ReraGenieLog inGet a buyer report

Home / Browse projects / Dakshina Kannada, Karnataka / SAGAR’S ISHA

Registration approved No litigation declared Residential/Group Housing project

SAGAR’S ISHA

By SAGAR PROPERTIES

RG-KA-15075 · RERA PRM/KA/RERA/1257/334/PR/261125/008276 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
May 2028Possession promisedno revision filed
5 of 15Construction stages donefurthest along: RCC or MS Framed structure, 98%
34 of 43Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 85 documents Report an error

SAGAR’S ISHA is a Residential/Group Housing project by SAGAR PROPERTIES in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/261125/008276 on 26 Nov 2025. Possession is promised by 31 May 2028. 9 of the 43 units on this registration are recorded sold or booked, and 5 of 15 construction stages are filed complete.

At a glance

Project

  • NameSAGAR’S ISHA
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1257/334/PR/261125/008276
  • ReraGenie IDRG-KA-15075

Builder

  • NameSAGAR PROPERTIES
  • Entity typePartnership Firm
  • GSTIN29AFDFS6563G1ZL
  • Authorized SignatoryGIRIDHAR SHETTY

Key dates

this monthRegisteredNov 2025PromisedMay 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on26 Nov 2025
  • Promised completion31 May 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed85 files

Current status

21%9 of 43 units booked
54.0%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAGAR’S ISHA---43043

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 15 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 98%.

Building: 59% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure98%
Masonry Construction85%
Plastering inside , outside & Ceiling60%
Joinery: Doors, Windows, Ventilators etc35%
Basic work of Water supply, Sanitary and Electrification30%
Dadoing, Skirting, Flooring, Tiles work (All types)30%
Railing and Grill fixing25%
Electrification, Water supply and Sanitary Finishing25%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes65%
LiftsYes25%
Corridor/LobbiesYes35%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes60%
TerraceYes40%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners2
LandownerVillageDistrict
GIRIDHAR SHETTY--
GIRIDHAR SHETTY--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 11.58 cr
Cost incurredRs 6.26 cr
Spent of the estimate54.05%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 11.58 crRs 5.10 cr
On-site expenditure-Salaries of workers-Rs 1.15 cr
Payment of taxes-Rs 18,674

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDHYAN ADAPPA
EngineerB G ADAPPA
Chartered AccountantB SUDESH KUMAR RAI

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed85

As listed on the registration, under the names the promoter filed them with; the newest 80 of 85 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/261125/008276 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: sagar rera_compressed.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM - 5.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM - 6.pdf15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 ca.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: FORM 5.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM 6.pdf14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: form 4 CA.pdf23 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: architect certificate.pdf23 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: engineer certificate.pdf23 Jan 2026
Stability certificateFile: stability certificate with valid lincece.pdf4 Nov 2025
RTC, survey 51/6(P)-
Mutation, survey 51/6(P)-
Encumbrance Certificate, survey 51/6(P)-
Conversion/Alienation Order, survey 51/6(P)-
Sale/Title/Gift Deed, survey 51/6(P)-
Khatha, survey 51/6(P)-
RTC, survey 51/6(P)-
Mutation, survey 51/6(P)-
Encumbrance Certificate, survey 51/6(P)-
Conversion/Alienation Order, survey 51/6(P)-
Sale/Title/Gift Deed, survey 51/6(P)-
Khatha, survey 51/6(P)-
Registration CertificateFile: Firm regsiatrtion.pdf-
GST CertificateFile: GST.pdf-
Partnership DeedFile: partnership deed.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: RERA Form 1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: form 2.pdf-
Certificate issued by Engineer Form 3File: form 3 engineer certificate.pdf-
TDR Purchase Deed / Sale DeedFile: TDR deed 1& 2.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: litigation affidavit.pdf-
Balance Sheet 2024 - 2025File: BS AY 2025-26.pdf-
Balance Sheet 2023 - 2024File: BS AY 2024-25.pdf-
Audited Profit and Loss Statement 2024 - 2025File: PL AY 2025-26.pdf-
Audited Profit and Loss Statement 2023 - 2024File: PL AY 2024-25.pdf-
Income Tax Return Acknowledgement 2024 - 2025File: ITR AY 2025-26.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: ITR AY 2024-25.pdf-
building licence-
Approved plan-
single layout-
stability certificate-
specification-
broucher_compressed-
proforma AOS-
proforma allottment letter-
form b-
affidvit 3(1)-
search report-
Mescom noc-
water noc-
UGD Noc-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
title deed 1-
title deed 2-
village map-
FAR-
TDR deed 1& 2-
TDR- BOTH-
TDR-UTILISATION CERTIFICATE - (BOTH)-
CDP plan-
mescom fee receipt-
carpet area statement-
Estimate cost by engineer-
Form 5-

How this compares with Dakshina Kannada

21%of this project is bookeddistrict median 38%
30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep SAGAR’S ISHA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

Builder: SAGAR PROPERTIES

SAGAR PROPERTIES has 1 registration on RERA Karnataka, including SAGAR’S ISHA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if SAGAR’S ISHA is delayed beyond 31 May 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SAGAR’S ISHA?

The registered promoter entity is SAGAR PROPERTIES, a partnership firm as per the filing. Its GSTIN 29AFDFS6563G1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SAGAR’S ISHA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SAGAR’S ISHA?

The professionals named in the filing: Architect: DHYAN ADAPPA; Engineer: B G ADAPPA; Chartered Accountant: B SUDESH KUMAR RAI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAGAR’S ISHA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAGAR’S ISHA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAGAR’S ISHA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.