Home / Browse projects / Raigarh, Maharashtra / SAGARIKA CO OP HSG SOCIETY LTD
SAGARIKA CO OP HSG SOCIETY LTD
By SAGARIKA CO OP HSG SOCIETY LTD
RG-MH-12678 · RERA P52000022792 · Last updated on MahaRERA portal: 6 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 2 complaints at MahaRERA
- Completion date moved by 35 months
- 2 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAGARIKA CO OP HSG SOCIETY LTD is a Residential / Group Housing project by SAGARIKA CO OP HSG SOCIETY LTD in Raigarh, Maharashtra, registered with MahaRERA as P52000022792 on 30 Oct 2019. Possession is promised by 30 Jul 2027. The completion date has moved by 35 months from the original filing. 44 of the 67 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.
At a glance
Project
- NameSAGARIKA CO OP HSG SOCIETY LTD
- TypeResidential / Group Housing
- Location
- SECTOR- 21
- NEW PANVEL (W)
- Panvel
- Raigarh
- 410206
- Pincode410206
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000022792
- ReraGenie IDRG-MH-12678
Builder
- NameSAGARIKA CO OP HSG SOCIETY LTD
- Entity typeSociety
- ChairpersonABDUL KADAR YAKUB SHAIKH
- SecretorySIBIL KANIYAMPADICKAL ITTYAVIRAH
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on30 Oct 2019
- Promised completion30 Jul 2027
- Revised completionRevised to 30 Jul 2027 (originally 5 Aug 2024)
- Buildings1 building record
- Documents filed151 files
Current status
Figures as on 6 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SAGARIKA CO OP HSG SOCIETY LTD | NA | 12 | 12 | 67 | 0 | 67 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 6 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 90%.
SAGARIKA CO OP HSG SOCIETY LTD: 75% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 72% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 16% |
Progress on shared amenities15
As on 6 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed88
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SAGARIKA CO OP HSG SOCIETY LTD | NA | Rs 15.16 cr | Rs 11.13 cr |
| - | NA | Rs 1.64 cr | Rs 16.40 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DESTINATION ARCHITECTURE INTERIOR DESIGNS |
| Engineer | SAMARTH AGARWAL |
| Chartered Accountant | DEEPAK NANDKUMAR GHADI |
| Chartered Accountant | ANKITA PAWAR & CO |
| Partner | Role in project |
|---|---|
| SAGARIKA CO OP HSG SOCIETY LTD | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterExplanatory note regarding the state of development works in the projects and reason for being not completing development works of the projects within the period declared in the declaration submitted in FORM ‘B’ at the time of making the application for the registration of SAGARIKA CO OP HSG SOCIETY LTD’ - As per the details mentioned at the time of registration of the project at the MahaRERA Website we had mentioned 05/08/2024 as the project completion date, we will not be able to complete the project due to various unavoidable reasons. Such as 1) After the impact of the pandemic, the increas
Reason as filed by the promoterImpact of Pandemic and Rising Construction Material Costs: The COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a significant and sustained increase in the prices of essential construction materials, including but not limited to cement, steel, copper, electrical components, plumbing materials, and paints. This escalation in material costs has resulted in severe financial strain, disrupting the supply chain and leading to delays in procurement and delivery of these materi
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12600786 | Ravindra Khulpe | SAGARIKA CO OP HSG SOCIETY LTD | 11/02/2026 |
| CC12600784 | Hanmant Gore | SAGARIKA CO OP HSG SOCIETY LTD | 11/02/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Sep 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Sep 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Oct 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jul 2027
Documents filed151
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 151 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1_ MARCH 26_ SAGARIKA CHSL.pdf | 6 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2_ MARCH 26_ SAGARIKA CHSL.pdf | 6 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3_ MARCH 26_ SAGARIKA CHSL.pdf | 6 Jul 2026 |
| Withdrawal Update Form 1File: FORM 1_DEC 25_ SAGARIKA CHSL.pdf | 22 Jun 2026 |
| Withdrawal Update Form 2File: FORM 2_DEC 25_ SAGARIKA CSHL.pdf | 22 Jun 2026 |
| Withdrawal Update Form 3File: FORM 3_ DEC 25_ SAGARIKA CHSL.pdf | 22 Jun 2026 |
| Withdrawal Update Form 1File: FORM 1_ SEP 25_ SAGARIKA CO OP HSG SOC (2).pdf | 13 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2_ SEP 25_ SAGARIKA CO OP HSG SOC.pdf | 13 Feb 2026 |
| Withdrawal Update Form 3File: FORM 3 _ SEP 25_ SAGARIKA CO OP HSG SOC.pdf | 13 Feb 2026 |
| Form 1File: FORM 1_ DEC 24_ SAGARIKA CHSL.pdf | 25 Jul 2025 |
| Form 2File: FORM 2_ DEC 24_ SAGARIKA CHSL.pdf | 25 Jul 2025 |
| Form 3File: FORM 3_ DEC 24_ SAGARIKA CHS.pdf | 25 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ DEC 24_ SARIKA CHS.pdf | 25 Jul 2025 |
| Form 1File: FORM 1_ MARCH 25_ SAGARIKA CHS.pdf | 25 Jul 2025 |
| Form 2File: FORM 2_ MARCH 25_ SAGARIKA CHS.pdf | 25 Jul 2025 |
| Form 3File: FORM 3_ MARCH 25_ SAGARIKA CHS.pdf | 25 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ MARCH 25_ SAGARIKA CHS.pdf | 25 Jul 2025 |
| Form 1File: FORM 1_ JUNE 25_ SAGARIKA CO OP HSG SOC.pdf | 25 Jul 2025 |
| Form 2File: FORM 2_ JUNE 25_ SAGARIKA CO OP HSG SOC.pdf | 25 Jul 2025 |
| Form 3File: FORM 3_ JUNE 25_ SAGARIKA CO OP HSG SOC_compressed.pdf | 25 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ JUNE 25_ SAGARIKA CO OP HOS SOC.pdf | 25 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_ june 24.pdf | 26 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_ sep 24.pdf | 26 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_ JUNE 24.pdf | 26 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_ SEP 24_compressed.pdf | 26 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_ JUNE 24.pdf | 26 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_ SEP 24.pdf | 26 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ JUNE 24.pdf | 26 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ SEP 24.pdf | 26 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24) (1).pdf | 9 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 15 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1).pdf | 18 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 13 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf | 18 Jul 2024 |
| Declaration in FORM BFile: FORM B.pdf | 17 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 14 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1).pdf | 17 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SDNLKA.pdf | 17 Jul 2024 |
| CERSAI detailsFile: DRAFTS_ON LETTERHEAD.pdf | 17 Jul 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: INDIVIDUAL DISCLOSURE.pdf | 17 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 KNSKLNVA.pdf | 17 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: INDIVIDUAL DISCLOSURE.pdf | 17 Jul 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A.pdf | 17 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-SAGARIKA_MAR 24.pdf | 7 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-SAGARIKA_MAR 24.pdf | 7 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A-SAGARIKA_23 24.pdf | 7 May 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD-SAGARIKA_MAR 24.pdf | 7 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-SAGARIKA_MAR 24_compressed.pdf | 7 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5-SAGARIKA_23 24.pdf | 7 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 4 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 4 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 4 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf | 4 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-SAGARIKA_SEP 23.pdf | 23 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-SAGARIKA_SEP 23.pdf | 23 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD-SAGARIKA_SEP 23.pdf | 23 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-SAGARIKA_SEP 23_compressed.pdf | 23 Nov 2023 |
| Building plan approvalFile: 1_compressed.pdf | 25 Oct 2023 |
| Building plan approvalFile: 2_compressed.pdf | 25 Oct 2023 |
| Building plan approvalFile: 3_compressed.pdf | 25 Oct 2023 |
| Building plan approvalFile: 4_compressed.pdf | 25 Oct 2023 |
| Building plan approvalFile: 5_compressed.pdf | 25 Oct 2023 |
| Building plan approvalFile: 6_compressed.pdf | 25 Oct 2023 |
| Building plan approvalFile: 7_compressed.pdf | 25 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 1_compressed.pdf | 25 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 2_compressed.pdf | 25 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 3_compressed.pdf | 25 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 4_compressed.pdf | 25 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 5_compressed.pdf | 25 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 6_compressed.pdf | 25 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 7_compressed.pdf | 25 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC_compressed.pdf | 25 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 2 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 2 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form_2A.pdf | 2 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form_2A.pdf | 2 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 2 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf | 2 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM_5_OF_SAGARIKA_CO-OP.pdf | 2 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM_1_ARCHITECT_S_CERTIFICATE_-_PLOT_G__31-03-2023_.pdf | 5 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form_2_SAGARIKA_EC_31-03-23.pdf | 5 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Sagarika_sold___unsold.pdf | 5 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3_RERA_compressed.pdf | 5 Jul 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 151 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SAGARIKA CO OP HSG SOCIETY LTD on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NEW PANVEL (W)5,900+ in Raigarh
Filed coordinates, straight-line distance. 345 registered projects within 2 km.
SHREE RAM DELTA
Shreenathji Enterprises
Brillante
Callista Realty Limited
SAI SUNCITY PHASE 3
Chariot Properties LLP
ANANDAM PHASE - II
TODAY GLOBAL HOMES
Maximus Residency Phase-I
Superb Maa Developers LLP
Sai Vrindavan Dham
KT & LK SWEET HOMES
See every Raigarh project, with the district possession charts
Builder: SAGARIKA CO OP HSG SOCIETY LTD
SAGARIKA CO OP HSG SOCIETY LTD has 1 registration on MahaRERA, including SAGARIKA CO OP HSG SOCIETY LTD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if SAGARIKA CO OP HSG SOCIETY LTD is delayed beyond 30 Jul 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAGARIKA CO OP HSG SOCIETY LTD?
The registered promoter entity is SAGARIKA CO OP HSG SOCIETY LTD, a society as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAGARIKA CO OP HSG SOCIETY LTD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SAGARIKA CO OP HSG SOCIETY LTD?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SAGARIKA CO OP HSG SOCIETY LTD?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAGARIKA CO OP HSG SOCIETY LTD?
The professionals named in the filing: Architect: DESTINATION ARCHITECTURE INTERIOR DESIGNS; Engineer: SAMARTH AGARWAL; Chartered Accountant: DEEPAK NANDKUMAR GHADI; Chartered Accountant: ANKITA PAWAR & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAGARIKA CO OP HSG SOCIETY LTD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback