Registration approved Residential/Group Housing project

SAFAL HOMES

By NIDHI LAND INFRASTRUCTURE DEVELOPERS PVT LTD

RG-KA-03534 · RERA PRM/KA/RERA/1257/334/PR/171031/001071

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Apr 2019Possession promisedmoved 12 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 47 documents Report an error

SAFAL HOMES is a Residential/Group Housing project by NIDHI LAND INFRASTRUCTURE DEVELOPERS PVT LTD in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/171031/001071 on 31 Oct 2017. Possession is promised by 30 Apr 2019. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameSAFAL HOMES
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/171031/001071
  • ReraGenie IDRG-KA-03534

Builder

  • NameNIDHI LAND INFRASTRUCTURE DEVELOPERS PVT LTD
  • Entity typeCompany
  • CINU45205KA2012PTC062255
  • Authorized SignatoryPRASHANTH K SANIL
  • DirectorSHARASCHANDRA SANIL
  • Other registrations1 more →
  • Declared earlier projects6 →

Key dates

this monthRegisteredOct 2017First promiseApr 2018Revised toApr 2019

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on31 Oct 2017
  • Promised completion30 Apr 2019
  • Revised completionRevised to 30 Apr 2019 (originally 30 Apr 2018)
  • Buildings1 building record
  • Documents filed47 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAFAL HOMES---24024

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyNoNot applicable
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area851 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 4.00 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1257/334/PR/220620/001071Apr 2018 → Apr 2019

Reason as filed by the promoterTransport strike - Delay in Delivery of Material

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed47

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/171031/001071 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: registration.jpeg-
Architect Certificate for Work Completion Schedule till DateFile: Architect Certificate FORM 5.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: form 6.pdf-
CA Certificate for Funds UtilizationFile: Form 4-CA.pdf-
Architect Certificate for Pending Work Completion Schedule.File: SFL extention Suprith.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Extension-MR.pdf-
CA Certificate for Funds required for Project CompletionFile: form 1.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
License1 (3 files merged)-
Plan - pdf-
Plan - pdf-
DEED OF SALE OF APARTMENT SFL-
AGREEMENT FOR SALE SAFAL-
Legal opinion PDF-
Plan - pdf-
Plan - pdf-
ALLOTMENT LETTER-
E Brochure PDF-
Fire NOC Pdf-
E Brochure PDF-
EC-
Katha-
Sale Deed-
Fire NOC Pdf-
Balance Sheet 2015 - 2016File: Balance sheet.jpg-
Balance Sheet 2014 - 2015File: balance sheet.jpg-
Balance Sheet 2013 - 2014File: Balance sheet.jpg-
Audited Profit and Loss Statement 2015 - 2016File: profit and loss .jpg-
Audited Profit and Loss Statement 2014 - 2015File: Profit and loss .jpg-
Audited Profit and Loss Statement 2013 - 2014File: Profit and Loss .jpg-
Director's Report 2015 - 2016File: Director 15-16.pdf-
Director's Report 2014 - 2015File: Director 14-15.pdf-
Director's Report 2013 - 2014File: Director 13-14.pdf-
Cash Flow Statement 2015 - 2016File: Cash flow .jpg-
Cash Flow Statement 2014 - 2015File: cash flow.jpg-
Auditor's Report 2015 - 2016File: Auditors Report.PDF-
Auditor's Report 2014 - 2015File: Auditor 14-15.pdf-
Auditor's Report 2013 - 2014File: Auditor 13-14.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: Income tax return.jpg-
Income Tax Return Acknowledgement 2014 - 2015File: Income tax return .jpg-
Income Tax Return Acknowledgement 2013 - 2014File: Income tax return.jpg-
Affidavit1-
Tower Excel SheetFile: PRM_KA_RERA_1257_334_PR_171031_001071.xlsx-
Occupancy CertificateFile: Completion certificate.pdf-
Completion certificate issued by the competent authorityFile: Completion certificate.pdf-
Registered Agreement of SaleFile: Sale Deed SFL final.pdf-
Registered conveyance deed for an individual unitFile: Sale Deed SFL final.pdf-

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
VRINDAVAN-Completed-No date filed
SAATHVIK-Completed-No date filed
JARDIN-Completed-No date filed

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one moved by 12 months
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep SAFAL HOMES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmSAFAL HOMESOther 13Dot size: filed unitsN

Filed coordinates, straight-line distance. 13 registered projects within 2 km.

Builder: NIDHI LAND INFRASTRUCTURE DEVELOPERS PVT LTD

Nidhi Land Infrastructure Developers pvt Ltd has 2 registrations on RERA Karnataka, including ROSARY COTTAGE and SAFAL HOMES. Its filings declare 6 earlier projects, 6 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if SAFAL HOMES is delayed beyond 30 Apr 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SAFAL HOMES?

The registered promoter entity is NIDHI LAND INFRASTRUCTURE DEVELOPERS PVT LTD, a company as per the filing. Its CIN U45205KA2012PTC062255 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SAFAL HOMES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in SAFAL HOMES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAFAL HOMES. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAFAL HOMES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.