Home / Browse projects / Mumbai Suburban, Maharashtra / Sagar C.H.S

Completed No litigation declared Residential / Group Housing project

Sagar C.H.S

By HIRANIMANTHAN BUILDERS AND DEVELOPERS

RG-MH-10916 · RERA P51800003741 · Last updated on MahaRERA portal: 6 Oct 2023

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 48 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
1Complaints at MahaRERAon this registration
Jump to the 98 documents Report an error

Sagar C.H.S is a Residential / Group Housing project by HIRANIMANTHAN BUILDERS AND DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003741 on 6 Aug 2017. The registration is recorded completed; possession was promised by 1 Dec 2023. The completion date has moved by 48 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSagar C.H.S
  • TypeResidential / Group Housing
  • Location
    • Nehru Nagar
    • Kurla
    • Mumbai Suburban
    • 400024
  • Pincode400024
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800003741
  • ReraGenie IDRG-MH-10916

Builder

  • NameHIRANIMANTHAN BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • PartnerDINESH SAVANT
  • Other registrations5 more →
  • Completed5 of 6
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2017First promiseDec 2019Revised toDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on6 Aug 2017
  • Promised completion1 Dec 2023
  • Revised completionRevised to 1 Dec 2023 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed98 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sagar Chs Bldg No 67NA200000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Sagar Chs Bldg No 67: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 6 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed43

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots43
Closed/Covered40
Open Space3

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area837 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
DINESH SAWANTKurlaMumbai Suburban

Approvals and building plan

Permissible FSI6654.45
Proposed, not sanctioned6,354 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHDFC Bank Borivali West Mumbai 400092

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKISHORE LOTLIKAR
EngineerNIRANJAN SHREEPAD LELE
PartnerRole in project
HIRANIMANTHAN BUILDERS AND DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800010105Dec 2019 → Jun 2023

Reason as filed by the promoterWe had completed entire development work of the project up to 16 floors as per the approved plans and shortly starting to give ‘Fit Out Possessions’ to the allottees. However we have not yet utilised full potential FSI of the project & for such balance FSI we got the sanctions from the authorities just now & plans are also amended accordingly. Our structure is also designed to that capacity to absorb this FSI load. We also got consent from allottees. Hence we require additional time for completing our balance FSI construction.

EXT51800003671Dec 2019 → Dec 2020

Reason as filed by the promoterIn view of the further approvals received for Proposed FSI/BUA, we need this time for construction of this proposed sanctioned FSI area.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000196738Deepak Nana PawarM/s. Hiranimanthan Builders and Developers20/04/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Oct 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 6 Oct 2023

Documents filed98

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 98 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FULL OC Sagar 67.pdf6 Oct 2023
Architect’s Certificate on Completion of Project (Form 4)File: BLDG NO - 67 BUILDING COMPLETION CERTIFICATE DATED - 01-08-2023.pdf6 Oct 2023
Other - FinanceFile: Bldg 67 HDFC Bank closure.pdf6 Oct 2023
Other - FinanceFile: Hirani Manthan - No Dues Letter - sagar.pdf9 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA-67-ARCH-JUNE23.pdf21 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG-RERA-67-MARCH23.pdf19 May 2023
Certificates of CA (Form 3)File: CA-RERA-67-MARCH23_compressed.pdf19 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA-ARCH-54-MARCH23.pdf26 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG-67-DEC22.pdf7 Feb 2023
Certificates of CA (Form 3)File: 67-CA-RERA-DEC22_compressed.pdf7 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH-54-DEC23.pdf24 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 54 - RERA Form 5 - Mar 22_compressed.pdf17 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 54 quality certificate rera.pdf13 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 67 ARCH Q2.pdf14 Oct 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Soc Regn Cert 67.pdf24 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA-67-ENG-JUNE22.pdf23 Aug 2022
Certificates of CA (Form 3)File: RERA-67-CA-JUNE22_compressed.pdf23 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA-67-ARCH-JUNE22.pdf27 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 54 quality certificate rera.pdf19 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BLDG_NO_-_67_RERA_CERTIFICATE_DATED_-_18-04-2022.pdf1 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 67-RERA-MARCH22n.pdf1 Jun 2022
Certificates of CA (Form 3)File: rera-67-ca-march22_compressed.pdf1 Jun 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BLDG_NO_-_67_RERA_CERTIFICATE_DATED_-_18-04-2022.pdf25 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: bldg no 67_compressed.pdf9 Mar 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OCC of bldg no67 NN dr 20-12-2021.pdf21 Dec 2021
Layout approvalFile: new paln 1_compressed.pdf22 Oct 2021
Copy of Layout Approval (in case of layout)File: new paln 1_compressed.pdf22 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: CC of bldg no 67 new.pdf22 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Q2 21-22.pdf22 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng-cer-67-sept21.pdf22 Oct 2021
Certificates of CA (Form 3)File: CA Q2 21-22.pdf22 Oct 2021
Details of encumbrancesFile: HMBD Encumbrance Certificate 67.pdf27 Sep 2021
Details of encumbrancesFile: HD Encumbrance Certificate 54.pdf22 Sep 2021
Declaration about Commencement CertificateFile: Declaration Format D Sagar CHSL.pdf29 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Q4 Final.pdf29 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA-67-ENG-FORM-2-MARCH21.pdf29 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM2A-67.pdf29 Jun 2021
Disclosure of sold/ booked inventoryFile: Disclosure Sagar CHSL_compressed.pdf29 Jun 2021
Certificates of CA (Form 3)File: RERA-67-CA-FORM-3-MARCH21_compressed.pdf29 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: form 5 18-19.pdf29 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA-67-CA-FORM5-19-20.pdf29 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA-67-CA-FORM5-19-20.pdf29 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BLDG_NO_-_67_RERA_CERTIFICATE_DATED_-_01-10-2020.pdf1 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA-67-9-20.pdf1 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA-67-9-20.pdf1 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA-67-9-20.pdf1 Mar 2021
Certificates of CA (Form 3)File: Full Certificate K67 Sept 20_compressed.pdf1 Mar 2021
Certificates of CA (Form 5)File: Full Certificate K67 Sept 20_compressed.pdf1 Mar 2021
Certificates of CA (Form 5)File: Full Certificate K67 Sept 20_compressed.pdf1 Mar 2021
Certificates of CA (Form 5)File: Full Certificate K67 Sept 20_compressed.pdf1 Mar 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BLDG_NO_-_67_RERA_CERTIFICATE_DATED_-_01-08-2020_compressed.pdf19 Oct 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eng-67-june.pdf19 Oct 2020
Certificates of CA (Form 3)File: 67 - HMBD - Rera Certificate - June 20_compressed.pdf19 Oct 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERT BLDG NO 67 MAR 2020.pdf24 Sep 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CERT 67 MAR 2020.pdf24 Sep 2020
Certificates of CA (Form 3)File: HMBD Bldg No 67 CA CERT MAR 2020.pdf24 Sep 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: bldg no 67.pdf10 Dec 2019
Certificates of CA (Form 5)File: Bldg 67 Form 5.pdf10 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH 67 SEPT 19.pdf19 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Bldg 67 Engineer Sept 19.pdf19 Nov 2019
Certificates of CA (Form 3)File: CA CERTIFICATE 67 Sept 2019.pdf19 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bldg no 67.pdf20 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Bldg no 67.pdf20 Aug 2019
Certificates of CA (Form 3)File: Bldg no 67.pdf20 Aug 2019
Details of encumbrancesFile: INDEX II- 67.pdf3 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA-67-17-4-19.pdf2 May 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Certificate 67.pdf2 May 2019
Certificates of CA (Form 3)File: bldg no 67.pdf2 May 2019
Certificates of CA (Form 5)File: BLDG NO 67.pdf1 Apr 2019
Details of encumbrancesFile: INDEX II- 67.pdf29 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH-67-DEC18.pdf29 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CER 67 DEC 18.pdf29 Jan 2019
Certificates of CA (Form 3)File: Rera Certificate - 67.pdf29 Jan 2019
Proforma of Allotment letterFile: Draft Agreement Bldg 67.pdf29 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 67.pdf15 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG-67-SEPT18.pdf15 Jan 2019
Certificates of CA (Form 3)File: Bldg no 67.pdf15 Jan 2019
Commencement Certificates / NA Order for plotted developmentFile: FULL CC.pdf31 Oct 2018
Certificates of CA (Form 3)File: CA CERTIFICATE-67-JULY18.pdf11 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 67-RERA-JUNE18 ARCH.pdf4 Aug 2018

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
MEGHDOOT CHSMEGHDOOT CHS BUIDLING NO 73 NEHRU NAGAR KURLA EAST MUMBAI 40002451CompletedNov 2010Late, Dec 2010
ANTARIKSH CHSANTARIKSH CHS BUILDING NO 43 NEHRU NAGAR KURLA EAST MUMBAI 40002475CompletedFeb 2008Late, Mar 2008

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 48 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sagar C.H.S on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nehru Nagar6,700+ in Mumbai Suburban

2 kmSagar C.H.SCompleted 114Lapsed / revoked 97Other 152Dot size: filed unitsN

Filed coordinates, straight-line distance. 363 registered projects within 2 km.

Builder: HIRANIMANTHAN BUILDERS AND DEVELOPERS

HIRANIMANTHAN BUILDERS AND DEVELOPERS has 6 registrations on MahaRERA, including SKYVIEW CHS and SHREE SIDDHI BLDG NO 69. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Sagar C.H.S is delayed beyond 1 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sagar C.H.S?

The registered promoter entity is HIRANIMANTHAN BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sagar C.H.S?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Sagar C.H.S?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Sagar C.H.S?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sagar C.H.S?

The professionals named in the filing: Architect: KISHORE LOTLIKAR; Engineer: NIRANJAN SHREEPAD LELE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sagar C.H.S?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sagar C.H.S. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sagar C.H.S to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.