2 | 0 | 0 | 0 | 0 |
| R312 | NA | 2 | 0 | 0 | 0 | 0 |
| R313 | NA | 2 | 0 | 0 | 0 | 0 |
| R314 | NA | 2 | 0 | 0 | 0 | 0 |
| R315 | NA | 2 | 0 | 0 | 0 | 0 |
| R316 | NA | 2 | 0 | 0 | 0 | 0 |
| R317 | NA | 2 | 0 | 0 | 0 | 0 |
| R318 | NA | 2 | 0 | 0 | 0 | 0 |
| R319 | NA | 2 | 0 | 0 | 0 | 0 |
| R320 | NA | 2 | 0 | 0 | 0 | 0 |
| R321 | NA | 2 | 0 | 0 | 0 | 0 |
| R322 | NA | 2 | 0 | 0 | 0 | 0 |
| R323 | NA | 2 | 0 | 0 | 0 | 0 |
| R324 | NA | 2 | 0 | 0 | 0 | 0 |
| R325 | NA | 2 | 0 | 0 | 0 | 0 |
| R326 | NA | 2 | 0 | 0 | 0 | 0 |
| R327 | NA | 2 | 0 | 0 | 0 | 0 |
| R328 | NA | 2 | 0 | 0 | 0 | 0 |
| R329 | NA | 2 | 0 | 0 | 0 | 0 |
| R330 | NA | 2 | 0 | 0 | 0 | 0 |
| R331 | NA | 2 | 0 | 0 | 0 | 0 |
| R332 | NA | 2 | 0 | 0 | 0 | 0 |
| R333 | NA | 2 | 0 | 0 | 0 | 0 |
| R334 | NA | 2 | 0 | 0 | 0 | 0 |
| R335 | NA | 2 | 0 | 0 | 0 | 0 |
| R336 | NA | 2 | 0 | 0 | 0 | 0 |
| R337 | NA | 2 | 0 | 0 | 0 | 0 |
| R338 | NA | 2 | 0 | 0 | 0 | 0 |
| R339 | NA | 2 | 0 | 0 | 0 | 0 |
| R340 | NA | 2 | 0 | 0 | 0 | 0 |
| R341 | NA | 2 | 0 | 0 | 0 | 0 |
| R342 | NA | 2 | 0 | 0 | 0 | 0 |
| R343 | NA | 2 | 0 | 0 | 0 | 0 |
| R344 | NA | 2 | 0 | 0 | 0 | 0 |
| R345 | NA | 2 | 0 | 0 | 0 | 0 |
| R346 | NA | 2 | 0 | 0 | 0 | 0 |
| R347 | NA | 2 | 0 | 0 | 0 | 0 |
| R348 | NA | 2 | 0 | 0 | 0 | 0 |
| R349 | NA | 2 | 0 | 0 | 0 | 0 |
| R350 | NA | 2 | 0 | 0 | 0 | 0 |
| R351 | NA | 2 | 0 | 0 | 0 | 0 |
| R352 | NA | 2 | 0 | 0 | 0 | 0 |
| R353 | NA | 2 | 0 | 0 | 0 | 0 |
| R354 | NA | 2 | 0 | 0 | 0 | 0 |
| R453 | NA | 2 | 0 | 0 | 0 | 0 |
| R454 | NA | 2 | 0 | 0 | 0 | 0 |
| R455 | NA | 2 | 0 | 0 | 0 | 0 |
| R456 | NA | 2 | 0 | 0 | 0 | 0 |
| R457 | NA | 2 | 0 | 0 | 0 | 0 |
| R458 | NA | 2 | 0 | 0 | 0 | 0 |
| R459 | NA | 2 | 0 | 0 | 0 | 0 |
| R460 | NA | 2 | 0 | 0 | 0 | 0 |
| R461 | NA | 2 | 0 | 0 | 0 | 0 |
| S397 | NA | 2 | 0 | 0 | 0 | 0 |
| S398 | NA | 2 | 0 | 0 | 0 | 0 |
| S399 | NA | 2 | 0 | 0 | 0 | 0 |
| S400 | NA | 2 | 0 | 0 | 0 | 0 |
| S401 | NA | 2 | 0 | 0 | 0 | 0 |
| S402 | NA | 2 | 0 | 0 | 0 | 0 |
| S403 | NA | 2 | 0 | 0 | 0 | 0 |
| S404 | NA | 2 | 0 | 0 | 0 | 0 |
| S405 | NA | 2 | 0 | 0 | 0 | 0 |
| S406 | NA | 2 | 0 | 0 | 0 | 0 |
| S407 | NA | 2 | 0 | 0 | 0 | 0 |
| S408 | NA | 2 | 0 | 0 | 0 | 0 |
| S409 | NA | 2 | 0 | 0 | 0 | 0 |
| S410 | NA | 2 | 0 | 0 | 0 | 0 |
| S411 | NA | 2 | 0 | 0 | 0 | 0 |
| S412 | NA | 2 | 0 | 0 | 0 | 0 |
| S413 | NA | 2 | 0 | 0 | 0 | 0 |
| S414 | NA | 2 | 0 | 0 | 0 | 0 |
| S415 | NA | 2 | 0 | 0 | 0 | 0 |
| S416 | NA | 2 | 0 | 0 | 0 | 0 |
| S417 | NA | 2 | 0 | 0 | 0 | 0 |
| S418 | NA | 2 | 0 | 0 | 0 | 0 |
| S419 | NA | 2 | 0 | 0 | 0 | 0 |
| S420 | NA | 2 | 0 | 0 | 0 | 0 |
| S421 | NA | 2 | 0 | 0 | 0 | 0 |
| S422 | NA | 2 | 0 | 0 | 0 | 0 |
| S423 | NA | 2 | 0 | 0 | 0 | 0 |
| S424 | NA | 2 | 0 | 0 | 0 | 0 |
| S425 | NA | 2 | 0 | 0 | 0 | 0 |
| S426 | NA | 2 | 0 | 0 | 0 | 0 |
| S427 | NA | 2 | 0 | 0 | 0 | 0 |
| S428 | NA | 2 | 0 | 0 | 0 | 0 |
| S429 | NA | 2 | 0 | 0 | 0 | 0 |
| S430 | NA | 2 | 0 | 0 | 0 | 0 |
| S431 | NA | 2 | 0 | 0 | 0 | 0 |
| S446 | NA | 2 | 0 | 0 | 0 | 0 |
| S447 | NA | 2 | 0 | 0 | 0 | 0 |
| S448 | NA | 2 | 0 | 0 | 0 | 0 |
| S449 | NA | 2 | 0 | 0 | 0 | 0 |
| S450 | NA | 2 | 0 | 0 | 0 | 0 |
| S451 | NA | 2 | 0 | 0 | 0 | 0 |
| S452 | NA | 2 | 0 | 0 | 0 | 0 |
| V355/356 | NA | 2 | 0 | 0 | 0 | 0 |
| V357/358 | NA | 2 | 0 | 0 | 0 | 0 |
| V359/360 | NA | 2 | 0 | 0 | 0 | 0 |
| V361/362 | NA | 2 | 0 | 0 | 0 | 0 |
| V363 | NA | 2 | 0 | 0 | 0 | 0 |
| V364 | NA | 2 | 0 | 0 | 0 | 0 |
| V365 | NA | 2 | 0 | 0 | 0 | 0 |
| V366 | NA | 2 | 0 | 0 | 0 | 0 |
| V367/368 | NA | 2 | 0 | 0 | 0 | 0 |
| V369/370 | NA | 2 | 0 | 0 | 0 | 0 |
| V371/372 | NA | 2 | 0 | 0 | 0 | 0 |
| V373/374 | NA | 2 | 0 | 0 | 0 | 0 |
| V375/376 | NA | 2 | 0 | 0 | 0 | 0 |
| V377/378 | NA | 2 | 0 | 0 | 0 | 0 |
| V379/380 | NA | 2 | 0 | 0 | 0 | 0 |
| V381/382 | NA | 2 | 0 | 0 | 0 | 0 |
| V383 | NA | 2 | 0 | 0 | 0 | 0 |
| V384 | NA | 2 | 0 | 0 | 0 | 0 |
| V385 | NA | 2 | 0 | 0 | 0 | 0 |
| V386 | NA | 2 | 0 | 0 | 0 | 0 |
| V387 | NA | 2 | 0 | 0 | 0 | 0 |
| V388 | NA | 2 | 0 | 0 | 0 | 0 |
| V389 | NA | 2 | 0 | 0 | 0 | 0 |
| V390 | NA | 2 | 0 | 0 | 0 | 0 |
| V391 | NA | 2 | 0 | 0 | 0 | 0 |
| V392 | NA | 2 | 0 | 0 | 0 | 0 |
| V393 | NA | 2 | 0 | 0 | 0 | 0 |
| V394 | NA | 2 | 0 | 0 | 0 | 0 |
| V395 | NA | 2 | 0 | 0 | 0 | 0 |
| V396 | NA | 2 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 27 Sep 2017, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 176 buildings; the table lists the first 20.
710 of 1936 construction stages are filed complete across 176 buildings. The stage furthest along is External plumbing and external plaster, at 99%.
Block A10%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Block A238%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 18% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Block A356%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 66% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 43% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Block B160%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 38% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Block B271%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 66% |
| Sanitary Fittings within the flats / premises | 43% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 85% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 48% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 36% |
Block B390%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Block B453%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 81% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 12% |
| Sanitary Fittings within the flats / premises | 8% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 54% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 23% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Block B554%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 20% |
| Sanitary Fittings within the flats / premises | 8% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 58% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 13% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Block B668%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 66% |
| Sanitary Fittings within the flats / premises | 47% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 63% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Block B6A0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Block B771%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 98% |
| Sanitary Fittings within the flats / premises | 78% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 31% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 5% |
Block B848%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 91% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 29% |
| Sanitary Fittings within the flats / premises | 8% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Block B936%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Block C191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Block C291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 99% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 98% |
Block C363%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 50% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 63% |
| Sanitary Fittings within the flats / premises | 58% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 41% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 5% |
Block C491%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 98% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Block C59%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Blocks C635%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 50% |
| Slabs of Super Structure | 27% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 1% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 5% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Block C759%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 50% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 74% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 7% |
Progress on shared amenities15
As on 27 Sep 2017, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 77% |
| Water Supply | Yes | 45% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 85% |
| Storm Water Drains | Yes | 59% |
| Landscaping & Tree Planting | Yes | 45% |
| Street Lighting | Yes | 70% |
| Community Buildings | Yes | 50% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 85% |
| Solid Waste Management And Disposal | Yes | 85% |
| Water conservation /Rain water harvesting | Yes | 40% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 45% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 70% |
| Open Parking | Yes | 50% |
Parking filed780
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Block A1 | 1 | 48 | 49 |
| Block A2 | 1 | 48 | 49 |
| Block A3 | 1 | 48 | 49 |
| Block B1 | 1 | 30 | 31 |
| Block B2 | 1 | 30 | 31 |
| Block B3 | 1 | 30 | 31 |
| Block B4 | 1 | 30 | 31 |
| Block B5 | 1 | 30 | 31 |
| Block B6 | 1 | 30 | 31 |
| Block B6A | 1 | 30 | 31 |
| Block B7 | 1 | 30 | 31 |
| Block B8 | 1 | 30 | 31 |
| Block B9 | 1 | 30 | 31 |
| Block C1 | 1 | 20 | 21 |
| Block C2 | 1 | 20 | 21 |
| Block C3 | 1 | 20 | 21 |
| Block C4 | 1 | 20 | 21 |
| Block C5 | 1 | 20 | 21 |
| Blocks C6 | 1 | 20 | 21 |
| Block C7 | 1 | 20 | 21 |
| Block C8 | 1 | 20 | 21 |
| Block C9 | 1 | 20 | 21 |
| Block C12A | 1 | 20 | 21 |
| Block C14 | 1 | 20 | 21 |
| Block D11 | 1 | 2 | 3 |
| Block D12 | 1 | 2 | 3 |
| Block D12A | 1 | 2 | 3 |
| Block B3A | 1 | 30 | 31 |
| Block C6A | 1 | 20 | 21 |
| R292 | 0 | 1 | 1 |
| V355/356 | 0 | 1 | 1 |
| V357/358 | 0 | 1 | 1 |
| V359/360 | 0 | 1 | 1 |
| V361/362 | 0 | 1 | 1 |
| V363 | 0 | 1 | 1 |
| V364 | 0 | 1 | 1 |
| V365 | 0 | 1 | 1 |
| V366 | 0 | 1 | 1 |
| V367/368 | 0 | 1 | 1 |
| V369/370 | 0 | 1 | 1 |
| V371/372 | 0 | 1 | 1 |
| V373/374 | 0 | 1 | 1 |
| V375/376 | 0 | 1 | 1 |
| V377/378 | 0 | 1 | 1 |
| V379/380 | 0 | 1 | 1 |
| V381/382 | 0 | 1 | 1 |
| V383 | 0 | 1 | 1 |
| V384 | 0 | 1 | 1 |
| V385 | 0 | 1 | 1 |
| V386 | 0 | 1 | 1 |
| V387 | 0 | 1 | 1 |
| V388 | 0 | 1 | 1 |
| V389 | 0 | 1 | 1 |
| V390 | 0 | 1 | 1 |
| V391 | 0 | 1 | 1 |
| V392 | 0 | 1 | 1 |
| V393 | 0 | 1 | 1 |
| V394 | 0 | 1 | 1 |
| V395 | 0 | 1 | 1 |
| V396 | 0 | 1 | 1 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Rajiv Nayan Srivastava |
| Partner | Role in project |
|---|---|
| SAHARA PRIME CITY LTD | - |
Complaints filed with MahaRERA29
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC004000000030190 | Sanjay Bansilal Paliwal | Sahara Prime City | 15/08/2020 |
| CC004000000030191 | Nitin Rameshchandra Gupta | Sahara Prime City Limited | 15/08/2020 |
| CC004000000030326 | Gopal Ramkaranji Mehadia | Sahara Prime City Limited | 03/02/2022 |
| CC004000000010082 | SAVEENA AGRAWAL | Sahara City Homes | 18/01/2019 |
| CC004000000030353 | Ajay Prabhakar Patekar | Sahara Prime City Limited | 21/04/2022 |
| CC004000000030393 | Naveen Kumar | Sahara City Homes | 03/06/2022 |
| CC004000000030394 | Sonika Kathuria | Sahara City Homes | 03/06/2022 |
| CC004000000030406 | SURESH SADASHIO PARATE | SAHARA CITY HOMES | 03/08/2022 |
| CC004000000030408 | Hari Easwaran | Sahara Prime City Limited | 30/07/2022 |
| CC004000000030421 | Kuldeep Kumar Sachdeva | sahara city homes nagpur | 09/09/2022 |
| CC004000000030422 | RAVINDER RAMLAL NARANG | SAHARA CITY HOMES LTD | 15/09/2022 |
| CC004000000030426 | HEMANT DOMAJI JAWADE | SAHARA CITY HOMES | 19/10/2022 |
| CC004000000030433 | RAJESH GOPICHAND LANJEWAR | SAHARA CITY HOMES | 28/11/2022 |
| CC004000000030434 | INDRAJEET SATYAJEET BANERJEE | SAHARA CITY HOMES | 28/11/2022 |
| CC004000000030470 | ROCHISH MADHUKARRAO THAOKAR | SAHARA CITY HOMES | 18/02/2023 |
| CC004000000030503 | PURUSHOTTAM TAMMALA | SAHARA CITY HOMES | 30/04/2023 |
| CC004000000050548 | Satyanrayan Champalal Taori | Sahara Prime City Limited | 21/09/2023 |
| CC004000000100612 | DEEPAK ANANTRAO RAWTAL | Sahara City Homes | 15/06/2024 |
| CC004000000100613 | DEVYANI DEEPAK RAWTAL | Sahara City Homes | 15/06/2024 |
| CC12401187 | SURESH SADASHIO PARATE | SAHARA PRIME CITY LTD | 20/12/2024 |
| CC12401191 | RAVINDER RAMLAL NARANG | SAHARA PRIME CITY LTD | 21/12/2024 |
| CC12401193 | HEMANT DOMAJI JAWADE | SAHARA PRIME CITY LTD | 21/12/2024 |
| CC12401194 | RAJESH GOPICHAND LANJEWAR | SAHARA PRIME CITY LTD | 21/12/2024 |
| CC12401195 | ROCHISH MADHUKARRAO THAOKAR | SAHARA PRIME CITY LTD | 21/12/2024 |
| CC12401198 | T. PURUSHOTTAM TAMMALA RAO | SAHARA PRIME CITY LTD | 21/12/2024 |
| CC12501926 | Rajkumar Through Legal Heirs Yogesh Agrawal Agrawal | SAHARA PRIME CITY LTD | 12/06/2025 |
| CC12501932 | Sajjankumar Agrawal | SAHARA PRIME CITY LTD | 12/06/2025 |
| CC12600877 | TUSHAR DNYANESHWAR SAKHARE | SAHARA PRIME CITY LTD | 17/02/2026 |
| CC12601890 | Ms Rashmi Bariar Krishna Kumar Bariar | SAHARA CITY HOMES | 31/03/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Sep 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Sep 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Sep 2017 - Commencement CertificateNot on the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
- Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Oct 2026
Documents filed27
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Layout approvalFile: Approved Layout.pdf | 27 Sep 2017 |
| Building plan approvalFile: Type A.pdf | 27 Sep 2017 |
| Building plan approvalFile: Type B.pdf | 27 Sep 2017 |
| Building plan approvalFile: Type C.pdf | 27 Sep 2017 |
| Building plan approvalFile: Type D.pdf | 27 Sep 2017 |
| Building plan approvalFile: Row House.pdf | 27 Sep 2017 |
| Building plan approvalFile: Semi Detached.pdf | 27 Sep 2017 |
| Building plan approvalFile: Bungalow.pdf | 27 Sep 2017 |
| Building plan approvalFile: Community Center.pdf | 27 Sep 2017 |
| PAN CardFile: SPCL PAN.pdf | 27 Sep 2017 |
| Copy of the legal title reportFile: Legal Title Report.pdf | 27 Sep 2017 |
| Details of encumbrancesFile: NEC.pdf | 27 Sep 2017 |
| Copy of Layout Approval (in case of layout)File: Approved Layout.pdf | 27 Sep 2017 |
| Building Plan Approval (IOD)File: Type A.pdf | 27 Sep 2017 |
| Building Plan Approval (IOD)File: Type B.pdf | 27 Sep 2017 |
| Building Plan Approval (IOD)File: Type C.pdf | 27 Sep 2017 |
| Building Plan Approval (IOD)File: Type D.pdf | 27 Sep 2017 |
| Building Plan Approval (IOD)File: Row House.pdf | 27 Sep 2017 |
| Building Plan Approval (IOD)File: Semi Detached.pdf | 27 Sep 2017 |
| Building Plan Approval (IOD)File: Bungalow.pdf | 27 Sep 2017 |
| Building Plan Approval (IOD)File: Community Center.pdf | 27 Sep 2017 |
| Declaration in FORM BFile: FORM B.pdf | 27 Sep 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate FORM 1.pdf | 27 Sep 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Form 2.pdf | 27 Sep 2017 |
| Certificates of CA (Form 3)File: CA Certificate Form 3.pdf | 27 Sep 2017 |
| Proforma of Allotment letterFile: Proforma of Allotment Letter.pdf | 27 Sep 2017 |
| Proforma of Allotment letterFile: Agreement for Sale.pdf | 27 Sep 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 27 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Sahara City Homes Phase 1 Nagpur on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Gawasi Manapur2,800+ in Nagpur
Kanher Nagri Developers
KANHER NAGRI DEVELOPERS
MAHALAXMI NAGAR 6
MAHALAXMI ESTATE
MAHALAXMI NAGAR 4
PADMALAXMI DEVELOPERS
Moreshwar park 4
PRASANNA PLANNERS
PRIME PLATINUM
UMAKANT VITTHAL MENDHE
MAULI NAGAR 8
MAULI INFRATECH
See every Nagpur project, with the district possession charts
Builder: SAHARA PRIME CITY LTD
SAHARA PRIME CITY LTD has 1 registration on MahaRERA, including Sahara City Homes Phase 1 Nagpur. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What are my rights if Sahara City Homes Phase 1 Nagpur is delayed beyond 30 Oct 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Sahara City Homes Phase 1 Nagpur?
The registered promoter entity is SAHARA PRIME CITY LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Sahara City Homes Phase 1 Nagpur?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Sahara City Homes Phase 1 Nagpur?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Sahara City Homes Phase 1 Nagpur?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Sahara City Homes Phase 1 Nagpur?
The professionals named in the filing: Architect: Rajiv Nayan Srivastava. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Sahara City Homes Phase 1 Nagpur?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.